Project overview

E8P02 Current project Beachline Expressway

The following reports track key metrics of your project as a whole, across all schedule updates.


This report consolidates successive schedule updates into a chronological record of scheduled completion, performance against the adjusted contract completion date, and period-to-period movement. Each row represents one schedule update at its data date.

To keep track of Adjusted Contract Compl. Date you must enter Days Added given to contractor in each uploaded schedule update, sometimes called weather days or time extension. You can do it at any time at Projects > [Edit] > Project Overview.

  • A. Schedule name: Identifies the specific schedule update.
  • B. Data date: The date on which the schedule data was recorded.
  • C. Scheduled Compl. Date: The projected completion date pulled from the schedule update.
  • D. Days Added: The number of "weather days" or time extension given to contractor in each schedule update. It must be manually added to the schedule at the time of import.
  • E. Adjusted Contract Compl. Date: The contract completion date adjusted for any time extension, see Days Added.
  • F. "Must Finish By" Date: The project-level Must Finish By date is imported from the schedule update. It is usually entered manually in P6 and may affect scheduling. The field is blank when the project has no Must Finish By date.
  • G. Cal Days Ahead / Behind: The number of calendar days the project is ahead or behind the adjusted contract completion date.
  • H. Periodic Change: The change in scheduled completion date from the previous update.
  • I. Total Float: The total float or slack time available in the schedule.

Schedule name
A
Data Date
B
Scheduled Compl. Date
C
Days Added
D
Adjusted Contract Compl. Date
E = C + D
Must Finish By Date
F
Cal Days Ahead / Behind
G = E - C
Periodic Change
H
Total Float
I
E8P02 Update No. 1118-Sep-1612-Aug-18--19-Jun-18---55
E8P02 Update No. 1216-Oct-1626-Jul-18-12-Aug-1828-Jul-1817d17d1
E8P02 Update No. 1313-Nov-1621-Jul-18-12-Aug-1802-Aug-1822d5d11
E8P02 Update No. 1418-Dec-1619-Aug-18-12-Aug-1804-Aug-18-7d-29d-16
E8P02 Update No. 1515-Jan-1717-Aug-18-12-Aug-1810-Aug-18-5d2d-8
E8P02 Update No. 1619-Feb-1704-Aug-18-12-Aug-1810-Aug-188d13d5
E8P02 Update No. 1719-Mar-1712-Aug-18-12-Aug-1812-Aug-18--8d-1
E8P02 Update No. 1816-Apr-1723-Aug-18-12-Aug-1812-Aug-18-11d-11d-12
E8P02 Update No. 1921-May-1725-Aug-18-12-Aug-1812-Aug-18-13d-2d-14
E8P02 Update No. 2011-Jun-1705-Sep-18-12-Aug-1820-Aug-18-24d-11d-17

The report compares milestone completion dates across successive schedule updates. It uses actual finish for completed milestones and scheduled finish otherwise. For changes of at least one day, the slippage indicator shows the difference in calendar days from the previous available date for that milestone.

A positive value such as +4 means the milestone date has slipped by 4 days (4 days lost). A negative value such as -8 means the milestone date has moved earlier by 8 days (8 days gained).

The MS Type column identifies the beginning or end of an activity or phase. A Start milestone marks the scheduled beginning; a Finish milestone marks planned completion. Use these dates to monitor project progress.

Activity IDActivity DescriptionMS TypeData Date
18-Sep-16
Data Date
16-Oct-16
Data Date
13-Nov-16
Data Date
18-Dec-16
Data Date
15-Jan-17
Data Date
19-Feb-17
Data Date
19-Mar-17
Data Date
16-Apr-17
Data Date
21-May-17
Data Date
11-Jun-17
GC-DP100PH MS - NTPStart19-Aug-1519-Aug-1519-Aug-1519-Aug-1519-Aug-1519-Aug-1519-Aug-1519-Aug-1519-Aug-1519-Aug-15
GC-GC100PH MS - NTP2 - Start Construction (35 days from NTP 1= Contract date )Start20-Sep-1520-Sep-1520-Sep-1520-Sep-1520-Sep-1520-Sep-1520-Sep-1520-Sep-1520-Sep-1520-Sep-15
GC-GCN110PH MS - Start Phase IA ConstructionStart20-Sep-1520-Sep-1520-Sep-1520-Sep-1520-Sep-1520-Sep-1520-Sep-1520-Sep-1520-Sep-1520-Sep-15
GC-GCN120PH MS - Start Phase IB ConstructionStart20-Nov-1520-Nov-1520-Nov-1520-Nov-1520-Nov-1520-Nov-1520-Nov-1520-Nov-1520-Nov-1520-Nov-15
GC-GCN130PH MS - Start Phase IIA ConstructionStart19-Sep-1619-Sep-1619-Sep-1619-Sep-1619-Sep-1619-Sep-1619-Sep-1619-Sep-1619-Sep-1619-Sep-16
GC-GCN140PH MS - Start Phase IIB ConstructionStart05-Dec-1604-Oct-16 (-62)04-Oct-1604-Oct-1604-Oct-1604-Oct-1604-Oct-1604-Oct-1604-Oct-1604-Oct-16
GC-GCN150PH MS - Start Phase IIC ConstructionStart10-Mar-1730-Mar-17 (+20)06-Feb-17 (-51)16-Feb-17 (+9)06-Mar-17 (+18)20-Mar-17 (+13)20-Mar-1717-Apr-17 (+28)22-May-17 (+35)12-Jun-17 (+21)
GC-GCN160PH MS - Start Phase IV ConstructionStart22-Feb-1806-Feb-18 (-16)01-Feb-18 (-5)01-Mar-18 (+28)27-Feb-18 (-2)14-Feb-18 (-13)22-Feb-18 (+8)05-Mar-18 (+11)07-Mar-18 (+2)16-Mar-18 (+9)
GC-GCN170PH MS - Start Phase IIIB ConstructionStart25-Apr-1715-May-17 (+20)09-Jun-17 (+25)21-Jun-17 (+11)30-Jun-17 (+8)04-Aug-17 (+35)15-Aug-17 (+11)14-Aug-17 (-1)05-Sep-17 (+22)14-Sep-17 (+9)
GC-GCN180PH MS - Start Phase IIIC ConstructionStart20-Sep-1710-Oct-17 (+20)01-Sep-17 (-38)14-Sep-17 (+12)25-Sep-17 (+10)31-Oct-17 (+36)07-Nov-17 (+7)06-Nov-17 (-1)30-Nov-17 (+24)11-Dec-17 (+11)
GC-GCN190PH MS - Start Phase IID ConstructionStart24-May-1701-Jun-17 (+8)21-Jun-17 (+19)08-Jun-17 (-12)09-Jun-1714-Jul-17 (+35)11-Aug-17 (+28)29-Jun-17 (-42)03-Aug-17 (+35)24-Aug-17 (+21)
GC-GCN200PH MS - Start Phase IIIA ConstructionStart24-Feb-1716-Mar-17 (+20)07-Mar-17 (-9)06-Apr-17 (+30)02-May-17 (+26)14-Mar-17 (-49)21-Mar-17 (+7)17-Apr-17 (+27)22-May-17 (+35)12-Jun-17 (+21)
GC-DP110PH MS - Project CompletionFinish12-Aug-1826-Jul-18 (-17)21-Jul-18 (-5)19-Aug-18 (+29)17-Aug-18 (-2)04-Aug-18 (-13)12-Aug-18 (+8)23-Aug-18 (+11)25-Aug-18 (+2)05-Sep-18 (+11)
GC-GC110PH MS - Substantial CompletionFinish03-Aug-1818-Jul-18 (-16)13-Jul-18 (-5)10-Aug-18 (+28)08-Aug-18 (-2)31-Jul-18 (-7)03-Aug-18 (+2)14-Aug-18 (+11)16-Aug-18 (+2)25-Aug-18 (+9)