Activity changes
Find activities added or deleted, descriptions revised, original durations changed, and actual start or finish dates added.
Primavera P6 schedule comparison
Compare baseline, prior, and current Primavera P6 schedules without reading a field-by-field change dump. Focus on the activity, logic, duration, float, calendar, and longest-path changes that can alter the completion forecast.
Changes organized by meaning
Schedule Tracker groups differences into focused reports. Reviewers can distinguish normal progress from changes to scope, sequencing, logic, duration, calendars, and the activities driving project completion.
Find activities added or deleted, descriptions revised, original durations changed, and actual start or finish dates added.
Review predecessor and successor relationships added or deleted, including relationship type and lag details.
Identify activities assigned to a different calendar between schedule versions.
Find activities that became critical and compare their previous and current total float.
Compare percent complete, actual dates, original versus actual duration, and activities that missed planned dates.
Copy focused tables into schedule narratives, progress reports, meeting notes, and review correspondence.
Driving sequence visibility
A completion date can remain unchanged while the activities driving that date move elsewhere in the schedule. The Longest Path Comparison shows activities newly entering the path, activities leaving it, their dates, and total float.
Comparison report catalog
Frequently asked questions
Yes. Import the baseline and current XER files into the same Schedule Tracker project, then select the two schedule versions to compare.
Reports identify activities and relationships added or deleted, description changes, original-duration changes, calendar changes, lag changes, new actual dates, activities becoming critical, and longest-path movement.
Yes. The Longest Path Comparison shows activities entering or leaving the driving sequence together with their dates and total float.
Yes. A project can preserve successive XER updates so you can compare selected periods and review milestone, progress, cost, and completion trends across the project history.
Replace the change dump