Open ends and logic
Find activities with missing predecessors or successors and inspect relationship lag that can conceal or distort the driving sequence.
Browser-based schedule analysis software
Review a P6 XER schedule for exported longest-path status, missing logic, constraints, float, out-of-sequence progress, resources, calendars, milestones, and dates that do not match the data date. Keep successive updates in one project record to analyze schedule change across the full duration of the project.
What the schedule analyzer reviews
Schedule Tracker reads native XER activity, relationship, calendar, resource, and project data. It does not edit the source file or recalculate the CPM network. Each finding connects summary metrics to the underlying schedule evidence.
Find activities with missing predecessors or successors and inspect relationship lag that can conceal or distort the driving sequence.
Review P6 longest-path status, activities at zero or negative total float, and the dates associated with each result.
Surface constrained activities and actual start or finish dates recorded beyond the schedule data date.
Identify work performed outside the planned predecessor-successor sequence and review the affected logic.
List project milestones by WBS, highlight negative float, and keep contractual and intermediate dates visible.
Find duplicate activity descriptions and inspect actual dates, original durations, calendars, and task-level schedule fields.
More than activity dates
A schedule can look healthy at the activity level while still carrying unrealistic working time, resource demand, or cost assumptions. Schedule Tracker exposes the supporting data needed for a broader review.
Available analysis reports
Frequently asked questions
Schedule analysis software reviews schedules created in a planning system such as Primavera P6. Schedule Tracker reads exported XER data to organize schedule-quality checks and supporting activity evidence without editing the source file or replacing P6.
Schedule Tracker reviews CPM data including open ends, relationship lag, constraints, negative float, critical and longest paths, future actual dates, out-of-sequence progress, calendars, resources, costs, and milestones.
No. Upload an XER export through a modern web browser. Schedule Tracker does not require a direct P6 database connection or a Windows-only desktop installation.
Schedule Tracker supports XER exports created by Primavera P6 version 7.0 or newer. The project should be scheduled in P6 before export so its calculated dates are available for analysis.
Schedule Tracker reports all 14 points with measured results, thresholds, and supporting findings where the required evidence is available. The recalculation-dependent Critical Path Test is marked not evaluated rather than treated as a pass. Results are diagnostic schedule-quality findings, not a certification or contractual compliance determination.
Analyze the schedule you already have