The following reports track key metrics of your project as a whole, across all schedule updates.
This table provides a comprehensive view of the project's progress over time by consolidating data from all schedule updates. Each row represents a snapshot of the projec's schedule at a specific date, allowing you to track changes and trends in the projected completion date, contract compliance, and overall timeline performance.
To keep track of Adjusted Contract Compl. Date you must enter Days Added given to contractor in each uploaded schedule update, sometimes called weather days or time extension. You can do it at any time at Projects > [Edit] > Project Overview.
Schedule name A |
Data Date B |
Scheduled Compl. Date C |
Days Added D |
Adjusted Contract Compl. Date E = C + D |
Must Finish By Date F |
Cal Days Ahead / Behind G = E - C |
Periodic Change H |
Total Float I |
---|---|---|---|---|---|---|---|---|
E8P02 Update No. 11 | 18-Sep-16 | 12-Aug-18 | - | - | 19-Jun-18 | - | - | -55 |
E8P02 Update No. 12 | 16-Oct-16 | 26-Jul-18 | - | 12-Aug-18 | 28-Jul-18 | 17d | 17d | 1 |
E8P02 Update No. 13 | 13-Nov-16 | 21-Jul-18 | - | 12-Aug-18 | 02-Aug-18 | 22d | 5d | 11 |
E8P02 Update No. 14 | 18-Dec-16 | 19-Aug-18 | - | 12-Aug-18 | 04-Aug-18 | -7d | -29d | -16 |
E8P02 Update No. 15 | 15-Jan-17 | 17-Aug-18 | - | 12-Aug-18 | 10-Aug-18 | -5d | 2d | -8 |
E8P02 Update No. 16 | 19-Feb-17 | 04-Aug-18 | - | 12-Aug-18 | 10-Aug-18 | 8d | 13d | 5 |
E8P02 Update No. 17 | 19-Mar-17 | 12-Aug-18 | - | 12-Aug-18 | 12-Aug-18 | - | -8d | -1 |
E8P02 Update No. 18 | 16-Apr-17 | 23-Aug-18 | - | 12-Aug-18 | 12-Aug-18 | -11d | -11d | -12 |
E8P02 Update No. 19 | 21-May-17 | 25-Aug-18 | - | 12-Aug-18 | 12-Aug-18 | -13d | -2d | -14 |
E8P02 Update No. 20 | 11-Jun-17 | 05-Sep-18 | - | 12-Aug-18 | 20-Aug-18 | -24d | -11d | -17 |
E8P02 Update No. 21 | 16-Jul-17 | 27-Sep-18 | - | 12-Aug-18 | 31-Aug-18 | -46d | -22d | -28 |
E8P02 Update No. 22 | 20-Aug-17 | 13-Oct-18 | - | 12-Aug-18 | 13-Oct-18 | -62d | -16d | -1 |
E8P02 Update No. 23 | 17-Sep-17 | 31-Oct-18 | - | 12-Aug-18 | 01-Oct-18 | -80d | -18d | -31 |
E8P02 Update No. 24 | 15-Oct-17 | 11-Nov-18 | - | 12-Aug-18 | 01-Nov-18 | -91d | -11d | -11 |
E8P02 Update No. 24 | 15-Oct-17 | 11-Nov-18 | - | 12-Aug-18 | 01-Nov-18 | -91d | - | -11 |
E8P02 Update No. 26 | 17-Dec-17 | 15-Nov-18 | - | 12-Aug-18 | 07-Nov-18 | -95d | -4d | -9 |
This
table aggregates project milestones across successive schedule updates
and compares their completion dates to reveal improvements or delays.
For every milestone, the table displays its computed completion
date along with a time slippage indicator. This indicator is calculated
by comparing the current
milestone's computed date with that from the previous schedule
update.
A positive value like +4 means that the milestone's projected completion
has been
delayed or slipped by an additional 4 days relative to
the previous update (4 days lost). Conversely, a negative value - for
example, –8 indicates that the
milestone has been moved forward and gained 8 days
compared to the last update.
MS Type column indicates whether a milestone represents the
beginning or the end of an activity or phase. A Start milestone
marks the scheduled
commencement, while a Finish milestone signals the planned
completion, serving as key indicators for monitoring and managing project progress.
Activity ID | Activity Description | MS Type | Data Date 18-Sep-16 |
Data Date 16-Oct-16 |
Data Date 13-Nov-16 |
Data Date 18-Dec-16 |
Data Date 15-Jan-17 |
Data Date 19-Feb-17 |
Data Date 19-Mar-17 |
Data Date 16-Apr-17 |
Data Date 21-May-17 |
Data Date 11-Jun-17 |
Data Date 16-Jul-17 |
Data Date 20-Aug-17 |
Data Date 17-Sep-17 |
Data Date 15-Oct-17 |
Data Date 17-Dec-17 |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
GC-DP100 | PH MS - NTP | Start | 19-Aug-15 | 19-Aug-15 | 19-Aug-15 | 19-Aug-15 | 19-Aug-15 | 19-Aug-15 | 19-Aug-15 | 19-Aug-15 | 19-Aug-15 | 19-Aug-15 | 19-Aug-15 | 19-Aug-15 | 19-Aug-15 | 19-Aug-15 | 19-Aug-15 |
GC-GC100 | PH MS - NTP2 - Start Construction (35 days from NTP 1= Contract date ) | Start | 20-Sep-15 | 20-Sep-15 | 20-Sep-15 | 20-Sep-15 | 20-Sep-15 | 20-Sep-15 | 20-Sep-15 | 20-Sep-15 | 20-Sep-15 | 20-Sep-15 | 20-Sep-15 | 20-Sep-15 | 20-Sep-15 | 20-Sep-15 | 20-Sep-15 |
GC-GCN110 | PH MS - Start Phase IA Construction | Start | 20-Sep-15 | 20-Sep-15 | 20-Sep-15 | 20-Sep-15 | 20-Sep-15 | 20-Sep-15 | 20-Sep-15 | 20-Sep-15 | 20-Sep-15 | 20-Sep-15 | 20-Sep-15 | 20-Sep-15 | 20-Sep-15 | 20-Sep-15 | 20-Sep-15 |
GC-GCN120 | PH MS - Start Phase IB Construction | Start | 20-Nov-15 | 20-Nov-15 | 20-Nov-15 | 20-Nov-15 | 20-Nov-15 | 20-Nov-15 | 20-Nov-15 | 20-Nov-15 | 20-Nov-15 | 20-Nov-15 | 20-Nov-15 | 20-Nov-15 | 20-Nov-15 | 20-Nov-15 | 20-Nov-15 |
GC-GCN130 | PH MS - Start Phase IIA Construction | Start | 19-Sep-16 | 19-Sep-16 | 19-Sep-16 | 19-Sep-16 | 19-Sep-16 | 19-Sep-16 | 19-Sep-16 | 19-Sep-16 | 19-Sep-16 | 19-Sep-16 | 19-Sep-16 | 19-Sep-16 | 19-Sep-16 | 19-Sep-16 | 19-Sep-16 |
GC-GCN140 | PH MS - Start Phase IIB Construction | Start | 05-Dec-16 | 04-Oct-16 (-62) | 04-Oct-16 | 04-Oct-16 | 04-Oct-16 | 04-Oct-16 | 04-Oct-16 | 04-Oct-16 | 04-Oct-16 | 04-Oct-16 | 04-Oct-16 | 04-Oct-16 | 04-Oct-16 | 04-Oct-16 | 04-Oct-16 |
GC-GCN150 | PH MS - Start Phase IIC Construction | Start | 10-Mar-17 | 30-Mar-17 (+20) | 06-Feb-17 (-51) | 16-Feb-17 (+9) | 06-Mar-17 (+18) | 20-Mar-17 (+13) | 20-Mar-17 | 17-Apr-17 (+28) | 22-May-17 (+35) | 12-Jun-17 (+21) | 17-Jul-17 (+35) | 21-Aug-17 (+35) | 18-Sep-17 (+28) | 16-Oct-17 | 18-Dec-17 (+63) |
GC-GCN160 | PH MS - Start Phase IV Construction | Start | 22-Feb-18 | 06-Feb-18 (-16) | 01-Feb-18 (-5) | 01-Mar-18 (+28) | 27-Feb-18 (-2) | 14-Feb-18 (-13) | 22-Feb-18 (+8) | 05-Mar-18 (+11) | 07-Mar-18 (+2) | 16-Mar-18 (+9) | 09-Apr-18 (+24) | 24-Apr-18 (+15) | 10-May-18 (+16) | 23-May-18 | 25-May-18 (+2) |
GC-GCN170 | PH MS - Start Phase IIIB Construction | Start | 25-Apr-17 | 15-May-17 (+20) | 09-Jun-17 (+25) | 21-Jun-17 (+11) | 30-Jun-17 (+8) | 04-Aug-17 (+35) | 15-Aug-17 (+11) | 14-Aug-17 (-1) | 05-Sep-17 (+22) | 14-Sep-17 (+9) | 22-Sep-17 (+8) | 24-Oct-17 (+32) | 16-Nov-17 (+22) | 12-Dec-17 | 22-Jan-18 (+40) |
GC-GCN180 | PH MS - Start Phase IIIC Construction | Start | 20-Sep-17 | 10-Oct-17 (+20) | 01-Sep-17 (-38) | 14-Sep-17 (+12) | 25-Sep-17 (+10) | 31-Oct-17 (+36) | 07-Nov-17 (+7) | 06-Nov-17 (-1) | 30-Nov-17 (+24) | 11-Dec-17 (+11) | 19-Dec-17 (+8) | 08-Jan-18 (+20) | 31-Jan-18 (+22) | 22-Feb-18 | 09-Mar-18 (+14) |
GC-GCN190 | PH MS - Start Phase IID Construction | Start | 24-May-17 | 01-Jun-17 (+8) | 21-Jun-17 (+19) | 08-Jun-17 (-12) | 09-Jun-17 | 14-Jul-17 (+35) | 11-Aug-17 (+28) | 29-Jun-17 (-42) | 03-Aug-17 (+35) | 24-Aug-17 (+21) | 28-Sep-17 (+35) | 02-Nov-17 (+35) | 09-Nov-17 (+7) | 11-Dec-17 | 25-Jan-18 (+45) |
GC-GCN200 | PH MS - Start Phase IIIA Construction | Start | 24-Feb-17 | 16-Mar-17 (+20) | 07-Mar-17 (-9) | 06-Apr-17 (+30) | 02-May-17 (+26) | 14-Mar-17 (-49) | 21-Mar-17 (+7) | 17-Apr-17 (+27) | 22-May-17 (+35) | 12-Jun-17 (+21) | 17-Jul-17 (+35) | 21-Aug-17 (+35) | 18-Sep-17 (+28) | 16-Oct-17 | 18-Dec-17 (+63) |
GC-DP110 | PH MS - Project Completion | Finish | 12-Aug-18 | 26-Jul-18 (-17) | 21-Jul-18 (-5) | 19-Aug-18 (+29) | 17-Aug-18 (-2) | 04-Aug-18 (-13) | 12-Aug-18 (+8) | 23-Aug-18 (+11) | 25-Aug-18 (+2) | 05-Sep-18 (+11) | 27-Sep-18 (+22) | 13-Oct-18 (+16) | 31-Oct-18 (+18) | 11-Nov-18 | 15-Nov-18 (+4) |
GC-GC110 | PH MS - Substantial Completion | Finish | 03-Aug-18 | 18-Jul-18 (-16) | 13-Jul-18 (-5) | 10-Aug-18 (+28) | 08-Aug-18 (-2) | 31-Jul-18 (-7) | 03-Aug-18 (+2) | 14-Aug-18 (+11) | 16-Aug-18 (+2) | 25-Aug-18 (+9) | 19-Sep-18 (+25) | 04-Oct-18 (+14) | 20-Oct-18 (+16) | 02-Nov-18 | 06-Nov-18 (+4) |