Schedule analysis

E8P02 Current project Beachline Expressway

Current schedule: E8P02 Update No. 20

Back Schedule Metrics

Beachline Update#20 DD June 11 TD June 15

  • 534Not started activities
  • 95In progress activities
  • 583Completed activities
  • 97 Critical activities
  • 42 Activities on longest path
  • 0 Activities with constraint
  • 0 Activities with unsatisfied constraint
  • 6 Available Calendars
  • 18 Project Resources
  • 14 Project Milestones

Activity Types

  • 2Finish Milestones
  • 12Start Milestones
  • 1198Task Dependent

Project Dates

  • Schedule-level Dates: are computed directly from the underlying activities, they reflect real-time changes and provide an updated view of the project timeline.
  • Project-level Dates: often set as part of the project baseline, they might not change as activities update and are used for tracking planned versus actual performance.
  • Must Finish By Date: a scheduling constraint that sets a hard deadline for a project, usually manually entered and is often left empty.
  • 17-Jun-17Last Save Date
  • 11-Jun-17Data Date
  • 20-Aug-18Must Finish By Date
  • 19-Aug-15Start Date (schedule-level)
  • 05-Sep-18Finish Date (schedule-level)
  • 1113 calendar daysProject Duration (schedule-level)
  • 19-Aug-15Start Date (project-level)
  • 05-Sep-18Finish Date (project-level)
  • 1113 calendar daysProject Duration (project-level)

Back Schedule Analysis

The Longest Path table identifies the critical sequence of activities that directly determines your project's overall duration. This table lists each activity's Start Date and Finish Date along with its Total Float - the available slack before a delay affects the project end date.

Highlighted in red are activities with negative total float.

Activity IDActivity DescriptionStart DateFinish DateTotal Float
IIBEBO-RW180PH IIB - Base (Universal - JYP) - EB Outside Widening - LR - (STA 320 to 332)01-May-1714-Jun-17-11
IIBEBO-AP140PH IIB - Asphalt - Structural - EB Outside Widening (Univ to JYP) - STA 320 to 33214-Jun-1720-Jun-17-11
IICR-TC130PH IIC - MOT Shift New Ramp Alignment - Ramp O20-Jun-1721-Jun-17-11
IICR-SP130PH IIC - Remove Ramp O Diversion - Construct EB Roadway Tie-In21-Jun-1713-Jul-17-11
IBEBM-TC220PH IIIA - Construct Diversion at Shingle Creek - WB Median Widening13-Jul-1703-Aug-17-11
IIIAR120PH IIIA - Construct Ramp Diversion P - Ramp P (Tie-in to SC Diversion)03-Aug-1710-Aug-17-11
IIIBWBO-ST190PH IIIB - Demo Traffic Rails - WB Outside Widening Area (Bridge over Shingle Creek)10-Aug-1718-Aug-17-11
IIIBWBO-ST650PH IIIB - Demo Bridge Deck - WB Outside Widening Area (Bridge over Shingle Creek)18-Aug-1728-Aug-17-11
IIIBWBO-ST660PH IIIB - Remove Beams - WB Outside Widening Area (Bridge over Shingle Creek)28-Aug-1730-Aug-17-11
IIIBWBO-ST670PH IIIB - Demo Pile Cap - WB Outside Widening Area (Bridge over Shingle Creek)30-Aug-1705-Sep-17-11
IIIBWBO-ST680PH IIIB - Extract Pile - WB Outside Widening Area (Bridge over Shingle Creek)05-Sep-1708-Sep-17-11
IIIBWBO-ST26PH IIIB - Production Pile (11-30)(Concrete) - WB Outside Widening Area (Bridge over Shingle Creek)08-Sep-1722-Sep-17-11
IIIBWBO-ST370PH IIIB - Wall Bent 1 - WB Outside Widening Area (Bridge over Shingle Creek)22-Sep-1704-Oct-17-11
IIIBWBO-ST400PH IIIB - End Bent 1 - WB Outside Widening Area (Bridge over Shingle Creek)04-Oct-1725-Oct-17-11
IIIBWBO-ST430PH IIIB - Wall Bent 4 - WB Outside Widening Area (Bridge over Shingle Creek)25-Oct-1706-Nov-17-11
IIIBWBO-ST480PH IIIB - End Bent 4 - WB Outside Widening Area (Bridge over Shingle Creek)06-Nov-1701-Dec-17-11
IIIBWBO-ST520PH IIIB - Curing for End Bent 4 - WB Outside Widening Area (Bridge over Shingle Creek)01-Dec-1708-Dec-17-17
IIIBWBO-ST560PH IIIB - Set Beams - WB Outside Widening Area (Bridge over Shingle Creek)08-Dec-1727-Dec-17-11
IIIBWBO-ST610PH IIIB - Superstructure Deck SIP & Start Rebar - WB Outside Widening Area (Bridge over Shingle Creek)27-Dec-1726-Jan-18-11
IIIBWBO-ST700PH IIIB - Superstructure Deck (Finish Rebar\Set Screed\Pour) - WB Outside Widening Area (Bridge over Shingle Creek)26-Jan-1816-Feb-18-11
IIIBWBO-ST120PH IIIB - Approach Slabs - WB Outside Widening Area (Bridge over Shingle Creek)16-Feb-1805-Mar-18-11
IIIBWBO-ST130PH IIIB - Lighting Conduit - WB Outside Widening Area (Bridge over Shingle Creek)06-Mar-1806-Mar-18-11
IIIBWBO-ST140PH IIIB - Traffic Railing (32") - WB Outside Widening Area (Bridge over Shingle Creek)07-Mar-1809-Mar-18-11
IIIBWBO-ST150PH IIIB - Grind and Groove - WB Outside Widening Area (Bridge over Shingle Creek)12-Mar-1815-Mar-18-11
GC-GCN160PH MS - Start Phase IV Construction16-Mar-18-11
IVEBM-TC100PH IV - Set Temp Traffic Barriers - EB Median Widening16-Mar-1821-Mar-18-11
IVEBM-GC100PH IV - Demo Temporary - EB Median Widening22-Mar-1828-Mar-18-11
IVEBM-W140PH IV - Median Wall - Grading for Station 1 (I4 to International Drive)29-Mar-1830-Mar-18-11
IVEBM-W150PH IV - Median Wall - FFP Footing/Stem for Station 1 (I4 to International Drive)02-Apr-1813-Apr-18-11
IVEBM-W160PH IV - Median Wall - Construct/ slip Top for Station 1 (I4 to International Drive)16-Apr-1820-Apr-18-11
IVEBM-W170PH IV - Median Wall - Grading for Station 2 (International Drive to Universal)23-Apr-1830-Apr-18-11
IVEBM-W180PH IV - Median Wall - FFP Footing/Stem for Station 2 (International Drive to Universal)01-May-1821-May-18-11
IVEBM-W190PH IV - Median Wall - Construct/ slip Top for Station 2 (International Drive to Universal)22-May-1829-May-18-11
IVEBM-W200PH IV - Median Wall - Grading for Station 3 (Universal to JYP)30-May-1812-Jun-18-11
IVEBM-W210PH IV - Median Wall - FFP Footing/Stem for Station 3 (Universal to JYP)13-Jun-1826-Jun-18-11
IVEBM-W220PH IV - Median Wall - Construct/ slip Top for Station 3 (Universal to JYP)27-Jun-1805-Jul-18-11
IVWBM-RW130PH IV - Grade for Station 3 (Universal to JYP) (B)06-Jul-1812-Jul-18-11
IVWBM-RW140PH IV - Stabilization for Station 3 (Universal to JYP) (A)13-Jul-1818-Jul-18-11
IVWBM-RW150PH IV - Base for Station 3 (Universal to JYP) (B)19-Jul-1831-Jul-18-11
IVWBM-AP100PH IV - Asphalt - Structural - WB Median Widening01-Aug-1806-Aug-18-11
GC-GCN210PH MS - Punch List/Acceptance07-Aug-1805-Sep-18-17
GC-DP110PH MS - Project Completion05-Sep-18-17

This table lists activities with zero or negative float - indicating no available slack before a delay impacts the overall project schedule. It helps you quickly pinpoint activities that require immediate attention to maintain project momentum.

Activity IDActivity DescriptionOn LPTotal Float
GC-DP110PH MS - Project CompletionYes-17
GC-GC110PH MS - Substantial CompletionNo-5
IIIAR120PH IIIA - Construct Ramp Diversion P - Ramp P (Tie-in to SC Diversion)Yes-11
NA-GC100TEC Install and TestNo-4
NA-GC110PH PW - ITS Testing and Commissioning - Critical AreasNo0
GC-GCN160PH MS - Start Phase IV ConstructionYes-11
GC-GCN210PH MS - Punch List/AcceptanceYes-17
TF-CO-004Precast ErectionNo-4
TF-CO-006FRP Conc. Roof Dec/cNo-4
TF-CO-009Const. Roof SystemNo-4
TF-CO-010FRP Conc. Pad (Generator)No-4
TF-CO-012Install Frames & DoorsNo-4
TF-CO-013Const. Screen Wall (Con.)No-4
TF-CO-016F+1 GeneratorNo-4
TF-CO-017F+1 Fuel TankNo-4
TF-CO-019Install Security SystemNo-4
TF-CO-020Install Lightning ProtectionNo-4
TF-CO-024Wall Treatments (Ply)No-4
TF-CO-026Cont. LightningNo-1
TF-CO-027Cont. HVACNo-4
TF-CO-030Pull WireNo-4
TF-CO-031Toll Facility Finishes and PunchlistNo-4
TF-CO-032Toll Facility CONo-4
IIAR-AP100PH IIB - Asphalt - Structural - Ramp ONo-11
IIAR-RW110PH IIB - Base - Ramp ONo-11
IIBR-ITS50PH IIB - Install ITS Poles (1-20)No0
IIBR-ITS60PH IIB - Install ITS Poles (21-41)No0
IIBR-ITS70PH IIB - Install CCTV's (1-8)No0
IIBR-ITS80PH IIB - Install CCTV's (9-16)No0
IIBR-ITS90PH IIB - Install CCTV's (17-22)No0
IICR-SP130PH IIC - Remove Ramp O Diversion - Construct EB Roadway Tie-InYes-11
IICR-TC130PH IIC - MOT Shift New Ramp Alignment - Ramp OYes-11
IVEBM-W140PH IV - Median Wall - Grading for Station 1 (I4 to International Drive)Yes-11
IVEBM-W150PH IV - Median Wall - FFP Footing/Stem for Station 1 (I4 to International Drive)Yes-11
IVEBM-W160PH IV - Median Wall - Construct/ slip Top for Station 1 (I4 to International Drive)Yes-11
IVEBM-W170PH IV - Median Wall - Grading for Station 2 (International Drive to Universal)Yes-11
IVEBM-W180PH IV - Median Wall - FFP Footing/Stem for Station 2 (International Drive to Universal)Yes-11
IVEBM-W190PH IV - Median Wall - Construct/ slip Top for Station 2 (International Drive to Universal)Yes-11
IVEBM-W200PH IV - Median Wall - Grading for Station 3 (Universal to JYP)Yes-11
IVEBM-W210PH IV - Median Wall - FFP Footing/Stem for Station 3 (Universal to JYP)Yes-11
IVEBM-W220PH IV - Median Wall - Construct/ slip Top for Station 3 (Universal to JYP)Yes-11
PRE-FA-030Fabricate and Deliver 042200 MasonryNo-4
PRE-PS-030Prepare and Submit 042200 MasonryNo-4
PRE-RA-030Review and Approve 042200 MasonryNo-4
IBEBM-TC220PH IIIA - Construct Diversion at Shingle Creek - WB Median WideningYes-11
IIIBR-ITS80PH IIIB - Install Conduit/Boxes (JYP to TPK)No0
IIIBR-ITS90PH IIIB - Install ITS Cabinets/HardwareNo0
IVEBM-AP100PH IV - Asphalt - Structural - EB Median WideningNo-10
IVEBM-GC100PH IV - Demo Temporary - EB Median WideningYes-11
IVEBM-TC100PH IV - Set Temp Traffic Barriers - EB Median WideningYes-11
IVEBM-TC110PH IV - Temp Striping for Phase - EB Median WideningNo-5
IVEBM-TC120PH IV - MOT Shift for Phase - EB Median WideningNo-5
IVEBO-AP100PH IV - Asphalt - Overbuild & Friction - EB Outside WideningNo-5
IVEBO-PM110PH IV - Pavement Markings (Final) - EB Outside WideningNo-5
IVWBM-AP100PH IV - Asphalt - Structural - WB Median WideningYes-11
IVWBM-RW130PH IV - Grade for Station 3 (Universal to JYP) (B)Yes-11
IVWBM-RW140PH IV - Stabilization for Station 3 (Universal to JYP) (A)Yes-11
IVWBM-RW150PH IV - Base for Station 3 (Universal to JYP) (B)Yes-11
IVWBM-RW260PH IV - Grade for Station 3 (Universal to JYP) (A)No-10
IVWBM-RW270PH IV - Stabilization for Station 3 (Universal to JYP) (A)No-10
IVWBM-RW280PH IV - Base for Station 3 (Universal to JYP)No-10
IVWBM-TC100PH IV - Set Temp Traffic Barriers - WB Median WideningNo-6
IVWBM-TC110PH IV - Temp Striping for Phase - WB Median WideningNo-4
IVWBM-TC120PH IV - MOT Shift for Phase - WB Median WideningNo-4
IVWBO-AP100PH IV - Asphalt - Overbuild & Friction - WB Outside Widening AreaNo-4
IVWBO-PM110PH IV - Pavement Markings (Final) - WB Outside Widening AreaNo-4
IIBEBO-AP140PH IIB - Asphalt - Structural - EB Outside Widening (Univ to JYP) - STA 320 to 332Yes-11
IIBEBO-RW180PH IIB - Base (Universal - JYP) - EB Outside Widening - LR - (STA 320 to 332)Yes-11
IIIBR-ITS100PH IIIB - Install Vehicle Detection Systems (1-11)No0
IIIBR-ITS110PH IIIB - Install Vehicle Detection Systems (12-22)No0
IIIBR-ITS130PH IIIB - Install Digital Message Signs (1-12)No0
IIIBR-ITS140PH IIIB - Install Digital Message Signs (13-23)No0
IIIBR-ITS150PH IIIB - Pull FOC (I-4 to International)No0
IIIBR-ITS160PH IIIB - Pull FOC ( International to Univ)No0
IIIBR-ITS170PH IIIB - Pull FOC (UNIV to JYP)No0
IIIBR-ITS180PH IIIB - Pull FOC (JYP to TPK)No0
IIIBR-ITS190PH IIIB - Splice/Terminate FOCNo0
IIIBWBO-ST26PH IIIB - Production Pile (11-30)(Concrete) - WB Outside Widening Area (Bridge over Shingle Creek)Yes-11
IIIBR-ITS1000PH IIIB - Install Conduit/Boxes (I-4 to International)No0
IIIBR-ITS1020PH IIIB - Install Conduit/Boxes (Univ to JYP)No0
IIIBWBO-ST120PH IIIB - Approach Slabs - WB Outside Widening Area (Bridge over Shingle Creek)Yes-11
IIIBWBO-ST130PH IIIB - Lighting Conduit - WB Outside Widening Area (Bridge over Shingle Creek)Yes-11
IIIBWBO-ST140PH IIIB - Traffic Railing (32") - WB Outside Widening Area (Bridge over Shingle Creek)Yes-11
IIIBWBO-ST150PH IIIB - Grind and Groove - WB Outside Widening Area (Bridge over Shingle Creek)Yes-11
IIIBWBO-ST190PH IIIB - Demo Traffic Rails - WB Outside Widening Area (Bridge over Shingle Creek)Yes-11
IIIBWBO-ST370PH IIIB - Wall Bent 1 - WB Outside Widening Area (Bridge over Shingle Creek)Yes-11
IIIBWBO-ST400PH IIIB - End Bent 1 - WB Outside Widening Area (Bridge over Shingle Creek)Yes-11
IIIBWBO-ST430PH IIIB - Wall Bent 4 - WB Outside Widening Area (Bridge over Shingle Creek)Yes-11
IIIBWBO-ST480PH IIIB - End Bent 4 - WB Outside Widening Area (Bridge over Shingle Creek)Yes-11
IIIBWBO-ST520PH IIIB - Curing for End Bent 4 - WB Outside Widening Area (Bridge over Shingle Creek)Yes-17
IIIBWBO-ST560PH IIIB - Set Beams - WB Outside Widening Area (Bridge over Shingle Creek)Yes-11
IIIBWBO-ST610PH IIIB - Superstructure Deck SIP & Start Rebar - WB Outside Widening Area (Bridge over Shingle Creek)Yes-11
IIIBWBO-ST650PH IIIB - Demo Bridge Deck - WB Outside Widening Area (Bridge over Shingle Creek)Yes-11
IIIBWBO-ST660PH IIIB - Remove Beams - WB Outside Widening Area (Bridge over Shingle Creek)Yes-11
IIIBWBO-ST670PH IIIB - Demo Pile Cap - WB Outside Widening Area (Bridge over Shingle Creek)Yes-11
IIIBWBO-ST680PH IIIB - Extract Pile - WB Outside Widening Area (Bridge over Shingle Creek)Yes-11
IIIBWBO-ST700PH IIIB - Superstructure Deck (Finish Rebar\Set Screed\Pour) - WB Outside Widening Area (Bridge over Shingle Creek)Yes-11

This table identifies activities that lack defined predecessor relationships. Missing predecessors can indicate gaps in the dependency chain, potentially compromising the accuracy of your schedule.

Activity IDActivity DescriptionOn LP
GC-DP100PH MS - NTPYes

This table identifies activities that lack defined successor relationships. Missing successors may signal gaps in the dependency chain, leading to potential scheduling inaccuracies and oversight of critical follow-up tasks.

Activity IDActivity DescriptionOn LP
GC-DP110PH MS - Project CompletionYes

Having unique and clear descriptions for each activity is essential for effective project tracking, resource allocation, and communication. Addressing this issue promptly is crucial to maintain clarity and efficiency in project execution.

Recommended actions: Review the activities with identical descriptions and update them with unique, specific descriptions showing phase, location or a category. This will help in distinguishing each activity clearly, improving tracking accuracy and communication, especially when it comes to a claim review process. Inform the project team of these updates to ensure everyone is aligned.

TotalActivity DescriptionActivity IDs
2PH IV - Stabilization for Station 3 (Universal to JYP) (A)IVWBM-RW140, IVWBM-RW270

Several activities were completed out-of-sequence. This table should be used as a tool to understand the impact of out-of-sequence work on the project schedule and to develop strategies to minimize disruptions in the future.

Out-of-sequence work can lead to inefficiencies, increased costs, and potential delays in subsequent activities. A small number of out-of-sequence activities is typically normal and can be expected in any project. However, a large number indicates that the contractor is either not following the schedule or not updating the progress timely. In such cases, it is essential to revisit the scheduling logic and see if it needs to be adjusted or revised.

Recommended actions: Meet with the contractor to review and discuss the reasons behind the out-of-sequence work for these activities and identify any patterns or recurring issues. Implement process improvements and communicate the importance of following the planned sequence to the project team. Adjust the project schedule if necessary and inform stakeholders of any changes to ensure alignment and transparency.

Activity IDActivity DescriptionOn LPAct start dateParent end date
GC-GC100PH MS - NTP2 - Start Construction (35 days from NTP 1= Contract date )Yes20-Sep-1511-Jun-17
GC-GCN100PH MS - Construction MobilizationYes19-Aug-1511-Jun-17
GC-GCN110PH MS - Start Phase IA ConstructionYes20-Sep-1511-Jun-17
GC-GCN120PH MS - Start Phase IB ConstructionYes20-Nov-1511-Jun-17
GC-GCN130PH MS - Start Phase IIA ConstructionNo19-Sep-1611-Jun-17
GC-GCN140PH MS - Start Phase IIB ConstructionNo04-Oct-1611-Jun-17
IAEBO-AP100PH IA - Overbuild Shoulder - EB Outside Widening (SR528)Yes20-Sep-1511-Jun-17
IAEBO-GC100PH IA - Set Erosion Control Devices - EB Outside WideningYes21-Sep-1511-Jun-17
IAEBO-GC110PH IA - Clear & Grub - EB Outside WideningNo22-Sep-1511-Jun-17
IAEBO-GC120PH IA - Drill Scuppers in Bridge (Shingle Creek) - EB Outside WideningYes08-Oct-1511-Jun-17
IAEBO-GC130PH IA - Clear & Grub - EB Outside Widening (I-4 to Ramp H)No22-Feb-1611-Jun-17
IAEBO-SP100PH IA - Jack & Bore 42" (Sta 351+00 near Duke energy access platform) - EB Outside Widening (SR528)No06-Jul-1611-Jun-17
IAEBO-SP110PH IA - Drainage (42") @ JYP Interchange - EB Outside Widening (SR528)No25-Jul-1611-Jun-17
IAEBO-TC100PH IA - Install Advance Sign & Traffic Control Devices - EB Outside WideningYes28-Sep-1511-Jun-17
IAEBO-TC110PH IA - Temp Striping for Phase IB - EB Outside Widening (SR528)Yes27-Sep-1511-Jun-17
IAEBO-W100PH IA - Noise/Sound Wall Prep Work (W-1) - EB Outside WideningNo04-Jan-1611-Jun-17
IAEBO-W110PH IA - Install Posts (1-101)- EB Outside WideningNo29-Apr-1611-Jun-17
IAEBO-W120PH IA - Install Posts (102- 203) - EB Outside WideningNo09-May-1611-Jun-17
IAEBO-W130PH IA - Noise/Sound Wall Prep Work (W-2) - EB Outside WideningNo22-Feb-1611-Jun-17
IAEBO-W140PH IA - Install Posts (204-305) - EB Outside WideningNo18-May-1611-Jun-17
IAEBO-W150PH IA - Install Posts (306- 409) - EB Outside WideningNo26-May-1611-Jun-17
IAEBO-W160PH IA - Install Panels (0-32000 SF) - EB Outside WideningNo27-Jun-1611-Jun-17
IAEBO-W170PH IA - Install Panels (32000-64000 SF) - EB Outside WideningNo29-Jun-1611-Jun-17
IAEBO-W180PH IA - Install Panels (64000-96000 SF)- EB Outside WideningNo05-Jul-1611-Jun-17
IAEBO-W190PH IA - Install Panels (96000-128000 SF)- EB Outside WideningNo08-Jul-1611-Jun-17
IAEBO-W200PH IA - Install Panels (128000-160000 SF) - EB Outside WideningNo12-Jul-1611-Jun-17
IAI-TC100PH IA - Set Temp Traffic Barriers - Interchanges Roads International DrNo21-Oct-1511-Jun-17
IAI-TC110PH IA - Set Temp Traffic Barriers - Interchanges Roads Universal AvnNo09-Nov-1511-Jun-17
IAI-TC120PH IA - Set Temp Traffic Barriers - Interchanges Roads John Young PKWNo17-Nov-1511-Jun-17
IAR-AP110PH IA - Mill & Resurface Transition (Ramp A)Yes25-Oct-1511-Jun-17
IAR-AP130PH IA - Over Build Shoulder- Ramp AYes26-Oct-1511-Jun-17
IAR-AP140PH IA - Over Build Shoulder - Ramp DYes20-Sep-1511-Jun-17
IAR-GC100PH IA - Guardrail Replacement (Ramp A)Yes25-Oct-1511-Jun-17
IAR-TC100PH IA - Close and Detour (Ramp A)Yes25-Oct-1511-Jun-17
IAR-TC120PH IA - Set Temp Traffic Barriers - Ramp AYes26-Oct-1511-Jun-17
IAR-TC130PH IA - Set Temp Traffic Barriers for Phase IB - WB Median WideningNo01-Nov-1511-Jun-17
IAR-TC140PH IA - Set Temp Traffic Barriers for Phase IB - EB Median WideningNo29-Oct-1511-Jun-17
IAWBO-AP100PH IA - Overbuild Shoulder - WB Outside Widening Area (SR528)Yes23-Sep-1511-Jun-17
IAWBO-EW100PH IA - Pond EXCAVATION (Shape 4A & 5A) - WB Outside Widening AreaNo26-Oct-1511-Jun-17
IAWBO-EW110PH IA - Embankment(Duke energy access platform & Poles) - WB Outside Widening AreaNo05-Oct-1511-Jun-17
IAWBO-GC100PH IA - Set Erosion Control Devices - WB Outside Widening AreaYes21-Sep-1511-Jun-17
IAWBO-GC110PH IA - Clear & Grub - WB Outside Widening AreaNo22-Sep-1511-Jun-17
IAWBO-GC120PH IA - Drill Scuppers in Bridge (Shingle Creek) - WB Outside Widening AreaYes13-Oct-1511-Jun-17
IAWBO-SP110PH IA - Drainage (42") @ JYP Interchange - WB Outside Widening Area (SR528)No10-Nov-1611-Jun-17
IAWBO-TC100PH IA - Install Advance Sign & Traffic Control Devices - WB Outside Widening AreaYes20-Sep-1511-Jun-17
IAWBO-TC110PH IA - Temp Striping for Phase IB - WB Outside Widening Area (SR528)Yes28-Sep-1511-Jun-17
IBEBM-AP100PH IB - Asphalt - Structural - EB Median Widening (I-4 to I-Drive)No02-Mar-1711-Jun-17
IBEBM-AP110PH IB - Asphalt - Structural - EB Median Widening (I-Drive to Univ)No06-Feb-1711-Jun-17
IBEBM-AP120PH IB - Asphalt - Structural - EB Median Widening (Univ to JYP)Yes23-Jan-1711-Jun-17
IBEBM-GC100PH IB - Median Clearing and Grubbing - EB Median WideningNo26-Oct-1511-Jun-17
IBEBM-RW110PH IB - Grade for Permanent Shoulder Construction (JYP-TRP) - EB Median WideningNo11-Jul-1611-Jun-17
IBEBM-RW111PH IB - Stabilization for Permanent Shoulder Construction (JYP-TRP) - EB Median WideningNo13-Jul-1611-Jun-17
IBEBM-RW220PH IB - Grade (I4-International Drive) - EB Median WideningNo06-Feb-1711-Jun-17
IBEBM-RW230PH IB - Grade (International Drive - Universal) - EB Median WideningNo30-Jan-1711-Jun-17
IBEBM-RW240PH IB - Grade (Universal - JYP) - EB Median WideningYes19-Dec-1611-Jun-17
IBEBM-RW250PH IB - Stabilization (I4-international Drive) - EB Median WideningNo17-Feb-1711-Jun-17
IBEBM-RW260PH IB - Stabilization (International Drive - Universal) - EB Median WideningNo08-Feb-1711-Jun-17
IBEBM-RW270PH IB - Stabilization (Universal - JYP) - EB Median WideningYes18-Jan-1711-Jun-17
IBEBM-RW280PH IB - Base (I4-International Drive) - EB Median WideningNo13-Jul-1611-Jun-17
IBEBM-RW290PH IB - Base (International Drive - Universal) - EB Median WideningNo08-Feb-1711-Jun-17
IBEBM-RW300PH IB - Base (Universal - JYP) - EB Median WideningYes18-Jan-1711-Jun-17
IBEBM-RW310PH IB - Guard Rail Removal - EB Median WideningYes10-Dec-1511-Jun-17
IBEBM-RW320PH IB - Base for Permanent Shoulder Construction (JYP-TRP) - EB Median WideningNo01-Nov-1616-Jun-17
IBEBM-RW330PH IB - Pavement for Permanent Shoulder Construction (JYP-TRP) - EB Median WideningNo17-Nov-1622-Jun-17
IBEBM-ST100PH IB - Construct Crane Access - EB Median Widening (Bridge over Shingle Creek)No05-Nov-1511-Jun-17
IBEBM-ST110PH IB - DemoTraffic Rail / End Bents - EB Median Widening (Bridge over Shingle Creek)No22-Nov-1511-Jun-17
IBEBM-ST120PH IB - Construct Crane Access - EB Median Widening (Bridge over John Young PKWY)No04-Dec-1511-Jun-17
IBEBM-ST130PH IB - Demo Traffic Rails - EB Median Widening (Bridge over John Young PKWY)No04-Jan-1611-Jun-17
IBEBM-ST140PH IB - Construct Crane Access - EB Median Widening (Bridge over International DR)No17-Mar-1611-Jun-17
IBEBM-ST150PH IB - Demo Traffic Rails - EB Median Widening (Bridge over International DR)No14-Mar-1611-Jun-17
IBEBM-ST160PH IB - Test Pile (Concrete) - EB Median Widening (Bridge over Shingle Creek)No20-Nov-1511-Jun-17
IBEBM-ST190PH IB - Production Pile (Concrete) - EB Median Widening (Bridge over Shingle Creek)No18-Jan-1611-Jun-17
IBEBM-ST200PH IB - Temp Sheet Pile - EB Median Widening (Bridge over International DR)No16-May-1611-Jun-17
IBEBM-ST210PH IB - Temp Sheet Pile - EB Median Widening (Bridge over John Young PKWY)No06-Mar-1611-Jun-17
IBEBM-ST220PH IB - Drive Production Pile (H Piles) - EB Median Widening (Bridge over John Young PKWY)No25-Jan-1611-Jun-17
IBEBM-ST230PH IB - Production Pile - EB Median Widening (Bridge over International DR)No28-Mar-1611-Jun-17
IBEBM-ST240PH IB - Construct Crane Access - EB Median Widening (Bridge over universal BLVD)No21-Feb-1611-Jun-17
IBEBM-ST250PH IB - Pier 2, (F/R/P)(Footer, Column & Pier Cap) - EB Median Widening (Bridge over International DR)No18-May-1611-Jun-17
IBEBM-ST260PH IB - Demo Traffic Rails - EB Median Widening (Bridge over universal BLVD)No29-Feb-1611-Jun-17
IBEBM-ST270PH IB - Test Pile - EB Median Widening (Bridge over universal BLVD)No10-Mar-1611-Jun-17
IBEBM-ST280PH IB - Temp Sheet Pile - EB Median Widening (Bridge over universal BLVD)No08-Jun-1611-Jun-17
IBEBM-ST290PH IB - Production Pile - EB Median Widening (Bridge over universal BLVD)No10-Mar-1611-Jun-17
IBEBM-ST300PH IB - Curing for Pier 2, (Footer, Column & Pier Cap) - EB Median Widening (Bridge over International DR)No27-Jul-1611-Jun-17
IBEBM-ST310PH IB - Removal of Concrete Forms for Pier 2, (Footer, Column & Pier Cap) - WB Median Widening (Bridge over InternationNo04-Aug-1611-Jun-17
IBEBM-ST320PH IB - Temp Sheet Pile Removal - EB Median Widening (Bridge over International DR)No25-Jul-1611-Jun-17
IBEBM-ST330PH IB - Wall Bent 1 - EB Median Widening (Bridge over International DR)No18-Apr-1611-Jun-17
IBEBM-ST340PH IB - Rip Rap Under Bridge - EB Median Widening (Bridge over Shingle Creek)No16-Feb-1611-Jun-17
IBEBM-ST350PH IB - Pier 2 & 3 (F/R/P)( Pile Cap) - EB Median Widening (Bridge over Shingle Creek)No29-Jan-1611-Jun-17
IBEBM-ST360PH IB - Pier 2, 3, 4(F/R/P) ( Pier Cap) - EB Median Widening (Bridge over John Young PKWY)No06-May-1611-Jun-17
IBEBM-ST370PH IB - End Bent 1 - EB Median Widening (Bridge over International DR)No18-Apr-1611-Jun-17
IBEBM-ST380PH IB - Wall Bent 3 - EB Median Widening (Bridge over International DR)No09-May-1611-Jun-17
IBEBM-ST390PH IB - Curing for Pier 2, 3, (Pile Cap) - EB Median Widening (Bridge over Shingle Creek)No24-Feb-1611-Jun-17
IBEBM-ST400PH IB - Remove Concrete Form for Pier 2, 3, (Pile Cap) - EB Median Widening (Bridge over Shingle Creek)No02-Mar-1611-Jun-17
IBEBM-ST410PH IB - End Bent 3 - EB Median Widening (Bridge over International DR)No09-May-1611-Jun-17
IBEBM-ST420PH IB - Curing for End Bent 3 - EB Median Widening (Bridge over International DR)No12-May-1611-Jun-17
IBEBM-ST430PH IB - End Bent 1 - EB Median Widening (Bridge over Shingle Creek)No28-Apr-1611-Jun-17
IBEBM-ST440PH IB - Curing For Pier 2, 3, 4(Footer, Column & Pier Cap) - EB Median Widening (Bridge over John Young PKWY)No02-Aug-1611-Jun-17
IBEBM-ST450PH IB - Set Beams - EB Median Widening (Bridge over International Drive)No13-Oct-1611-Jun-17
IBEBM-ST460PH IB - Superstructure Deck - EB Median Widening (Bridge over International Drive)No24-Oct-1611-Jun-17
IBEBM-ST470PH IB - Remove Concrete Forms for Pier 2, 3, 4 (Footer, Column & Pier Cap) - EB Median Widening (Bridge over John YoungNo26-Apr-1611-Jun-17
IBEBM-ST480PH IB - Temp Sheet Pile Removal - EB Median Widening (Bridge over John Young PKWY)No05-May-1611-Jun-17
IBEBM-ST490PH IB - Wall Bent 1 - EB Median Widening (Bridge over John Young PKWY)No05-Aug-1611-Jun-17
IBEBM-ST510PH IB - End Bent 1 - EB Median Widening (Bridge over John Young PKWY)No03-Aug-1611-Jun-17
IBEBM-ST520PH IB - Wall Bent 5 - EB Median Widening (Bridge over John Young PKWY)No13-Jun-1611-Jun-17
IBEBM-ST530PH IB - End Bent 4 - EB Median Widening (Bridge over Shingle Creek)No05-May-1611-Jun-17
IBEBM-ST540PH IB - Pier 2,(F/R/P) (Footer, Column & Pier Cap) - EB Median Widening (Bridge over Universal BLVD)No10-Jun-1611-Jun-17
IBEBM-ST550PH IB - Approach Slabs - EB Median Widening (Bridge over International DR)No12-Jan-1711-Jun-17
IBEBM-ST560PH IB - Concrete Slope Pavement - EB Median Widening (Bridge over International DR)No13-Jun-1611-Jun-17
IBEBM-ST570PH IB - End Bent 5 - EB Median Widening (Bridge over John Young PKWY)No13-Jun-1611-Jun-17
IBEBM-ST580PH IB - Lighting Conduit - EB Median Widening (Bridge over International DR)No26-Jan-1711-Jun-17
IBEBM-ST590PH IB - Traffic Railing (32") - EB Median Widening (Bridge over International DR)No07-Feb-1711-Jun-17
IBEBM-ST600PH IB - Grind and Groove - EB Median Widening (Bridge over International DR)No20-Feb-1711-Jun-17
IBEBM-ST610PH IB - Curing for Pier 2,(Footer, Column & Pier Cap) - EB Median Widening (Bridge over Universal BLVD)No04-Aug-1611-Jun-17
IBEBM-ST620PH IB - Set Beams - EB Median Widening (Bridge over Shingle Creek)No23-May-1611-Jun-17
IBEBM-ST630PH IB - Removal concrete form for Pier 2,(Footer, Column & Pier Cap) - EB Median Widening (Bridge over Universal BLVD)No05-Aug-1611-Jun-17
IBEBM-ST640PH IB - Temp Sheet Pile Removal - EB Median Widening (Bridge over universal BLVD)No26-Jul-1611-Jun-17
IBEBM-ST650PH IB - Wall Bent 1 - EB Median Widening (Bridge over universal BLVD)No02-Sep-1611-Jun-17
IBEBM-ST660PH IB - Set Beams - EB Median Widening (Bridge over John Young PKWY)No27-Sep-1611-Jun-17
IBEBM-ST670PH IB - Superstructure Deck - EB Median Widening (Bridge over John Young PKWY)No21-Oct-1611-Jun-17
IBEBM-ST680PH IB - End Bent 1 - EB Median Widening (Bridge over universal BLVD)No18-Aug-1611-Jun-17
IBEBM-ST690PH IB - Superstructure Deck- EB Median Widening (Bridge over Shingle Creek)No26-May-1611-Jun-17
IBEBM-ST700PH IB - Wall Bent 3 - EB Median Widening (Bridge over universal BLVD)No06-May-1611-Jun-17
IBEBM-ST710PH IB - End Bent 3 - EB Median Widening (Bridge over universal BLVD)No20-Apr-1611-Jun-17
IBEBM-ST720PH IB - Curing for End Bent 5 - EB Median Widening (Bridge over John Young PKWY)No22-Jul-1611-Jun-17
IBEBM-ST730PH IB - Approach Slabs - EB Median Widening (Bridge over John Young PKWY)No15-Feb-1711-Jun-17
IBEBM-ST740PH IB - Concrete Slope Pavement - EB Median Widening (Bridge over John Young PKWY)No12-Sep-1611-Jun-17
IBEBM-ST750PH IB - Set Beams - EB Median Widening (Bridge over Universal BLVD)No11-Oct-1611-Jun-17
IBEBM-ST760PH IB - Superstructure Deck - EB Median Widening Bridge over Universal BLVD)No24-Oct-1611-Jun-17
IBEBM-ST770PH IB - Lighting Conduit - EB Median Widening (Bridge over John Young PKWY)No01-Feb-1711-Jun-17
IBEBM-ST780PH IB - Traffic Railing (32") - EB Median Widening (Bridge over John Young PKWY)No03-Mar-1711-Jun-17
IBEBM-ST790PH IB - Grind and Groove - EB Median Widening (Bridge over John Young PKWY)No28-Feb-1711-Jun-17
IBEBM-ST800PH IB - Approach Slabs - EB Median Widening (Bridge over Shingle Creek)No13-Jul-1611-Jun-17
IBEBM-ST810PH IB - Grind and Groove - EB Median Widening (Bridge over Shingle Creek)No03-Aug-1611-Jun-17
IBEBM-ST840PH IB - Approach Slabs - EB Median Widening (Bridge over universal BLVD)No20-Jan-1711-Jun-17
IBEBM-ST850PH IB - Concrete Slope Pavement - EB Median Widening (Bridge over universal BLVD)No06-Jun-1611-Jun-17
IBEBM-ST860PH IB - Lighting Conduit - EB Median Widening (Bridge over universal BLVD)No30-Jan-1711-Jun-17
IBEBM-ST870PH IB - Traffic Railing (32") - EB Median Widening (Bridge over universal BLVD)No09-Feb-1711-Jun-17
IBEBM-ST880PH IB - Grind and Groove - EB Median Widening (Bridge over universal BLVD)No21-Feb-1711-Jun-17
IBEBM-ST890PH IB - Demo Bridge Deck - EB Median Widening (Bridge over International DR)No14-Mar-1611-Jun-17
IBEBM-ST900PH IB - Demo Bridge Deck - EB Median Widening (Bridge over universal BLVD)No29-Feb-1611-Jun-17
IBEBM-ST910PH IB - Demo Bridge Deck - EB Median Widening (Bridge over Shingle Creek)No22-Nov-1511-Jun-17
IBEBM-ST920PH IB - Remove Beams - EB Median Widening (Bridge over Shingle Creek)No09-Dec-1511-Jun-17
IBEBM-ST930PH IB - Demo Pile Caps - EB Median Widening (Bridge over Shingle Creek)No20-Dec-1511-Jun-17
IBEBM-ST940PH IB - Extract Piles - EB Median Widening (Bridge over Shingle Creek)No30-Jan-1611-Jun-17
IBEBM-ST950PH IB - Demo Bridge Deck - EB Median Widening (Bridge over John Young PKWY)No04-Jan-1611-Jun-17
IBEBM-ST960PH IB - Pier 2, 3, 4(F/R/P) (Footer, Column) - EB Median Widening (Bridge over John Young PKWY)No09-Mar-1611-Jun-17
IBEBM-ST970PH IB - Curing for End Bent 3 - EB Median Widening (Bridge over universal BLVD)No10-May-1611-Jun-17
IBEBM-ST980PH IB - Curing for End Bent 4 - EB Median Widening (Bridge over Shingle Creek)No18-May-1611-Jun-17
IBEBM-ST990PH IB - Bolt/Pin Temp B/W - EB Median Widening (Bridge over Shingle Creek)No04-Aug-1611-Jun-17
IBEBM-TC110PH IB - Set Temp Traffic Barriers for Phase IIA - EB Median WideningNo18-Jul-1611-Jun-17
IBEBM-TC130PH IB - Temp Striping for Phase IIA - EB Median WideningNo18-Jul-1611-Jun-17
IBEBM-TC210PH IB - Construct Diversion at Shingle Creek- EB Median WideningNo20-Jun-1611-Jun-17
IBEBM-W100PH IB - Median Wall - Grading (JYP to TPK)No11-May-1611-Jun-17
IBEBM-W110PH IB - Median Wall - FFP Footing/Stem (JYP to TPK)No20-May-1611-Jun-17
IBEBM-W130PH IB - Wire (mse) Retaining Wall TW 18 - EB Median Widening (SR528)No06-Jun-1611-Jun-17
IBEBM-W140PH IB - Wire (mse) Retaining Wall TW 20 - EB Median Widening (SR528)No06-Jun-1611-Jun-17
IBEBO-EW110PH IB - Pond Excav/Embank JYP to TPK - EB Outside WideningNo16-Nov-1511-Jun-17
IBEBO-EW120PH IB - Pond Excav/Embank I-4 to Int. Dr. - EB Outside WideningNo16-Jan-1711-Jun-17
IBEBO-EW130PH IB - Pond Excav/Embank JYP to Universal - WB Outside WideningNo16-Nov-1511-Jun-17
IBEBO-EW140PH IB - Pond Excav/Embank Universal to Int. Dr. - WB Outside WideningNo19-Nov-1513-Jun-17
IBEBO-EW150PH IB - Pond Excav/Embank Universal to Int. Dr. - EB Outside WideningNo16-Nov-1511-Jun-17
IBEBO-EW160PH IB - Pond Excav/Embank Universal to JYP - EB Outside WideningNo30-Nov-1513-Jun-17
IBEBO-EW170PH IB - Pond Excav/Embank Int. Dr. to I-4 - WB Outside WideningNo18-Jan-1616-Jun-17
IBEBO-GC100PH IB - Remove Existing Overhead Sign (sta 356+25) & Foundation - EB Outside WideningNo08-Sep-1611-Jun-17
IBEBO-SP150PH IB - Drainage (Pond 5C @ John Young) - EB Outside Widening (Ponds)No04-Aug-1619-Jun-17
IBR-AP120PH IB - Asphalt - Structural - Ramp C (Redundant)No19-Dec-1611-Jun-17
IBR-EW110PH IB - Embankment - Ramp C (Redundant)No19-Dec-1611-Jun-17
IBR-GC120PH IB - Guardrail (Roadway) - Ramp B/C Gore (Activity Not Req'd)No19-Dec-1606-Jul-17
IBR-GC130PH IB - Clear & Grub/Demo - Ramp C (Redundant)No19-Dec-1611-Jun-17
IBR-GC150PH IB - Performance Turf, SOD - Ramp C (Redundant)No19-Dec-1611-Jun-17
IBR-GC160PH IB - Guardrail (Roadway) - Ramp C (Redundant)No19-Dec-1611-Jun-17
IBR-IDS10PH IB - Install Drilled Shafts (1-13)No04-Mar-1611-Jun-17
IBR-IHM300PH IB - Install High Mast/Service (1-3)No06-Jun-1611-Jun-17
IBR-RW120PH IB - Stabilization - Ramp C (Redundant)No19-Dec-1611-Jun-17
IBR-RW130PH IB - Base - Ramp C (Redundant)No19-Dec-1611-Jun-17
IBR-TC100PH IB - Set Temp Traffic Barriers - Ramp B/C GoreNo22-May-1711-Jun-17
IBR-TC110PH IB - Set Temp Traffic Barriers - Ramp C (Redundant)No19-Dec-1611-Jun-17
IBWBM-AP100PH IB - Asphalt - Structural - WB Median WideningNo16-Nov-1611-Jun-17
IBWBM-GC100PH IB - Median Clearing and Grubbing - WB Median WideningNo27-Oct-1511-Jun-17
IBWBM-RW110PH IB - Grade for Permanent Shoulder Construction (JYP-TRP) - WB Median WideningNo06-Jun-1611-Jun-17
IBWBM-RW111PH IB - Stabilization for Permanent Shoulder Construction (JYP-TRP) - WB Median WideningNo13-Jul-1611-Jun-17
IBWBM-RW130PH IB - Grade (JYP-Universal) - WB Median WideningNo26-Oct-1611-Jun-17
IBWBM-RW140PH IB - Stabilization (JYP-Universal) - WB Median WideningNo28-Oct-1611-Jun-17
IBWBM-RW150PH IB - Base (JYP-Universal) - WB Median WideningNo03-Nov-1611-Jun-17
IBWBM-RW160PH IB - Grade (Universal-International Drv.) - WB Median WideningNo14-Dec-1611-Jun-17
IBWBM-RW170PH IB - Stabilization (Universal-International Drv.) - WB Median WideningNo14-Dec-1611-Jun-17
IBWBM-RW180PH IB - Base (Universal-International Drv.) - WB Median WideningNo14-Dec-1611-Jun-17
IBWBM-RW190PH IB - Grade (International Drive-I4) - WB Median WideningNo15-Dec-1611-Jun-17
IBWBM-RW200PH IB - Stabilization (International Drv.-I4) - WB Median WideningNo15-Dec-1611-Jun-17
IBWBM-RW210PH IB - Base (International Drv.-I4) - WB Median WideningNo15-Dec-1611-Jun-17
IBWBM-RW220PH IB - Base for Permanent Shoulder Construction (JYP-TRP) - WB Median WideningNo27-Oct-1616-Jun-17
IBWBM-RW230PH IB - Pavement for Permanent Shoulder Construction (JYP-TRP) - WB Median WideningNo15-Nov-1622-Jun-17
IBWBM-RW240PH IB - Pavement for Permanent Shoulder Construction (Universal-International Drv.) - WB Median WideningNo18-Jul-1611-Jun-17
IBWBM-SP100PH IB - Drainage for JYP Interchange (Sta 354 +04)No12-Apr-1611-Jun-17
IBWBM-SP110PH IB - Drainage for JYP to STA 390No18-Feb-1611-Jun-17
IBWBM-SP120PH IB - Drainage for JYP to Int. Dr. (Sta 354+04 to 234+50)No12-Apr-1611-Jun-17
IBWBM-SP140PH IB - Drainage for STA 390 to TPKNo08-Feb-1611-Jun-17
IBWBM-ST110PH IB - Construct Crane Access - WB Median Widening (Bridge over International DR)No17-Mar-1611-Jun-17
IBWBM-ST120PH IB - Demo Traffic Rail - WB Median Widening (Bridge over International DR)No14-Mar-1611-Jun-17
IBWBM-ST130PH IB - Test Pile H-Piles - WB Median Widening (Bridge over International DR)No28-Mar-1611-Jun-17
IBWBM-ST140PH IB - Temp Sheet Pile - WB Median Widening (Bridge over International DR)No16-May-1611-Jun-17
IBWBM-ST150PH IB - Production Pile - WB Median Widening (Bridge over International DR)No28-Mar-1611-Jun-17
IBWBM-ST160PH IB - Construct Crane Access - WB Median Widening (Bridge over universal BLVD)No21-Feb-1611-Jun-17
IBWBM-ST170PH IB - Pier 2, (F/R/P)(Footer, Column & Pier Cap) - WB Median Widening (Bridge over International DR)No18-May-1611-Jun-17
IBWBM-ST180PH IB - Demo Traffic Rail / End Bents - WB Median Widening (Bridge over universal BLVD)No29-Feb-1611-Jun-17
IBWBM-ST190PH IB - Test Pile Concrete - WB Median Widening (Bridge over universal BLVD)No10-Aug-1611-Jun-17
IBWBM-ST200PH IB - Temp Sheet Pile - WB Median Widening (Bridge over universal BLVD)No08-Jun-1611-Jun-17
IBWBM-ST210PH IB - Production Pile Concrete - WB Median Widening (Bridge over universal BLVD)No10-Mar-1611-Jun-17
IBWBM-ST220PH IB - Curing for Pier 2, (Footer, Column & Pier Cap) - WB Median Widening (Bridge over International DR)No27-Jul-1611-Jun-17
IBWBM-ST230PH IB - Construct Crane Access - WB Median Widening (Bridge over John Young PKWY)No04-Dec-1511-Jun-17
IBWBM-ST240PH IB - Demo Traffic Rails - WB Median Widening (Bridge over John Young PKWY)No04-Jan-1611-Jun-17
IBWBM-ST250PH IB - Test Pile (H Piles) - WB Median Widening (Bridge over John Young PKWY)No14-Dec-1511-Jun-17
IBWBM-ST260PH IB - Removal of Concrete Forms for Pier 2, (Footer, Column & Pier Cap) - (Bridge over International DR)No04-Aug-1611-Jun-17
IBWBM-ST270PH IB - Temp Sheet Pile Removal - WB Median Widening (Bridge over International DR)No25-Jul-1611-Jun-17
IBWBM-ST280PH IB - Wall Bent 1 - WB Median Widening (Bridge over International DR)No18-Apr-1611-Jun-17
IBWBM-ST290PH IB - End Bent 1 - WB Median Widening (Bridge over International DR)No18-Apr-1611-Jun-17
IBWBM-ST300PH IB - Temp Sheet Pile - WB Median Widening (Bridge over John Young PKWY)No06-Mar-1611-Jun-17
IBWBM-ST310PH IB - Production Pile (H Piles) - WB Median Widening (Bridge over John Young PKWY)No25-Jan-1611-Jun-17
IBWBM-ST320PH IB - Wall Bent 3 - WB Median Widening (Bridge over International DR)No09-May-1611-Jun-17
IBWBM-ST330PH IB - End Bent 3 - WB Median Widening (Bridge over International DR)No05-May-1611-Jun-17
IBWBM-ST340PH IB - Pier 2, 3, 4(F/R/P) (Footer, Column & Pier Cap) - WB Median Widening (Bridge over John Young PKWY)No09-Mar-1611-Jun-17
IBWBM-ST350PH IB - Set Beams - WB Median Widening (Bridge over International Drive)No13-Oct-1611-Jun-17
IBWBM-ST360PH IB - Superstructure Deck - WB Median Widening (Bridge over International Drive)No24-Oct-1611-Jun-17
IBWBM-ST370PH IB - Curing For Pier 2, 3, 4(Footer, Column & Pier Cap) - WB Median Widening (Bridge over John Young PKWY)No02-Aug-1611-Jun-17
IBWBM-ST380PH IB - Pier 2, (F/R/P)(Footer, Column & Pier Cap) - WB Median Widening (Bridge over Universal BLVD)No13-Jun-1611-Jun-17
IBWBM-ST390PH IB - Approach Slabs - WB Median Widening (Bridge over International DR)No12-Jan-1711-Jun-17
IBWBM-ST400PH IB - Concrete Slope Pavement - WB Median Widening (Bridge over International DR)No13-Jun-1611-Jun-17
IBWBM-ST410PH IB - Removal of Concrete forms for Pier 2, 3, 4 (Footer, Column & Pier Cap) - WB Median Widening (Bridge over JYP)No09-Aug-1611-Jun-17
IBWBM-ST420PH IB - Wall Bent 1 - WB Median Widening (Bridge over John Young PKWY)No05-Aug-1611-Jun-17
IBWBM-ST430PH IB - Lighting Conduit - WB Median Widening (Bridge over International DR)No26-Jan-1711-Jun-17
IBWBM-ST440PH IB - Traffic Railing (32") - WB Median Widening (Bridge over International DR)No07-Feb-1711-Jun-17
IBWBM-ST450PH IB - Temp Sheet Pile Removal - WB Median Widening (Bridge over John Young PKWY)No05-May-1611-Jun-17
IBWBM-ST460PH IB - End Bent 1 - WB Median Widening (Bridge over John Young PKWY)No03-Aug-1611-Jun-17
IBWBM-ST470PH IB - Grind and Groove - WB Median Widening (Bridge over International DR)No20-Feb-1711-Jun-17
IBWBM-ST480PH IB - Curing for Pier 2, (Footer, Column & Pier Cap) - WB Median Widening (Bridge over Universal BLVD)No04-Aug-1611-Jun-17
IBWBM-ST490PH IB - Wall Bent 5 - WB Median Widening (Bridge over John Young PKWY)No13-Jun-1611-Jun-17
IBWBM-ST500PH IB - Removal of Concrete Forms for Pier 2, (Footer, Column & Pier Cap) - WB Median Widening (Bridge over Universal BLNo05-Aug-1611-Jun-17
IBWBM-ST510PH IB - Temp Sheet Pile Removal - WB Median Widening (Bridge over universal BLVD)No26-Jul-1611-Jun-17
IBWBM-ST520PH IB - Wall Bent 1 - WB Median Widening (Bridge over universal BLVD)No02-Sep-1611-Jun-17
IBWBM-ST530PH IB - End Bent 5 - WB Median Widening (Bridge over John Young PKWY)No13-Jun-1611-Jun-17
IBWBM-ST540PH IB - End Bent 1 - WB Median Widening (Bridge over universal BLVD)No18-Aug-1611-Jun-17
IBWBM-ST550PH IB - Wall Bent 3 - WB Median Widening (Bridge over universal BLVD)No06-May-1611-Jun-17
IBWBM-ST560PH IB - Set Beams - WB Median Widening (Bridge over John Young PKWY)No27-Sep-1611-Jun-17
IBWBM-ST570PH IB - End Bent 3 - WB Median Widening (Bridge over universal BLVD)No20-Apr-1611-Jun-17
IBWBM-ST580PH IB - Superstructure Deck - WB Median Widening (Bridge over John Young PKWY)No18-Nov-1611-Jun-17
IBWBM-ST590PH IB - Set Beams - WB Median Widening (Bridge over Universal BLVD)No11-Oct-1611-Jun-17
IBWBM-ST600PH IB - Superstructure Deck - WB Median Widening Bridge over Universal BLVD)No06-Dec-1611-Jun-17
IBWBM-ST610PH IB - Approach Slabs - WB Median Widening (Bridge over John Young PKWY)No15-Feb-1711-Jun-17
IBWBM-ST620PH IB - Concrete Slope Pavement - WB Median Widening (Bridge over John Young PKWY)No06-Sep-1611-Jun-17
IBWBM-ST630PH IB - Lighting Conduit - WB Median Widening (Bridge over John Young PKWY)No31-Jan-1711-Jun-17
IBWBM-ST640PH IB - Traffic Railing (32") - WB Median Widening (Bridge over John Young PKWY)No06-Mar-1711-Jun-17
IBWBM-ST650PH IB - Approach Slabs - WB Median Widening (Bridge over universal BLVD)No25-Jan-1711-Jun-17
IBWBM-ST660PH IB - Concrete Slope Pavement - WB Median Widening (Bridge over universal BLVD)No15-Sep-1611-Jun-17
IBWBM-ST670PH IB - Grind and Groove - WB Median Widening (Bridge over John Young PKWY)No27-Feb-1711-Jun-17
IBWBM-ST680PH IB - Lighting Conduit - WB Median Widening (Bridge over universal BLVD)No31-Jan-1711-Jun-17
IBWBM-ST690PH IB - Traffic Railing (32") - WB Median Widening (Bridge over universal BLVD)No09-Feb-1711-Jun-17
IBWBM-ST700PH IB - Grind and Groove - WB Median Widening (Bridge over universal BLVD)No21-Feb-1711-Jun-17
IBWBM-ST710PH IB - Demo Bridge Deck- WB Median Widening (Bridge over universal BLVD)No22-Mar-1611-Jun-17
IBWBM-ST720PH IB - Demo Bridge Deck - WB Median Widening (Bridge over John Young PKWY)No04-Jan-1611-Jun-17
IBWBM-ST730PH IB - Demo Bridge Deck - WB Median Widening (Bridge over International DR)No14-Mar-1611-Jun-17
IBWBM-ST740PH IB - Curing for End Bent 5 - WB Median Widening (Bridge over John Young PKWY)No22-Jul-1611-Jun-17
IBWBM-ST750PH IB - Curing for End Bent 3 - WB Median Widening (Bridge over International DR)No13-May-1611-Jun-17
IBWBM-ST760PH IB - Curing for End Bent 3 - WB Median Widening (Bridge over universal BLVD)No16-May-1611-Jun-17
IBWBM-TC150PH IB - Construct Diversion at I-Drive - WB Median WideningNo08-Feb-1711-Jun-17
IBWBM-W100PH IB - Median Wall - Construct/ slip Top (JYP to TPK)No27-Jun-1611-Jun-17
IBWBM-W120PH IB - Wire (mse) Retaining Wall TW 19 - WB Median Widening (SR528)No06-Jun-1611-Jun-17
IBWBM-W140PH IB - Wire (mse) Retaining Wall TW 21 - WB Median Widening (SR528)No06-Jun-1611-Jun-17
IBWBO-EW100PH IB - Pond Excav/Embank JYP to TPK - WB Outside WideningNo07-Dec-1516-Jun-17
IBWBO-SP100PH IB - Jack & Bore JYP Interchange (Sta 354 +04)No11-Apr-1611-Jun-17
IBWBO-SP130PH IB - Jack & Bore JYP to TPK (East of Sta 354+04 to 415+33)No06-Jan-1611-Jun-17
IBWBO-SP140PH IB - Jack & Bore JYP to Int. Dr. (Sta 354+04 to 234+50)No17-Mar-1611-Jun-17
IBWBO-SP160PH IB - Drainage Outfalls (Pond 4A @ John Young) - WB Outside Widening Area (Ponds)No13-Jul-1611-Jun-17
IBWBO-SP190PH IB - Drainage Outfalls (Pond 5A @ John Young) - WB Outside Widening Area (Ponds)No24-Oct-1606-Jul-17
IIAEBO-AP100PH IIA - Mill & Resurface (sacrificial) - EB Outside Widening (SR528)No29-Mar-1711-Jun-17
IIAEBO-TC100PH IIA - Install Sign & Traffic Control Devices - EB Outside WideningNo20-Sep-1511-Jun-17
IIAEBO-TC120PH IIA - MOT Shift for Phase IIA - EB Outside WideningNo07-Sep-1611-Jun-17
IIAR-EW100PH IIB - Embankment - Ramp ONo14-Dec-1511-Jun-17
IIAR-RW100PH IIB - Stabilization - Ramp ONo18-May-1711-Jun-17
IIAR-RW110PH IIB - Base - Ramp ONo30-May-1711-Jun-17
IIAR-SP100PH IIA - Jack & Bore (42" (Sta 351+00 near Duke energy access platform) - Ramp ONo06-Jul-1611-Jun-17
IIAR-SP110PH IIB - Drainage - Ramp ONo26-Jul-1611-Jun-17
IIAR-TC140PH IIA - Temp Striping New Ramp Alignment - Ramp ONo07-Sep-1619-Jun-17
IIAR100PH IIA - Construct Ramp O Diversion - Ramp ONo11-Jul-1611-Jun-17
IIAR110PH IIA - Construct Ramp O Diversion - Ramp O (Tie in to EB)No07-Sep-1611-Jun-17
IIBEBO-AP100PH IIB - Mill & Resurface (sacrificial) - EB Outside Widening (SR528)No05-Apr-1711-Jun-17
IIBEBO-EW101PH IIB - Embankment (Int. Drive - Universal) - EB Outside WideningNo15-Sep-1610-Jul-17
IIBEBO-EW102PH IIB - Embankment (Universal - JYP) - EB Outside WideningNo03-Oct-1610-Jul-17
IIBEBO-EW112PH IIB - Embankment (Int. Drive - Universal) - at Toll FacilityNo10-Oct-1611-Jun-17
IIBEBO-GC100PH IIB - MISC. Demo - EB Outside WideningNo06-Feb-1711-Jun-17
IIBEBO-GC110PH IIB - Performance Turf, SOD - EB Outside WideningNo20-Mar-1710-Jul-17
IIBEBO-RW111PH IIB - Stabilization (Int. Drive - Universal) - EB Outside WideningNo03-Apr-1710-Jul-17
IIBEBO-RW112PH IIB - Stabilization (Universal - JYP) - EB Outside Widening - (STA 291 to 320)No17-Mar-1711-Jun-17
IIBEBO-RW170PH IIB - Stabilization (Universal - JYP) - EB Outside Widening - (STA 320 to 332)Yes17-Mar-1711-Jun-17
IIBEBO-RW180PH IIB - Base (Universal - JYP) - EB Outside Widening - LR - (STA 320 to 332)Yes01-May-1711-Jun-17
IIBEBO-SP110PH IIB - Drainage (Int. Drive - Universal) - EB Outside Widening (SR528)No07-Nov-1611-Jun-17
IIBEBO-SP120PH IIB - Drainage (Universal - JYP) - EB Outside Widening (SR528)No20-Mar-1711-Jun-17
IIBEBO-SP130PH IIB - Gutter Drainage - STA 228 - 248 (EB Outside)No18-May-1710-Jul-17
IIBEBO-SP140PH IIB - Gutter Drainage - STA 280 - 299 (EB Outside)No08-May-1710-Jul-17
IIBEBO-SP150PH IIB - Gutter Drainage - STA 326 - 336 (EB Outside)No05-Apr-1710-Jul-17
IIBEBO-ST1PH IIB - Construct Crane Access - EB Outside Widening (Bridge over International DR)No18-Jul-1611-Jun-17
IIBEBO-ST10PH IIB - Test Pile - EB Outside Widening (Bridge over universal BLVD)No10-Oct-1611-Jun-17
IIBEBO-ST11PH IIB - Temp Sheet Pile - EB Outside Widening (Bridge over universal BLVD)No17-Oct-1611-Jun-17
IIBEBO-ST110PH IIB - Demo Traffic Rails - EB Outside Widening (Bridge over Shingle Creek)No10-Oct-1611-Jun-17
IIBEBO-ST12PH IIB - Production Pile - EB Outside Widening (Bridge over universal BLVD)No17-Oct-1611-Jun-17
IIBEBO-ST120PH IIB - Wall Bent 1 - EB Outside Widening (Bridge 750629 Ramp S over JYP)No30-Jan-1711-Jun-17
IIBEBO-ST130PH IIB - Demo Traffic Rails - EB Outside Widening (Bridge over International DR)No12-Apr-1711-Jun-17
IIBEBO-ST14PH IIB - Pier 2, (F/R/P)(Footer, Column & Pier Cap) - EB Outside Widening (Bridge over Universal BLVD)No31-Oct-1611-Jun-17
IIBEBO-ST150PH IIB - End Bent 1 - EB Outside Widening (Bridge 750629 Ramp S over JYP)No24-Jan-1711-Jun-17
IIBEBO-ST16PH IIB - Curing for Pier 2, (Footer, Column & Pier Cap) - EB Outside Widening (Bridge over Universal BLVD)No08-Dec-1611-Jun-17
IIBEBO-ST17PH IIB - Removal of Concrete Forms Pier 2, (Footer, Column & Pier Cap) - EB Outside Widening (Bridge over Universal BLVNo15-Dec-1611-Jun-17
IIBEBO-ST170PH IIB - Pier 2, 3, (F/R/P)(Pile Cap) - EB Outside Widening (Bridge over Shingle Creek)No07-Nov-1611-Jun-17
IIBEBO-ST18PH IIB - Temp Sheet Pile Removal - EB Outside Widening (Bridge over universal BLVD)No15-Dec-1611-Jun-17
IIBEBO-ST180PH IIB - Wall Bent 5 - EB Outside Widening (Bridge 750629 Ramp S over JYP)No13-Jan-1711-Jun-17
IIBEBO-ST19PH IIB - Construct Crane Access - EB Outside Widening (Bridge 750629 Ramp S over JYP)No04-Jan-1611-Jun-17
IIBEBO-ST20PH IIB - Test Pile (H Piles) - EB Outside Widening (Bridge 750629 Ramp S over JYP)No05-Jan-1611-Jun-17
IIBEBO-ST21PH IIB - Temp Sheet Pile - EB Outside Widening (Bridge 750629 Ramp S over JYP)No17-Mar-1611-Jun-17
IIBEBO-ST210PH IIB - Curing Pier 2, 3, (Pile Cap) - EB Outside Widening (Bridge over Shingle Creek)No10-Jan-1711-Jun-17
IIBEBO-ST22PH IIB - Production Pile (H Piles) (1-31) - EB Outside Widening (Bridge 750629 Ramp S over JYP)No09-Feb-1611-Jun-17
IIBEBO-ST220PH IIB - End Bent 5 - EB Outside Widening (Bridge 750629 Ramp S over JYP)No10-Jan-1711-Jun-17
IIBEBO-ST23PH IIB - Production Pile (H Piles) (32-62) -EB Outside Widening (Bridge 750629 Ramp S over JYP)No18-Apr-1611-Jun-17
IIBEBO-ST230PH IIB - Removal concrete form for Pier 2, 3, (Pile Cap) - EB Outside Widening (Bridge over Shingle CrNo20-Jan-1711-Jun-17
IIBEBO-ST24PH IIB - Pier 2, 3, 4 (F/R/P)(Footer, Column) - EB Outside Widening (Bridge 750629 Ramp S over JYP)No18-Mar-1611-Jun-17
IIBEBO-ST240PH IIB - Wall Bent 1 - EB Outside Widening (Bridge over Shingle Creek)No11-Jan-1711-Jun-17
IIBEBO-ST25PH IIB - Curing for Pier 2, 3, 4(Footer, Column & Pier Cap) - EB Outside Widening (Bridge 750629 Ramp S over JYP)No14-Nov-1611-Jun-17
IIBEBO-ST26PH IIB - Remove of Concrete Form Pier 2, 3, 4 (Footer, Column & Pier Cap) - EB Outside Widening (Bridge 750629 Ramp S ovNo15-Sep-1611-Jun-17
IIBEBO-ST260PH IIB - End Bent 1 - EB Outside Widening (Bridge over Shingle Creek)No11-Jan-1711-Jun-17
IIBEBO-ST27PH IIB - Temp Sheet Pile Removal - EB Outside Widening (Bridge 750629 Ramp S over JYP)No12-Aug-1611-Jun-17
IIBEBO-ST28PH IIB - Construct Crane Access - EB Outside Widening (Bridge over Shingle Creek)No01-Aug-1611-Jun-17
IIBEBO-ST280PH IIB - Set Beams - EB Outside Widening (Bridge 750629 Ramp S over JYP)No13-Feb-1711-Jun-17
IIBEBO-ST290PH IIB - Superstructure Deck SIP & Start Rebar - EB Outside Widening (Bridge 750629 Ramp S over JYP)No17-Feb-1711-Jun-17
IIBEBO-ST3PH IIB - Temp Sheet Pile - EB Outside Widening (Bridge over International DR)No13-Jun-1611-Jun-17
IIBEBO-ST30PH IIB - Production Pile (Concrete) - EB Outside Widening (Bridge over Shingle Creek)No17-Oct-1611-Jun-17
IIBEBO-ST300PH IIB - Wall Bent 4 - EB Outside Widening (Bridge over Shingle Creek)No26-Jan-1711-Jun-17
IIBEBO-ST31PH IIB - Gravity Wall @ Shingle Creek - EB Outside Widening (Bridge over Shingle Creek)No16-May-1611-Jun-17
IIBEBO-ST310PH IIB - End Bent 4 - EB Outside Widening (Bridge over Shingle Creek)No13-Jan-1711-Jun-17
IIBEBO-ST32PH IIB - Rip Rap Under Bridge - EB Outside Widening (Bridge over Shingle Creek)No02-Dec-1611-Jun-17
IIBEBO-ST320PH IIB - Demo Traffic Rails - EB Outside Widening (Bridge over universal BLVD)No10-Apr-1711-Jun-17
IIBEBO-ST350PH IIB - Superstructure Deck Finish Rebar\Set screed\Pouring - EB Outside Widening (Bridge 750629 Ramp S over JYP)No10-Mar-1711-Jun-17
IIBEBO-ST4PH IIB - Production Pile - EB Outside Widening (Bridge over International DR)No01-May-1611-Jun-17
IIBEBO-ST400PH IIB - End Bent 1 - EB Outside Widening (Bridge over universal BLVD)No06-Jun-1716-Jun-17
IIBEBO-ST410PH IIB - Set Beams - EB Outside Widening (Bridge over Shingle Creek)No06-Feb-1711-Jun-17
IIBEBO-ST420PH IIB - Wall Bent 3 - EB Outside Widening (Bridge over universal BLVD)No08-Jun-1711-Jun-17
IIBEBO-ST430PH IIB - Approach Slabs - EB Outside Widening (Bridge 750629 Ramp S over JYP)No01-May-1711-Jun-17
IIBEBO-ST450PH IIB - End Bent 3 - EB Outside Widening (Bridge over universal BLVD)No31-May-1726-Jun-17
IIBEBO-ST460PH IIB - Lighting Conduit - EB Outside Widening (Bridge 750629 Ramp S over JYP)No17-May-1711-Jun-17
IIBEBO-ST470PH IIB - Traffic Railing (32") - EB Outside Widening (Bridge 750629 Ramp S over JYP)No19-May-1711-Jun-17
IIBEBO-ST490PH IIB - Superstructure Deck SIP & Start Rebar - EB Outside Widening (Bridge over Shingle Creek)No10-Feb-1711-Jun-17
IIBEBO-ST5PH IIB - Pier 2, (F/R/P) (Footer, Column & Pier Cap) - EB Outside Widening (Bridge over International DR)No13-Jun-1614-Jun-17
IIBEBO-ST510PH IIB - Grind and Groove - EB Outside Widening (Bridge 750629 Ramp S over JYP)No02-Jun-1711-Jun-17
IIBEBO-ST590PH IIB - Approach Slabs - EB Outside Widening (Bridge over Shingle Creek)No27-Mar-1711-Jun-17
IIBEBO-ST6PH IIB - Curing for Pier 2, (Footer, Column & Pier Cap) - EB Outside Widening (Bridge over International DR)No05-Aug-1621-Jun-17
IIBEBO-ST600PH IIB - Lighting Conduit - EB Outside Widening (Bridge over Shingle Creek)No20-Apr-1711-Jun-17
IIBEBO-ST610PH IIB - Traffic Railing (32") - EB Outside Widening (Bridge over Shingle Creek)No24-Apr-1711-Jun-17
IIBEBO-ST620PH IIB - Grind and Groove - EB Outside Widening (Bridge over Shingle Creek)No31-May-1711-Jun-17
IIBEBO-ST630PH IIB - Demo Bridge Deck - EB Outside Widening (Bridge over International DR)No24-Apr-1711-Jun-17
IIBEBO-ST640PH IIB - Demo Bridge Deck - EB Outside Widening (Bridge over universal BLVD)No24-Apr-1711-Jun-17
IIBEBO-ST650PH IIB - Demo Bridge Deck - EB Outside Widening (Bridge over Shingle Creek)No11-Oct-1611-Jun-17
IIBEBO-ST660PH IIB - Remove Beams - EB Outside Widening (Bridge over Shingle Creek)No11-Oct-1611-Jun-17
IIBEBO-ST670PH IIB - Demo Pile Cap - EB Outside Widening (Bridge over Shingle Creek)No12-Oct-1611-Jun-17
IIBEBO-ST680PH IIB - Extract Piles - EB Outside Widening (Bridge over Shingle Creek)No13-Oct-1611-Jun-17
IIBEBO-ST690PH IIB - Pier 2, 3, 4 (F/R/P)(Pier Cap) - EB Outside Widening (Bridge 750629 Ramp S over JYP)No06-Jul-1611-Jun-17
IIBEBO-ST7PH IIB- Removal of Concrete Forms for Pier 2, (Footer, Column & Pier Cap) - EB Outside Widening (Bridge over InternatioNo12-Aug-1621-Jun-17
IIBEBO-ST700PH IIB - Superstructure Deck (Finish Rebar\Set Screed\Pour) - EB Outside Widening (Bridge over Shingle Creek)No24-Feb-1711-Jun-17
IIBEBO-ST710PH IIB - Curing for End Bent 5 - EB Outside Widening (Bridge 750629 Ramp S over JYP)No30-Jan-1711-Jun-17
IIBEBO-ST740PH IIB - Curing for End Bent 4 - EB Outside Widening (Bridge over Shingle Creek)No27-Jan-1711-Jun-17
IIBEBO-ST8PH IIB - Temp Sheet Pile Removal - EB Outside Widening (Bridge over International DR)No26-Jul-1621-Jun-17
IIBEBO-ST9PH IIB - Construct Crane Access - EB Outside Widening (Bridge over universal BLVD)No22-Aug-1611-Jun-17
IIBEBO-TC130PH IIB - Set Temp Traffic Barriers - EB Outside WideningNo21-Mar-1711-Jun-17
IIBR-AP160PH IIB - Asphalt - Structural - Ramp I4- InterstateNo19-Dec-1607-Jul-17
IIBR-AP180PH IIB - Asphalt - Structural - Ramp UNo11-May-1705-Jul-17
IIBR-EHM340PH IIB - Existing High Mast Removal (1-8)No01-Mar-1714-Jun-17
IIBR-EHM350PH IIB - Existing High Mast Removal (9-18)No05-May-1714-Jun-17
IIBR-EW110PH IIB - Embankment - Ramp ENo28-Dec-1511-Jun-17
IIBR-EW120PH IIB - Embankment - Ramp S-1No23-May-1611-Jun-17
IIBR-EW122PH IIB - Embankment - Ramp ANo18-May-1611-Jun-17
IIBR-EW130PH IIB - Embankment - Ramp R-1No20-Mar-1712-Jun-17
IIBR-EW160PH IIB - Embankment - Ramp HNo28-Nov-1611-Jun-17
IIBR-EW170PH IIB - Embankment - Ramp R-2No20-Mar-1713-Jun-17
IIBR-EW180PH IIB - Embankment - Ramp I4- InterstateNo19-Dec-1607-Jul-17
IIBR-EW190PH IIB - Embankment - Ramp LNo03-Apr-1705-Jul-17
IIBR-EW200PH IIB - Embankment - Ramp UNo15-Dec-1512-Jun-17
IIBR-GC110PH IIB - Demo - Ramp ENo06-Mar-1711-Jun-17
IIBR-GC130PH IIB - Demo - Ramp R-1No21-Mar-1712-Jun-17
IIBR-GC150PH IIB - Demo - Ramp S-1No16-Jan-1711-Jun-17
IIBR-GC171PH IIB - Clear & Grub/Demo - Ramp ANo13-Jun-1611-Jun-17
IIBR-GC191PH IIB - Performance Turf, SOD - Ramp ANo13-Sep-1611-Jun-17
IIBR-GC240PH IIB - Demo - Ramp HNo07-Mar-1711-Jun-17
IIBR-GC290PH IIB - Demo - Ramp R-2No21-Mar-1711-Jun-17
IIBR-GC300PH IIB - Demo - Ramp I4- InterstateNo19-Dec-1607-Jul-17
IIBR-GC310PH IIB - Demo - Ramp LNo20-Mar-1711-Jun-17
IIBR-GC340PH IIB - Performance Turf, SOD - Ramp I4- InterstateNo19-Dec-1607-Jul-17
IIBR-GC350PH IIB - Demo - Ramp UNo29-Mar-1712-Jun-17
IIBR-GC400PH IIB - Guardrail (Roadway) - Ramp I4- InterstateNo19-Dec-1607-Jul-17
IIBR-IDS20PH IIB - Install Drilled Shafts (14-35)No14-Sep-1611-Jun-17
IIBR-IDS30PH IIB - Install Drilled Shafts (36-57)No03-May-1711-Jun-17
IIBR-IHM310PH IIB - Install High Mast/Service (4-6)No27-Oct-1614-Jun-17
IIBR-IHM320PH IIB - Install High Mast/Service (7-9)No07-Mar-1722-Jun-17
IIBR-ITS10PH IIB - Install Conduit/Boxes (I-4 to International)No28-Sep-1611-Jun-17
IIBR-ITS20PH IIB - Install Conduit/Boxes ( International to Univ)No24-Feb-1720-Jun-17
IIBR-ITS30PH IIB - Install Conduit/Boxes (Univ to JYP)No27-Jul-1626-Jun-17
IIBR-ITS40PH IIB - Install Conduit/Boxes (JYP to TPK)No26-Jul-1628-Jun-17
IIBR-RES120PH IIB - Remove Existing Sign Structures (2-4)No20-Mar-1714-Jun-17
IIBR-RW141PH IIB - Stabilization - Ramp ANo05-Jul-1611-Jun-17
IIBR-RW151PH IIB - Base - Ramp ANo14-Jul-1611-Jun-17
IIBR-RW210PH IIB - Stabilization - Ramp I4- InterstateNo19-Dec-1607-Jul-17
IIBR-RW230PH IIB - Base - Ramp I4- InterstateNo19-Dec-1607-Jul-17
IIBR-RW260PH IIB - Stabilization - Ramp UNo03-Apr-1705-Jul-17
IIBR-RW270PH IIB - Base - Ramp UNo12-Apr-1705-Jul-17
IIBR-SM390PH IIB - Shoulder Mount Light Pole/Service (International to Univ.) (20 EA) (A)No19-Dec-1605-Jul-17
IIBR-SM400PH IIB - Shoulder Mount Light Pole/Service (International to Univ.) (20 EA) (B)No27-Mar-1717-Jul-17
IIBR-SM410PH IIB - Shoulder Mount Light Pole/Service (International to Univ.) (20 EA) (C)No25-Apr-1727-Jul-17
IIBR-SM440PH IIB - Shoulder Mount Light Pole/Service (Univ. to JYP) (18 EA) (A)No27-Jul-1607-Sep-17
IIBR-SM450PH IIB - Shoulder Mount Light Pole/Service (Univ. to JYP) (19 EA)No10-May-1714-Sep-17
IIBR-SM460PH IIB - Shoulder Mount Light Pole/Service (Univ. to JYP) (18 EA) (B)No16-May-1722-Sep-17
IIBR-SM470PH IIB - Shoulder Mount Light Pole/Service (JYP to TPK) (20 EA) (A)No26-Jul-1629-Sep-17
IIBR-SM480PH IIB - Shoulder Mount Light Pole/Service (JYP to TPK) (20 EA) (B)No09-May-1604-Oct-17
IIBR-SP110PH IIB - Drainage - Ramp ENo22-May-1711-Jun-17
IIBR-SP120PH IIB - Drainage (Temp) - Ramp R-1No10-Apr-1712-Jun-17
IIBR-SP121PH IIB - Drainage - Ramp ANo13-Jun-1611-Jun-17
IIBR-SP140PH IIB - Drainage (Temp) - Ramp S-1No16-Jan-1711-Jun-17
IIBR-SP160PH IIB - Drainage (Temp) - Ramp HNo31-Jan-1711-Jun-17
IIBR-SP170PH IIB - Drainage (Temp) - Ramp R-2No20-Mar-1713-Jun-17
IIBR-SP180PH IIB - Drainage (Temp) - Ramp I4 InterstateNo19-Dec-1607-Jul-17
IIBR-SP190PH IIB - Drainage (Temp) - Ramp LNo19-Dec-1611-Jun-17
IIBR-SP200PH IIB - Drainage (Temp) - Ramp UNo19-Dec-1612-Jun-17
IIBR-SP250PH IIB - Drainage - Ramp R-2No17-Apr-1713-Jun-17
IIBR-TC220PH IIB - Set Temp Traffic Barriers (Shoulder) - Ramp ENo27-Feb-1711-Jun-17
IIBR-TC230PH IIB - Temp Striping New Ramp Alignment - Ramp ENo28-Feb-1711-Jun-17
IIBR-TC250PH IIB - Set Temp Traffic Barriers (Shoulder) - Ramp CNo16-Apr-1707-Jul-17
IIBR-TC280PH IIB - Set Temp Traffic Barriers (Shoulder) - Ramp I-1No16-Jan-1711-Jun-17
IIBR-TC290PH IIB - Set Temp Traffic Barriers (Shoulder) - Ramp I4- InterstateNo19-Dec-1607-Jul-17
IIBR-TC300PH IIB - Temp Striping New Ramp Alignment - Ramp I-1No23-Feb-1711-Jun-17
IIBR-TC310PH IIB - Set Temp Traffic Barriers (Shoulder) - Ramp HNo27-Feb-1711-Jun-17
IIBR-TC320PH IIB - Temp Striping New Ramp Alignment - Ramp HNo28-Feb-1711-Jun-17
IIBR-TC330PH IIB - Temp Striping New Ramp Alignment - Ramp R-2No13-Mar-1711-Jun-17
IIBR-TC340PH IIB - Set Temp Traffic Barriers (Shoulder) - Ramp R-2No09-Mar-1711-Jun-17
IIBR-TC360PH IIB - Temp Striping New Ramp Alignment - Ramp I4- InterstateNo19-Dec-1611-Jun-17
IIBR-TC370PH IIB - MOT Shift New Ramp Alignment - Ramp I4- InterstateNo19-Dec-1611-Jun-17
IIBR-TC380PH IIB - Set Temp Traffic Barriers (Shoulder) - Ramp LNo16-Jan-1711-Jun-17
IIBR-TC390PH IIB - Temp Striping New Ramp Alignment - Ramp LNo28-Feb-1711-Jun-17
IIBR-TC400PH IIB - Set Temp Traffic Barriers (Shoulder) - Ramp UNo16-Jan-1711-Jun-17
IIBR-TC410PH IIB - Temp Striping New Ramp Alignment - Ramp UNo09-Mar-1712-Jun-17
IIBR-TC440PH IIB - Temp Striping New Ramp Alignment - Ramp DNo10-Apr-1711-Jun-17
IIBR-TC450PH IIB - Set Temp Traffic Barriers (Shoulder) - Ramp DNo20-Mar-1711-Jun-17
IIBR100PH IIB - Construct Ramp E Diversion - Ramp ENo07-Dec-1611-Jun-17
IIBR110PH IIB - Construct Ramp I-1 Diversion - Ramp I-1No21-Nov-1611-Jun-17
IIBR120PH IIB - Construct Ramp R-1 Diversion - Ramp R-1No06-Feb-1711-Jun-17
IIBR140PH IIB - Construct Ramp R-2 Diversion - Ramps R-2No06-Feb-1711-Jun-17
IIBR150PH IIB - Construct Ramp H Diversion - Ramp HNo06-Dec-1611-Jun-17
IIBR151PH IIB - Construct Ramp L Diversion - Ramp LNo28-Jul-1611-Jun-17
IIBR170PH IIB - Construct Ramp U Diversion - Ramp UNo04-Jan-1712-Jun-17
IICR-EW100PH IIC - Embankment - Ramp S-2No04-Oct-1613-Jul-17
IICR-TC140PH IIC - MOT Shift for New Ramp Alignment - Ramp CNo19-Dec-1604-Oct-17
IICR100PH IIC - Construct Ramp S-2 Diversion - Ramp S-2No15-Feb-1711-Jun-17
IIDEBO-ST100PH IID - Construct Crane Access - EB Outside Widening (Bridge over John Young PKWY)No29-Feb-1623-Jun-17
IIDEBO-ST120PH IID - Temp Sheet Pile - EB Outside Widening (Bridge over John Young PKWY)No18-Mar-1611-Jun-17
IIDEBO-ST130PH IID - Production Pile (H Piles) - EB Outside Widening (Bridge over John Young PKWY)No01-Mar-1614-Sep-17
IIDEBO-ST140PH IID - Pier 2, 3, 4 (F/R/P) (Footer & Column) - EB Outside Widening (Bridge over John Young PKWY)No18-Mar-1611-Jun-17
IIDEBO-ST150PH IID - Curing for Pier 2, 3, 4(Footer, Column & Pier Cap) - EB Outside Widening (Bridge over John Young PKWY)No21-Sep-1616-Oct-17
IIDEBO-ST160PH IID - Remove Concrete form for Pier 2, 3, 4(Footer, Column & Pier Cap) - EB Outside Widening (Bridge over JYP)No16-Sep-1616-Oct-17
IIDEBO-ST170PH IID - Temp Sheet Pile Removal - EB Outside Widening (Bridge over John Young PKWY)No05-May-1616-Oct-17
IIDEBO-ST310PH IID - Pier 2, 3, 4 (F/R/P) ( Pier Cap) - EB Outside Widening (Bridge over John Young PKWY)No08-Jul-1616-Oct-17
IIIAR100PH IIIA - Construct Ramp Diversion P - Ramp P (STA 2013+84 to 2005+50)No10-Jan-1711-Jun-17
IIIAWBO-SP100PH IIIA - Jack & Bore - WB Outside Widening Area (SR528)No24-Apr-1712-Jun-17
IIIAWBO-ST15PH IIIA - Construct Crane Access - WB Outside Widening Area (Bridge 750630 Ramp T over JYP)No12-Jan-1623-Jun-17
IIIAWBO-ST16PH IIIA - Test Pile (H Piles) - WB Outside Widening Area (Bridge 750630 Ramp T over JYP)No07-Dec-1511-Jun-17
IIIAWBO-ST17PH IIIA - Temp Sheet Pile - WB Outside Widening Area (Bridge 750630 Ramp T over JYP)No05-May-1611-Jun-17
IIIAWBO-ST18PH IIIA - Production Pile (H Piles) (1-32) - WB Outside Widening Area (Bridge 750630 Ramp T over JYP)No04-Apr-1611-Jun-17
IIIAWBO-ST19PH IIIA - Production Pile (H Piles) (33-65) - WB Outside Widening Area (Bridge 750630 Ramp T over JYP)No13-Apr-1623-Jun-17
IIIAWBO-ST20PH IIIA - Pier 2, 3, 4 (F/R/P)(Footer, Column) - WB Outside Widening Area (Bridge 750630 Ramp T over JYP)No08-May-1623-Jun-17
IIIAWBO-ST200PH IIIA - Wall Bent 1 - WB Outside Widening Area (Bridge 750630 Ramp T over JYP)No17-Mar-1723-Jun-17
IIIAWBO-ST21PH IIIA - Curing for Pier 2, 3, 4 (Footer, Column & Pier Cap) - WB Outside Widening Area (Bridge 750630 Ramp T over JYP)No21-Sep-1623-Jun-17
IIIAWBO-ST22PH IIIA - Remove Concrete Form Pier 2, 3, 4 (Footer, Column & Pier Cap) - WB Outside Widening Area (Bridge 750630 Ramp TNo16-Sep-1623-Jun-17
IIIAWBO-ST23PH IIIA - Temp Sheet Pile Removal - WB Outside Widening Area (Bridge 750630 Ramp T over JYP)No11-Aug-1611-Jun-17
IIIAWBO-ST230PH IIIA - End Bent 1 - WB Outside Widening Area (Bridge 750630 Ramp T over JYP)No15-Mar-1723-Jun-17
IIIAWBO-ST27PH IIIA - Construct Crane Access - WB Outside Widening Area (Bridge over John Young PKWY)No05-Apr-1623-Jun-17
IIIAWBO-ST290PH IIIA - Wall Bent 5 - WB Outside Widening Area (Bridge 750630 Ramp T over JYP)No13-Apr-1723-Jun-17
IIIAWBO-ST30PH IIIA - Temp Sheet Pile - WB Outside Widening Area (Bridge over John Young PKWY)No25-May-1623-Jun-17
IIIAWBO-ST31PH IIIA - Production Pile (H Piles) - WB Outside Widening Area (Bridge over John Young PKWY)No07-Apr-1611-Jun-17
IIIAWBO-ST32PH IIIA - Pier 2, 3, 4 (F/R/P)(Footer, Column) - WB Outside Widening Area (Bridge over John Young PKWY)No26-May-1611-Jun-17
IIIAWBO-ST33PH IIIA - Curing of Pier 2, 3, 4 (Footer, Column & Pier Cap) - WB Outside Widening Area (Bridge over John Young PKWY)No21-Sep-1617-Jul-17
IIIAWBO-ST330PH IIIA - End Bent 5 - WB Outside Widening Area (Bridge 750630 Ramp T over JYP)No05-Apr-1723-Jun-17
IIIAWBO-ST34PH IIIA - Remove Concrete Form for Pier 2, 3, 4(Footer, Column & Pier Cap) - WB Outside Widening Area (Bridge over JohnNo16-Sep-1617-Jul-17
IIIAWBO-ST340PH IIIA - Curing for End Bent 5 - WB Outside Widening Area (Bridge 750630 Ramp T over JYP)No19-Apr-1723-Jun-17
IIIAWBO-ST35PH IIIA - Temp Sheet Pile Removal - WB Outside Widening Area (Bridge over John Young PKWY)No10-Aug-1617-Jul-17
IIIAWBO-ST410PH IIIA - Set Beams - WB Outside Widening Area (Bridge 750630 Ramp T over JYP)No10-May-1723-Jun-17
IIIAWBO-ST420PH IIIA - Superstructure Deck SIP & Start Rebar - WB Outside Widening Area (Bridge 750630 Ramp T over JYP)No15-May-1723-Jun-17
IIIAWBO-ST520PH IIIA - Superstructure Deck Finish Rebar\Set Screed\ Pour - WB Outside Widening Area (Bridge 750630 Ramp T over JYP)No31-May-1711-Jun-17
IIIAWBO-ST690PH IIIA - Pier 2, 3, 4 (F/R/P)(Pier Cap) - WB Outside Widening Area (Bridge 750630 Ramp T over JYP)No15-Aug-1623-Jun-17
IIIAWBO-ST710PH IIIA - Pier 2, 3, 4 (F/R/P) (Pier Cap) - WB Outside Widening Area (Bridge over John Young PKWY)No08-Jul-1617-Jul-17
IIIBR-EW120PH IIIB - Embankment - Ramp VNo18-May-1722-Nov-17
IIIBR-EW140PH IIIB - Embankment - Ramp TNo28-Dec-1525-Sep-17
IIIBR-GC180PH IIIB - Demo - Ramp VNo28-Mar-1707-Nov-17
IIIBR-IHM330PH IIIB - Install High Mast/Service (10-13)No14-Mar-1730-Jun-17
IIIBR-ITS80PH IIIB - Install Conduit/Boxes (JYP to TPK)No18-Jul-1606-Jul-17
IIIBR-SM550PH IIIB - Shoulder Mount Light Pole/Service (International to Univ.) (10 EA)No19-Dec-1611-Dec-17
IIIBR-SM600PH IIIB - Shoulder Mount Light Pole/Service (JYP to TPK) (20 EA) (A)No17-Oct-1628-Mar-18
IIIBR-SM610PH IIIB - Shoulder Mount Light Pole/Service (JYP to TPK) (20 EA) (B)No17-Oct-1613-Apr-18
IIIBR-SM620PH IIIB - Shoulder Mount Light Pole/Service (JYP to TPK) (20 EA) (C)No17-Oct-1601-May-18
IIIBR-SP140PH IIIB - Drainage (Temp) - Ramp TNo19-Dec-1621-Sep-17
IIIBR-TC180PH IIIB - Set Temp Traffic Barriers (Shoulder) - Ramp VNo19-Apr-1707-Nov-17
IIIBR-TC190PH IIIB - Temp Striping New Ramp Alignment - Ramp VNo16-Mar-1707-Nov-17
IIIBR120PH IIIB - Construct Ramp V Diversion - Ramp VNo23-Jan-1714-Sep-17
IIIBR130PH IIIB - Construct Ramp K Diversion/Temp Pavement - Ramp KNo03-Apr-1714-Sep-17
IIIBWBO-EW100PH IIIB - Surcharge/ Embankment 1 - WB Outside Widening AreaNo01-May-1714-Sep-17
IIIBWBO-EW101PH IIIB - Surcharge/ Embankment 2 - WB Outside Widening AreaNo19-May-1714-Sep-17
IIIBWBO-EW110PH IIIB - Embankment (JYP-Universal) - WB Outside Widening AreaNo16-Nov-1513-Jun-17
IIIBWBO-EW120PH IIIB - Embankment (Universal - International) - WB Outside Widening AreaNo18-Apr-1614-Aug-17
IIIBWBO-EW140PH IIIB - Pond Excav/Embank JYP to Universal - WB Outside WideningNo19-Sep-1614-Sep-17
IIIBWBO-SP100PH IIIB - Drainage (JYP-Universal) - WB Outside Widening Area (SR528)No16-May-1611-Jun-17
IIIBWBO-SP110PH IIIB - Drainage (Universal - International) - WB Outside Widening Area (SR528)No07-Mar-1614-Jun-17
IIIBWBO-ST1PH IIIB - Construct Crane Access - WB Outside Widening Area (Bridge over International DR)No18-Jul-1611-Jun-17
IIIBWBO-ST10PH IIIB - Production Pile - WB Outside Widening Area (Bridge over universal BLVD)No12-Sep-1616-Aug-17
IIIBWBO-ST11PH IIIB - Pier 2, (F/R/P)(Footer, Column & Pier Cap) - WB Outside Widening Area (Bridge over Universal BLVD)No01-Nov-1616-Aug-17
IIIBWBO-ST12PH IIIB - Curing for Pier 2, (Footer, Column & Pier Cap) - WB Outside Widening Area (Bridge over Universal BLVD)No08-Dec-1621-Aug-17
IIIBWBO-ST13PH IIIB - Removal for Concrete Forms for Pier 2, (Footer, Column & Pier Cap) - WB Outside Widening Area (Bridge over UniNo15-Dec-1621-Aug-17
IIIBWBO-ST14PH IIIB - Temp Sheet Pile Removal - WB Outside Widening Area (Bridge over universal BLVD)No16-Dec-1611-Jun-17
IIIBWBO-ST3PH IIIB - Temp Sheet Pile - WB Outside Widening Area (Bridge over International DR)No27-Jun-1611-Jun-17
IIIBWBO-ST4PH IIIB - Production Pile - WB Outside Widening Area (Bridge over International DR)No01-May-1611-Jun-17
IIIBWBO-ST5PH IIIB - Pier 2, (F/R/P)(Footer, Column & Pier Cap) - WB Outside Widening Area (Bridge over International DR)No28-Jun-1618-Sep-17
IIIBWBO-ST6PH IIIB - Construct Crane Access - WB Outside Widening Area (Bridge over universal BLVD)No15-Aug-1611-Aug-17
IIIBWBO-ST7PH IIIB - Test Pile - WB Outside Widening Area (Bridge over universal BLVD)No08-Sep-1611-Jun-17
IIIBWBO-ST8PH IIIB - Temp Sheet Pile - WB Outside Widening Area (Bridge over universal BLVD)No28-Oct-1611-Aug-17
IIIBWBO-ST9PH IIIB - Temp Sheet Pile Removal - WB Outside Widening Area (Bridge over International DR)No27-Jul-1626-Sep-17
IIICR-EW100PH IIIC - Embankment - Ramp FNo05-Apr-1629-Dec-17
PRE-FA-001Fabricate and Deliver 506 Bridge Drainage SystemNo25-Jan-1711-Jun-17
PRE-FA-00123Fabricate and Deliver 455 Structure Foundations Prestressed Concrete Piling 18" (Structures 750089 & 750216)No15-Feb-1611-Jun-17
PRE-FA-00132Fabricate and Deliver 455 Structure Foundations Prestressed Concrete Piling 24" (Structure 750631-Shingle Creek)No21-Oct-1511-Jun-17
PRE-FA-00145Fabricate and Deliver 455 Structure Foundations Steel Pile HP 14X89 (Structures 750088 and 750215 I-Drive)No15-Feb-1611-Jun-17
PRE-FA-00147Fabricate and Deliver 455 Structure Foundations Steel Pile HP 12X53 (Structure 750629-Ramp S JYP)No17-Jan-1611-Jun-17
PRE-FA-00154Fabricate and Deliver 455 Structure Foundations Steel Pile HP 12X53 (Structures 750091 and 750218-JYP)No16-Nov-1511-Jun-17
PRE-FA-00174Fabricate and Deliver 455 Structure Foundations Steel Pile HP 12X53 (Structure 750630-Ramp T JYP)No16-Nov-1511-Jun-17
PRE-FA-007Fabricate and Deliver 400 Concrete Structures (Bearing Pads)No09-Mar-1611-Jun-17
PRE-FA-008Fabricate and Deliver 450 Precast Prestressed Florida I Beam 36" (Structures 750088 & 750215- I-Drive)No21-Feb-1611-Jun-17
PRE-FA-009Fabricate and Deliver 450 Precast Prestressed Florida I Beam 45" (Structures 750089, & 750216- Universal/Orangewood)No21-Feb-1611-Jun-17
PRE-FA-010Fabricate and Deliver 450 Precast Prestressed Beams TY II (Structures 750631-Shingle Creek)No21-Feb-1611-Jun-17
PRE-FA-011Fabricate and Deliver 450 Precast Prestressed Florida I Beam 36" (Structures 750091 & 750218- JYP)No21-Feb-1611-Jun-17
PRE-FA-0111Fabricate and Deliver 455 Temp Sheet Pile/CriticalNo26-Jan-1611-Jun-17
PRE-FA-012Fabricate and Deliver 450 Precast Prestressed Florida I Beam 36" (Structures 750629 Ramp S JYP & 750630 Ramp T JYP)No21-Feb-1611-Jun-17
PRE-FA-013Fabricate and Deliver 455 Auger Cast Piles (w/noise wall submittal)No26-Jan-1611-Jun-17
PRE-FA-014Fabricate and Deliver 534 Noise and Perimeter WallsNo01-Feb-1611-Jun-17
PRE-FA-015Fabricate and Deliver 548 Retaining/MSE Wall SystemsNo18-Jul-1611-Jun-17
PRE-FA-016Fabricate and Deliver 641 Prestressed Concrete PolesNo22-Aug-1611-Jun-17
PRE-FA-019Fabricate and Deliver 700 Highway Signing (Single, Multi, Panel, and Overhead)No09-Mar-1711-Jun-17
PRE-FA-021Fabricate and Deliver 05500 Metal FabricationsNo20-Mar-1711-Jun-17
PRE-FA-022Fabricate and Deliver 133420 Pre-Engineered Precast Concrete StructureNo27-Feb-1711-Jun-17
PRE-FA-023Fabricate and Deliver 263213 Engine GeneratorNo22-May-1711-Jun-17
PRE-FA-024Fabricate and Deliver 633 Communication CableNo22-Aug-1611-Jun-17
PRE-FA-025Fabricate and Deliver 635 Pull, Splice, & Junction BoxesNo22-Aug-1611-Jun-17
PRE-FA-029Fabricate and Deliver 033000 Cast-In-Place ConcreteNo15-May-1711-Jun-17
PRE-FA-031Fabricate and Deliver 081100 Metal Doors and FramesNo16-Jan-1711-Jun-17
PRE-FA-032Fabricate and Deliver 099100 Painting Product Data and SampleNo16-Jan-1711-Jun-17
PRE-FA-034Fabricate and Deliver 231113 Fuel Oil PipingNo05-May-1711-Jun-17
PRE-FA-035Fabricate and Deliver 231323 Aboveground Diesel Storage Tank and PipingNo05-May-1711-Jun-17
PRE-FA-036Fabricate and Deliver 232000 Piping and SpecialtiesNo25-Jan-1711-Jun-17
PRE-FA-037Fabricate and Deliver 233113 Ductwork Product Data and Shop DrawingNo22-May-1711-Jun-17
PRE-FA-038Fabricate and Deliver 238119 Packaged Air ConditionersNo17-Jan-1711-Jun-17
PRE-FA-039Fabricate and Deliver 260536 Cable TraysNo09-Feb-1711-Jun-17
PRE-FA-040Fabricate and Deliver 264113 Lighting Protection System Product Data and Shop DrawingNo19-Apr-1711-Jun-17
PRE-FA-041Fabricate and Deliver 682 CCTV CameraNo22-Aug-1611-Jun-17
PRE-FA-042Fabricate and Deliver 781 DMSNo18-May-1711-Jun-17
PRE-FA-044Fabricate and Deliver 783 ITS Fiber Optic CableNo22-Aug-1611-Jun-17
PRE-FA-046Fabricate and Deliver 784 ITS Managed Ethernet Hub SwitchNo22-Aug-1611-Jun-17
PRE-FA-047Fabricate and Deliver 685 ITS Uninterruptible Power Source (UPS)No22-Aug-1611-Jun-17
PRE-FA-049Fabricate and Deliver 262913 ITS Standby Generator Product Data and Shop DrawingNo22-Aug-1611-Jun-17
PRE-FA-050Fabricate and Deliver 400 Concrete Structures (SIP Metal Forms)No14-Dec-1511-Jun-17
PRE-PS-001Prepare and Submit 506 Bridge Drainage SystemNo08-Aug-1611-Jun-17
PRE-PS-002Prepare and Submit 455 Pile Installation Plan (Structures 750089 & 750216-Universal/Orangewood)No20-Sep-1511-Jun-17
PRE-PS-003Prepare and Submit 455 Pile Installation Plan (Structures 750091 & 750218-John Young Parkway)No20-Sep-1511-Jun-17
PRE-PS-004Prepare and Submit 455 Pile Installation Plan (Structure 750629- Ramp S JYP)No20-Sep-1511-Jun-17
PRE-PS-005Prepare and Submit 455 Pile Installation Plan (Structure 750630- Ramp T JYP)No20-Sep-1511-Jun-17
PRE-PS-006Prepare and Submit Precast ErectionNo03-Jun-1611-Jun-17
PRE-PS-007Prepare and Submit 400 Concrete Structures (Bearing Pads)No11-Jan-1611-Jun-17
PRE-PS-008Prepare and Submit 450 Precast Prestressed Florida I Beam 36" (Structures 750088 & 750215- I-Drive)No01-Oct-1511-Jun-17
PRE-PS-009Prepare and Submit 450 Precast Prestressed Florida I Beam 45" (Structures 750089, & 750216- Universal/Orangewood)No01-Oct-1511-Jun-17
PRE-PS-010Prepare and Submit 450 Precast Prestressed Beams TY II (Structures 750631-Shingle Creek)No01-Oct-1511-Jun-17
PRE-PS-011Prepare and Submit 450 Precast Prestressed Florida I Beam 36" (Structures 750091 & 750218- JYP)No01-Oct-1511-Jun-17
PRE-PS-012Prepare and Submit 450 Precast Prestressed Florida I Beam 36" (Structures 750629 Ramp S JYP & 750630 Ramp T JYP)No20-Sep-1511-Jun-17
PRE-PS-013Prepare and Submit 455 Auger Cast Piles (w/noise wall submittal)No07-Oct-1511-Jun-17
PRE-PS-014Prepare and Submit 534 Noise and Perimeter WallsNo21-Oct-1511-Jun-17
PRE-PS-015Prepare and Submit 548 Retaining/MSE Wall SystemsNo17-Apr-1611-Jun-17
PRE-PS-016Prepare and Submit 641 Prestressed Concrete PolesNo15-Feb-1611-Jun-17
PRE-PS-017Prepare and Submit 646 Aluminum Pedestal PolesNo20-Mar-1711-Jun-17
PRE-PS-018Prepare and Submit 650 Traffic SignalsNo15-Feb-1611-Jun-17
PRE-PS-019Prepare and Submit 700 Highway Signing (Single, Multi, Panel, and Overhead)No11-Jan-1611-Jun-17
PRE-PS-021Prepare and Submit 05500 Metal FabricationsNo16-May-1611-Jun-17
PRE-PS-022Prepare and Submit 133420 Pre-Engineered Precast Concrete StructureNo03-Jun-1611-Jun-17
PRE-PS-023Prepare and Submit 263213 Engine GeneratorNo18-Nov-1611-Jun-17
PRE-PS-024Prepare and Submit 633 Communication CableNo15-Feb-1611-Jun-17
PRE-PS-025Prepare and Submit 635 Pull, Splice, & Junction BoxesNo18-Jan-1611-Jun-17
PRE-PS-026Prepare and Submit 653 Pedestrian SignalsNo20-Mar-1711-Jun-17
PRE-PS-027Prepare and Submit 663 Signal Priority and Preemption SystemsNo28-Jan-1611-Jun-17
PRE-PS-028Prepare and Submit 665 Pedestrian DetectorNo20-Mar-1711-Jun-17
PRE-PS-029Prepare and Submit 033000 Cast-In-Place ConcreteNo26-Sep-1611-Jun-17
PRE-PS-030Prepare and Submit 042200 MasonryNo20-Feb-1711-Jun-17
PRE-PS-031Prepare and Submit 081100 Metal Doors and FramesNo19-Oct-1611-Jun-17
PRE-PS-032Prepare and Submit 099100 Painting Product Data and SampleNo19-Oct-1611-Jun-17
PRE-PS-033Prepare and Submit 101400 SignageNo27-Feb-1711-Jun-17
PRE-PS-034Prepare and Submit 231113 Fuel Oil PipingNo13-Feb-1711-Jun-17
PRE-PS-035Prepare and Submit 231323 Aboveground Diesel Storage Tank and PipingNo13-Feb-1711-Jun-17
PRE-PS-036Prepare and Submit 232000 Piping and SpecialtiesNo16-Jan-1711-Jun-17
PRE-PS-037Prepare and Submit 233113 Ductwork Product Data and Shop DrawingNo20-Feb-1711-Jun-17
PRE-PS-038Prepare and Submit 238119 Packaged Air ConditionersNo09-Jan-1711-Jun-17
PRE-PS-039Prepare and Submit 260536 Cable TraysNo16-Jan-1711-Jun-17
PRE-PS-040Prepare and Submit 264113 Lighting Protection System Product Data and Shop DrawingNo20-Mar-1711-Jun-17
PRE-PS-041Prepare and Submit 682 CCTV CameraNo01-Aug-1611-Jun-17
PRE-PS-042Prepare and Submit 781 DMSNo22-Aug-1611-Jun-17
PRE-PS-044Prepare and Submit 783 ITS Fiber Optic CableNo08-Feb-1611-Jun-17
PRE-PS-045Prepare and Submit 660 ITS Vehicle Detection SystemNo01-Aug-1611-Jun-17
PRE-PS-046Prepare and Submit 684 ITS Managed Ethernet Hub SwitchNo01-Aug-1611-Jun-17
PRE-PS-047Prepare and Submit 785 ITS Uninterruptible Power Source (UPS)No01-Aug-1611-Jun-17
PRE-PS-049Prepare and Submit 639 ITS Standby Generator Product Data and Shop DrawingNo21-Mar-1611-Jun-17
PRE-PS-050Prepare and Submit 400 Concrete Structures (SIP Metal Forms)No20-Sep-1511-Jun-17
PRE-RA-001Review and Approve 506 Bridge Drainage SystemNo19-Jan-1711-Jun-17
PRE-RA-002Review and Approve 455 Pile Installation Plan (Structures 750089 & 750216-Universal/Orangewood)No27-Sep-1511-Jun-17
PRE-RA-003Review and Approve 455 Pile Installation Plan (Structures 750091 & 750218-John Young Parkway)No27-Sep-1511-Jun-17
PRE-RA-004Review and Approve 455 Pile Installation Plan (Structure 750629- Ramp S JYP)No27-Sep-1511-Jun-17
PRE-RA-005Review and Approve 455 Pile Installation Plan (Structure 750630- Ramp T JYP)No27-Sep-1511-Jun-17
PRE-RA-007Review and Approve 400 Concrete Structures (Bearing Pads)No02-Mar-1611-Jun-17
PRE-RA-008Review and Approve 450 Precast Prestressed Florida I Beam 36" (Structures 750088 & 750215- I-Drive)No18-Oct-1511-Jun-17
PRE-RA-009Review and Approve 450 Precast Prestressed Florida I Beam 45" (Structures 750089, & 750216- Universal/Orangewood)No18-Oct-1511-Jun-17
PRE-RA-010Review and Approve 450 Precast Prestressed Beams TY II (Structures 750631-Shingle Creek)No18-Oct-1511-Jun-17
PRE-RA-011Review and Approve 450 Precast Prestressed Florida I Beam 36" (Structures 750091 & 750218- JYP)No18-Oct-1511-Jun-17
PRE-RA-012Review and Approve 450 Precast Prestressed Florida I Beam 36" (Structures 750629 Ramp S JYP & 750630 Ramp T JYP)No18-Oct-1511-Jun-17
PRE-RA-013Review and Approve 455 Auger Cast Piles (w/noise wall submittal)No21-Oct-1511-Jun-17
PRE-RA-014Review and Approve 534 Noise and Perimeter WallsNo21-Oct-1511-Jun-17
PRE-RA-015Review and Approve 548 Retaining/MSE Wall SystemsNo29-Apr-1611-Jun-17
PRE-RA-016Review and Approve 641 Prestressed Concrete PolesNo16-Feb-1611-Jun-17
PRE-RA-017Review and Approve 646 Aluminum Pedestal PolesNo23-Mar-1711-Jun-17
PRE-RA-018Review and Approve 650 Traffic SignalsNo23-Mar-1724-Jun-17
PRE-RA-019Review and Approve 700 Highway Signing (Single, Multi, Panel, and Overhead)No18-Jan-1611-Jun-17
PRE-RA-021Review and Approve 05500 Metal FabricationsNo08-Jun-1611-Jun-17
PRE-RA-022Review and Approve 133420 Pre-Engineered Precast Concrete StructureNo12-Jan-1711-Jun-17
PRE-RA-023Review and Approve 263213 Engine GeneratorNo01-Feb-1711-Jun-17
PRE-RA-024Review and Approve 633 Communication CableNo16-Feb-1611-Jun-17
PRE-RA-025Review and Approve 635 Pull, Splice, & Junction BoxesNo16-Feb-1611-Jun-17
PRE-RA-026Review and Approve 653 Pedestrian SignalsNo23-Mar-1711-Jun-17
PRE-RA-027Review and Approve 663 Signal Priority and Preemption SystemsNo16-Feb-1615-Jun-17
PRE-RA-028Review and Approve 665 Pedestrian DetectorNo23-Mar-1711-Jun-17
PRE-RA-029Review and Approve 033000 Cast-In-Place ConcreteNo26-Oct-1611-Jun-17
PRE-RA-031Review and Approve 081100 Metal Doors and FramesNo26-Oct-1611-Jun-17
PRE-RA-032Review and Approve 099100 Painting Product Data and SampleNo26-Oct-1611-Jun-17
PRE-RA-033Review and Approve 101400 SignageNo29-Mar-1711-Jun-17
PRE-RA-034Review and Approve 231113 Fuel Oil PipingNo21-Apr-1711-Jun-17
PRE-RA-035Review and Approve 231323 Aboveground Diesel Storage Tank and PipingNo28-Mar-1711-Jun-17
PRE-RA-036Review and Approve 232000 Piping and SpecialtiesNo18-Jan-1711-Jun-17
PRE-RA-037Review and Approve 233113 Ductwork Product Data and Shop DrawingNo22-May-1711-Jun-17
PRE-RA-038Review and Approve 238119 Packaged Air ConditionersNo12-Jan-1711-Jun-17
PRE-RA-039Review and Approve 260536 Cable TraysNo18-Jan-1711-Jun-17
PRE-RA-040Review and Approve 264113 Lighting Protection System Product Data and Shop DrawingNo28-Mar-1711-Jun-17
PRE-RA-041Review and Approve 682 CCTV CameraNo03-Aug-1611-Jun-17
PRE-RA-042Review and Approve 781 DMSNo25-Aug-1611-Jun-17
PRE-RA-044Review and Approve 633 ITS Fiber Optic CableNo26-Jul-1611-Jun-17
PRE-RA-045Review and Approve 660 ITS Vehicle Detection SystemNo03-Aug-1611-Jun-17
PRE-RA-046Review and Approve 684 ITS Managed Ethernet Hub SwitchNo03-Aug-1611-Jun-17
PRE-RA-047Review and Approve 685 ITS Uninterruptible Power Source (UPS)No03-Aug-1611-Jun-17
PRE-RA-049Review and Approve 639 ITS Standby Generator Product Data and Shop DrawingNo30-Mar-1611-Jun-17
PRE-RA-050Review and Approve 400 Concrete Structures (SIP Metal Forms)No30-Nov-1511-Jun-17
TF-CO-003Begin Electrical (Stub Outs & Site Electrical)No23-May-1711-Jun-17
TF-CO-005Install Upright 2 D.S.No22-Mar-1711-Jun-17
TF-CO-007Install Upright 3 D.S.No24-Mar-1711-Jun-17
TF-CO-011AS Build D.S.No30-Mar-1711-Jun-17
TF-FA-001Fabricate and Deliver Precast ErectionNo30-Jan-1711-Jun-17
TF-RA-001Review and Approve Precast ErectionNo12-Jan-1711-Jun-17
USATT-CO-001ATT FloridaNo29-Oct-1511-Jun-17
USB-CO-001Bright houseNo27-Oct-1511-Jun-17
USDED-CO-001Duke Energy Distribution (A)No01-Dec-1511-Jun-17
USDED-CO-002Duke Energy Distribution (B)No30-Nov-1511-Jun-17
USDET-CO-001Duke Energy Transmission Phase 1No12-Oct-1511-Jun-17
USOUC-CO-001OUC Remove Water Main @ JYP (Sta 325 - 329)No29-Oct-1511-Jun-17
USS-CO-001SummitNo29-Oct-1511-Jun-17
UST-CO-001TECONo07-Dec-1511-Jun-17
USV-CO-001VerizonNo07-Dec-1511-Jun-17

This table lists activities with non-zero relationship lag, highlighting the intentional or unintentional delays (or overlaps) between tasks. Lag reflects the gap between a predecessor and its successor, and it may be contributing to scheduling bottlenecks.

Highlighted in red are activities with negative lag - meaning the successor is scheduled to start before the predecessor has finished. This can be intentional, to optimize parallel work, or unintentional, which might result in resource conflicts or quality issues. In either case, monitoring negative lag is crucial for identifying potential risks and ensuring the project schedule remains realistic and achievable

Activity IDActivity DescriptionOn LPRelationship TypePredecessor Activity IDPredecessor Activity DescriptionRelationship Lag
IVEBM-TC120PH IV - MOT Shift for Phase - EB Median WideningNoSS IVEBM-TC110PH IV - Temp Striping for Phase - EB Median Widening1

This table lists the calendars, their weekly schedule and holidays used in the project and any default calendars. Calendars are essential for resource allocation, as they define working days, holidays, and other time-related constraints.

Highlighted in green are project default and global/base default calendars, if any.
Highlighted in red are calendars that are not used by any activity. This situation may indicate that the calendar is obsolete or not relevant to the current project schedule. It is important to review these calendars and determine if they should be removed or updated to reflect the current project requirements.

Recommended actions: Review the calendars listed in this table and ensure that they are relevant and up-to-date. Remove any obsolete calendars and update the project schedule to reflect the current working days and holidays.

IDScopeDefaultLinked ActivitiesNameLast updated
9959BaseNo905 day FDOT with Holiday22-Aug-16
1559BaseNo-5 day FDOT with Holidays18-May-13
8489BaseNo-Standard 7-Day Workweek19-Sep-16
21490ProjectYes836Beachline 5-days with Holidays15-Dec-15
21489ProjectNo197Beachline 7-Day Workweek15-Dec-15
21491ProjectNo89Beachline Night-Shift 5-Days with Holidays15-Dec-15

1559: 5 day FDOT with Holidays

Day Hours: 8, Week Hours: 40, Month Hours: 172, Year Hours: 2024

There are non-working days going back prior to 01-Jan-2020. You should consider migrating to a newer calendar.

Weekly Schedule

DayTime Slots
SunNo Work
Mon08:00-12:00, 13:00-17:00
Tue08:00-12:00, 13:00-17:00
Wed08:00-12:00, 13:00-17:00
Thu08:00-12:00, 13:00-17:00
Fri08:00-12:00, 13:00-17:00
SatNo Work

Holidays and No Work days

DayHoliday
01-Jan-20New Year's Day
25-May-20Memorial Day
03-Jul-20-
07-Sep-20Labor Day
26-Nov-20Thanksgiving Day
27-Nov-20-
25-Dec-20Christmas Day
01-Jan-21New Year's Day

8489: Standard 7-Day Workweek

Day Hours: 8, Week Hours: 56, Month Hours: 172, Year Hours: 2000

There are non-working days going back prior to 01-Jan-2020. You should consider migrating to a newer calendar.

Weekly Schedule

DayTime Slots
Sun08:00-16:00
Mon08:00-16:00
Tue08:00-16:00
Wed08:00-16:00
Thu08:00-16:00
Fri08:00-16:00
Sat08:00-16:00

Holidays and No Work days

[no data]

9959: 5 day FDOT with Holiday

Day Hours: 8, Week Hours: 40, Month Hours: 172, Year Hours: 2024

There are non-working days going back prior to 01-Jan-2020. You should consider migrating to a newer calendar.

Weekly Schedule

DayTime Slots
SunNo Work
Mon08:00-12:00, 13:00-17:00
Tue08:00-12:00, 13:00-17:00
Wed08:00-12:00, 13:00-17:00
Thu08:00-12:00, 13:00-17:00
Fri08:00-12:00, 13:00-17:00
SatNo Work

Holidays and No Work days

DayHoliday
01-Jan-20New Year's Day
20-Jan-20Martin Luther King Jr. Day
25-May-20Memorial Day
03-Jul-20-
07-Sep-20Labor Day
11-Nov-20Veterans Day
26-Nov-20Thanksgiving Day
27-Nov-20-
25-Dec-20Christmas Day
01-Jan-21New Year's Day

21489: Beachline 7-Day Workweek

Day Hours: 8, Week Hours: 56, Month Hours: 172, Year Hours: 2000

Weekly Schedule

DayTime Slots
Sun08:00-16:00
Mon08:00-16:00
Tue08:00-16:00
Wed08:00-16:00
Thu08:00-16:00
Fri08:00-16:00
Sat08:00-16:00

Holidays and No Work days

[no data]

21490: Beachline 5-days with Holidays

Day Hours: 8, Week Hours: 40, Month Hours: 172, Year Hours: 2024

There are non-working days going back prior to 01-Jan-2020. You should consider migrating to a newer calendar.

Weekly Schedule

DayTime Slots
SunNo Work
Mon08:00-12:00, 13:00-17:00
Tue08:00-12:00, 13:00-17:00
Wed08:00-12:00, 13:00-17:00
Thu08:00-12:00, 13:00-17:00
Fri08:00-12:00, 13:00-17:00
SatNo Work

Holidays and No Work days

DayHoliday
01-Jan-20New Year's Day
20-Jan-20Martin Luther King Jr. Day
25-May-20Memorial Day
03-Jul-20-
07-Sep-20Labor Day
11-Nov-20Veterans Day
26-Nov-20Thanksgiving Day
27-Nov-20-
25-Dec-20Christmas Day
01-Jan-21New Year's Day

21491: Beachline Night-Shift 5-Days with Holidays

Day Hours: 8, Week Hours: 40, Month Hours: 172, Year Hours: 2024

There are non-working days going back prior to 01-Jan-2020. You should consider migrating to a newer calendar.

Weekly Schedule

DayTime Slots
SunNo Work
Mon00:00-06:00, 22:00-00:00
Tue00:00-06:00, 22:00-00:00
Wed00:00-06:00, 22:00-00:00
Thu00:00-06:00, 22:00-00:00
Fri00:00-06:00, 22:00-00:00
SatNo Work

Holidays and No Work days

DayHoliday
01-Jan-20New Year's Day
20-Jan-20Martin Luther King Jr. Day
25-May-20Memorial Day
03-Jul-20-
07-Sep-20Labor Day
11-Nov-20Veterans Day
26-Nov-20Thanksgiving Day
27-Nov-20-
25-Dec-20Christmas Day
01-Jan-21New Year's Day

Each row represents a unique resource and summarizes how it is being utilized across activities.

Highlighted in red are resources that P6 will not allow you to assign tasks to (i.e. those not cost‑linked or not auto‑compute‑active).
The Assignable in P6 column shows "Yes" for resources P6 treats as assignable and "No" for those it hides.

TypeIDNameAssigned ActivitiesAssignable in P6
LaborAsphaltAsphalt team71Yes
LaborBaseRoad base team81Yes
LaborCarrCarr24Yes
LaborCIFCIF2Yes
LaborConcreteConcrete team254Yes
LaborDemoDemo Team72Yes
LaborDrainageDrainage team54Yes
LaborElectricalElectrical team16Yes
LaborEmbankmentEmbankment58Yes
LaborExcavationExcavation team23Yes
LaborJVDJVD23Yes
LaborMOTTraffic Control Team107Yes
LaborPaffPaff26Yes
LaborPilePile team64Yes
LaborSlagterSlagter26Yes
LaborStabilizationStabilization team69Yes
LaborUS&SUS & S101Yes
MatTPKCOTPK COST1041Yes

This report compares each resource's scheduled workload against their available capacity on a month-by-month basis. We calculate capacity using each resource's work calendar (their working days and hours), shift schedules, and defined production or labor rates. Remaining activity work is then spread across the months that the activity is scheduled to run. Whenever the total assigned units in a given month exceed the resource's calculated capacity, that resource is flagged as overallocated.

Demand is the total work assigned to a resource in a month.
Limit is that resource's available capacity.
Overage is the actual resource overallocation - the amount by which Demand exceeds Limit.

Resource overallocation can lead to missed deadlines, reduced quality, and team burnout. By clearly highlighting these overbooked periods, this report helps you take corrective action: adjust task start or finish dates, redistribute work to less-busy teams, extend deadlines, or bring in additional support.

Resource IDResource NameMonthDemandLimitOverageActivities
AsphaltAsphalt teamJun-2017468176292IBEBM-RW330 = 60, IBWBM-RW220 = 45, IBWBM-RW230 = 50, IIAR-AP100 = 20, IIBEBO-AP140 = 200, IIBR-AP110 = 20, IIBR-AP151 = 10, IICR-SP130 = 53, IIIAWBO-AP100 = 10
Jul-2017398168230IBR-AP110 = 50, IIBEBO-AP130 = 200, IIBR-AP130 = 20, IIBR-AP140 = 20, IIBR-AP150 = 20, IIBR-AP170 = 20, IIBR-AP180 = 1, IICR-AP100 = 20, IICR-SP130 = 47
Aug-201719518411IIBEBO-AP120 = 175, IICR-AP120 = 20
Sep-201723516867IIBEBO-AP110 = 200, IIBEBO-AP120 = 25, IIBR-AP120 = 10
Oct-2017596176420IIBR-AP100 = 40, IIBR-AP120 = 30, IIDEBO-RW150 = 143, IIIBR-AP100 = 20, IIIBR-AP140 = 20, IIIBR-AP150 = 20, IIICR130 = 83, IIICR170 = 40, IIICR180 = 200
Nov-2017434176258IIDEBO-RW150 = 78, IIIBWBO-AP100 = 80, IIICR130 = 117, IIICR170 = 160
Dec-2017610168442IIIBR-AP110 = 20, IIIBR-AP120 = 20, IIIBWBO-AP100 = 20, IIICR110 = 150, IIICR140 = 200, IIICR200 = 200
Jan-2018567184383IIIBR-AP130 = 20, IIIBR-AP160 = 20, IIICR-AP100 = 20, IIICR110 = 50, IIICR120 = 107, IIICR160 = 150, IIICR190 = 200
Feb-2018317160157IIIBWBO-AP110 = 100, IIICR-AP110 = 20, IIICR120 = 93, IIICR150 = 53, IIICR160 = 50
Aug-2018310184126IVEBM-AP100 = 30, IVEBO-AP100 = 80, IVEBO-PM110 = 50, IVWBM-AP100 = 40, IVWBO-AP100 = 60, IVWBO-PM110 = 50
CarrCarrJun-2017534176358IIBR-ITS10 = 70, IIBR-ITS20 = 40, IIBR-ITS30 = 20, IIBR-ITS40 = 4, IIIBR-ITS1000 = 200, IIIBR-ITS1010 = 100, IIIBR-ITS1020 = 100
Jul-2017356168188IIBR-ITS40 = 6, IIBR-ITS50 = 90, IIIBR-ITS1010 = 100, IIIBR-ITS1020 = 100, IIIBR-ITS80 = 60
Aug-201723018446IIBR-ITS50 = 110, IIBR-ITS60 = 120
Sep-201720016832IIBR-ITS60 = 80, IIIBR-ITS90 = 120
Oct-201725517679IIBR-ITS70 = 175, IIIBR-ITS90 = 80
Nov-2017285176109IIBR-ITS70 = 25, IIBR-ITS80 = 200, IIBR-ITS90 = 60
Dec-2017280168112IIBR-ITS90 = 140, IIIBR-ITS100 = 140
Feb-201820016040IIIBR-ITS110 = 100, IIIBR-ITS130 = 100
Mar-201822017644IIIBR-ITS130 = 100, IIIBR-ITS140 = 120
Apr-201821016842IIIBR-ITS140 = 80, IIIBR-ITS150 = 100, IIIBR-ITS160 = 30
May-201823018446IIIBR-ITS160 = 70, IIIBR-ITS170 = 100, IIIBR-ITS180 = 60
Jun-201820016832IIIBR-ITS180 = 40, IIIBR-ITS190 = 160
ConcreteConcrete teamJun-2017475176299IIBEBO-ST140 = 70, IIBEBO-ST160 = 10, IIBEBO-ST360 = 50, IIBEBO-ST400 = 20, IIBEBO-ST420 = 40, IIBEBO-ST440 = 100, IIBEBO-ST730 = 40, IIIAWBO-ST520 = 15, IIIAWBO-ST570 = 40, IIIAWBO-ST580 = 40, IIIAWBO-ST700 = 50
Jul-2017816168648IIBEBO-ST160 = 60, IIBEBO-ST190 = 70, IIBEBO-ST200 = 70, IIBEBO-ST480 = 18, IIBEBO-ST500 = 150, IIBEBO-ST520 = 8, IIBEBO-ST730 = 30, IIBEBO-W130 = 150, IIIAWBO-ST111 = 50, IIIAWBO-ST120 = 50, IIIAWBO-ST570 = 60, IIIAWBO-ST580 = 60, IIIAWBO-ST620 = 40
Aug-2017833184649IIBEBO-ST250 = 18, IIBEBO-ST270 = 113, IIBEBO-ST520 = 33, IIBEBO-ST530 = 50, IIBEBO-ST540 = 50, IIBEBO-ST570 = 10, IIBEBO-ST580 = 30, IIBEBO-ST720 = 70, IIBEBO-W140 = 210, IIIAWBO-ST120 = 50, IIIAWBO-ST130 = 50, IIIAWBO-ST140 = 100, IIIAWBO-ST170 = 30, IIIBWBO-ST220 = 20
Sep-20171162168994IIBEBO-ST270 = 88, IIBEBO-ST330 = 50, IIBEBO-ST340 = 40, IIBEBO-ST390 = 30, IIBEBO-W140 = 10, IIBEBO-W150 = 190, IIIAWBO-ST150 = 27, IIIAWBO-ST160 = 113, IIIAWBO-ST170 = 40, IIIBWBO-ST220 = 30, IIIBWBO-ST240 = 50, IIIBWBO-ST260 = 50, IIIBWBO-ST270 = 45, IIIBWBO-ST28 = 60, IIIBWBO-ST300 = 50, IIIBWBO-ST330 = 30, IIIBWBO-ST370 = 60, IIIBWBO-ST750 = 150, IIIBWBO-W101 = 20, IIIBWBO-W110 = 30
Oct-201716211761445IIBEBO-W150 = 30, IIDEBO-ST190 = 50, IIDEBO-ST200 = 50, IIDEBO-ST210 = 20, IIIAWBO-ST160 = 108, IIIAWBO-ST171 = 50, IIIAWBO-ST181 = 100, IIIAWBO-ST211 = 40, IIIBWBO-ST211 = 70, IIIBWBO-ST250 = 70, IIIBWBO-ST270 = 105, IIIBWBO-ST28 = 140, IIIBWBO-ST280 = 40, IIIBWBO-ST320 = 70, IIIBWBO-ST330 = 40, IIIBWBO-ST340 = 18, IIIBWBO-ST350 = 120, IIIBWBO-ST360 = 10, IIIBWBO-ST370 = 20, IIIBWBO-ST400 = 150, IIIBWBO-ST430 = 50, IIIBWBO-W101 = 80, IIIBWBO-W110 = 190
Nov-2017854176678IIDEBO-ST210 = 30, IIDEBO-ST220 = 50, IIDEBO-ST230 = 18, IIDEBO-ST240 = 15, IIDEBO-ST340 = 70, IIIBWBO-ST100 = 135, IIIBWBO-ST280 = 30, IIIBWBO-ST310 = 70, IIIBWBO-ST350 = 80, IIIBWBO-ST380 = 18, IIIBWBO-ST390 = 8, IIIBWBO-ST410 = 70, IIIBWBO-ST430 = 30, IIIBWBO-ST480 = 160, IIIBWBO-W111 = 70
Dec-2017783168615IIDEBO-ST240 = 135, IIDEBO-ST330 = 60, IIIBWBO-ST100 = 15, IIIBWBO-ST390 = 193, IIIBWBO-ST440 = 50, IIIBWBO-ST450 = 80, IIIBWBO-ST510 = 30, IIIBWBO-ST520 = 70, IIIBWBO-ST560 = 120, IIIBWBO-ST610 = 23, IIIBWBO-ST690 = 8
Jan-2018650184466IIDEBO-ST250 = 60, IIDEBO-ST260 = 50, IIDEBO-ST290 = 30, IIDEBO-ST330 = 90, IIIBWBO-ST490 = 50, IIIBWBO-ST500 = 20, IIIBWBO-ST610 = 178, IIIBWBO-ST690 = 143, IIIBWBO-ST700 = 30
Feb-201825016090IIIBWBO-ST120 = 90, IIIBWBO-ST500 = 10, IIIBWBO-ST550 = 30, IIIBWBO-ST700 = 120
Apr-201821016842IVEBM-W150 = 100, IVEBM-W160 = 50, IVEBM-W170 = 60
May-201822018436IVEBM-W180 = 150, IVEBM-W190 = 50, IVEBM-W200 = 20
Jun-201821016842IVEBM-W200 = 80, IVEBM-W210 = 100, IVEBM-W220 = 30
DemoDemo TeamJun-2017290176114IBR-GC100 = 150, IIBR-GC140 = 20, IIIBWBO-GC100 = 80, IIICWBO-ST100 = 40
Jul-2017340168172IIBR-GC100 = 80, IIBR-GC170 = 100, IICR-GC100 = 20, IICR-GC170 = 20, IIIBWBO-GC100 = 20, IIICWBO-ST220 = 100
Aug-2017373184189IIDEBO-ST180 = 40, IIDEBO-ST300 = 20, IIIBWBO-ST180 = 20, IIIBWBO-ST190 = 80, IIIBWBO-ST640 = 50, IIIBWBO-ST650 = 80, IIIBWBO-ST660 = 50, IIIBWBO-ST670 = 33
Sep-2017457168289IIDEBO-ST300 = 80, IIDEBO-ST320 = 120, IIIBR-GC100 = 20, IIIBR-GC210 = 20, IIIBR-GC250 = 20, IIIBWBO-ST171 = 20, IIIBWBO-ST631 = 10, IIIBWBO-ST670 = 17, IIIBWBO-ST680 = 150
DrainageDrainage teamJun-2017754176578IBWBM-RW111 = 25, IIBEBO-SP100 = 150, IIBEBO-SP120 = 20, IIBEBO-SP160 = 200, IIBR-SP130 = 100, IIBR-SP210 = 30, IIBR-SP240 = 100, IIIBWBO-SP110 = 99, IIIBWBO-SP120 = 30
Jul-2017680168512IIBEBO-SP100 = 50, IIBEBO-SP130 = 160, IIBEBO-SP140 = 80, IIBR-SP100 = 50, IIBR-SP150 = 60, IICR-SP100 = 50, IICR-SP120 = 60, IIIBWBO-SP120 = 170
Aug-2017730184546IIBR-SP100 = 50, IIBR-SP150 = 40, IICR-SP120 = 40, IIIBWBO-SP130 = 200, IIIBWBO-SP140 = 200, IIIBWBO-SP150 = 200
Sep-2017380168212IIIBR-SP100 = 100, IIIBR-SP150 = 80, IIIBWBO-SP160 = 200
Dec-2017300168132IIIBR-SP130 = 100, IIIBR-SP160 = 100, IIICR-SP100 = 100
Apr-201826016892IVEBM-SP100 = 130, IVWBM-SP100 = 130
EmbankmentEmbankmentAug-2017575184391IIBR-EW100 = 220, IIBR-EW140 = 200, IIIBWBO-EW110 = 75, IIIBWBO-EW130 = 80
Jun-2017453176277IBR-EW100 = 220, IIBEBO-EW100 = 150, IIBR-EW130 = 3, IIBR-EW150 = 30, IIBR-EW210 = 30, IIIAWBO-ST24 = 20
Sep-201724516877IIIBWBO-EW101 = 45, IIIBWBO-EW102 = 80, IIIBWBO-EW130 = 120
Oct-2017463176287IIDEBO-RW150 = 143, IIIBR-EW100 = 50, IIIBR-EW150 = 50, IIIBWBO-EW102 = 90, IIIBWBO-EW103 = 130
PilePile teamJun-20171801764IIBEBO-ST2 = 30, IIBEBO-W100 = 150
Jul-201720016832IIBEBO-W110 = 150, IIBEBO-W120 = 50
Sep-201725016882IIIBWBO-ST2 = 30, IIIBWBO-ST26 = 100, IIIBWBO-W100 = 120
Oct-201722017644IIIBWBO-W100 = 30, IIIBWBO-W120 = 150, IIIBWBO-W130 = 40
BaseRoad base teamJun-201712921761116IBR-RW110 = 165, IIAR-RW110 = 20, IIBR-RW130 = 80, IIBR-RW190 = 30, IIBR-RW220 = 50, IIBR-RW310 = 30, IIBR-RW320 = 30, IIBR120 = 10, IICR-SP130 = 107, IICR100 = 150, IICR120 = 140, IIIAR100 = 30, IIIBR100 = 150, IIIBR110 = 150, IIICR100 = 150
Jul-2017688168520IBR-RW110 = 55, IIBR-RW170 = 80, IIBR-RW190 = 50, IIBR-RW220 = 30, IIBR-RW250 = 80, IICR-RW110 = 80, IICR-SP130 = 93, IICR100 = 10, IICR120 = 60, IIIBR100 = 50, IIIBR110 = 50, IIICR100 = 50
Aug-2017395184211IIBEBO-RW120 = 80, IIBR-RW110 = 5, IIBR-RW160 = 30, IICR-RW140 = 80, IIIAR120 = 200
Sep-2017495168327IIBEBM-GC110 = 20, IIBEBO-RW120 = 140, IIBR-RW110 = 15, IIBR-RW160 = 190, IIBR-RW280 = 50, IIBR-RW290 = 10, IIIAR110 = 60, IIIBR-RW190 = 10
Oct-2017996176820IIBEBM-GC110 = 10, IIBR-RW280 = 50, IIBR-RW290 = 140, IIDEBO-RW150 = 143, IIIBR-RW110 = 80, IIIBR-RW190 = 70, IIIBR-RW210 = 80, IIIBWBO-RW140 = 100, IIICR130 = 83, IIICR170 = 40, IIICR180 = 200
Nov-2017464176288IIDEBO-RW150 = 78, IIIBR-RW130 = 80, IIIBR-RW150 = 30, IIICR130 = 117, IIICR170 = 160
Dec-2017660168492IIIBR-RW150 = 50, IIIBR-RW230 = 30, IIIBWBM-GC110 = 30, IIICR110 = 150, IIICR140 = 200, IIICR200 = 200
Jan-2018777184593IIIBR-GC380 = 60, IIIBR-RW170 = 80, IIIBR-RW230 = 50, IIICR-RW110 = 80, IIICR110 = 50, IIICR120 = 107, IIICR160 = 150, IIICR190 = 200
Feb-2018317160157IIIBR-GC380 = 40, IIICR-RW130 = 80, IIICR120 = 93, IIICR150 = 53, IIICR160 = 50
SlagterSlagterOct-2017283176107IIBR-GC160 = 80, IIDEBO-RW150 = 143, IIIBR-GC120 = 20, IIIBR-GC290 = 20, IIIBR-GC320 = 20
StabilizationStabilization teamJun-2017681176505IBEBM-RW111 = 25, IBEBM-RW320 = 45, IBR-RW100 = 120, IIBEBO-RW112 = 110, IIBEBO-RW140 = 160, IIBEBO-RW160 = 60, IIBEBO-RW180 = 48, IIBR-RW120 = 20, IIBR-RW180 = 20, IIBR-RW200 = 20, IICR-SP130 = 53
Jul-2017322168154IIBEBO-RW110 = 70, IIBEBO-RW111 = 55, IIBEBO-RW130 = 90, IIBR-RW150 = 20, IIBR-RW240 = 20, IICR-RW100 = 20, IICR-SP130 = 47
Aug-2017480184296IIBEBO-RW110 = 150, IIBEBO-RW130 = 60, IIBEBO-RW150 = 70, IIBR-RW100 = 60, IIBR-RW140 = 120, IICR-RW150 = 20
Sep-2017280168112IIIBR-RW180 = 20, IIIBWBO-RW100 = 120, IIIBWBO-RW110 = 120, IIIBWBO-RW120 = 20
Oct-2017663176487IIDEBO-RW150 = 143, IIIBR-RW100 = 20, IIIBR-RW200 = 20, IIIBWBO-RW100 = 80, IIIBWBO-RW110 = 80, IIIBWBO-RW120 = 180, IIIBWBO-RW150 = 100, IIIBWBO-RW160 = 40
Nov-20171781762IIDEBO-RW150 = 78, IIIBR-RW120 = 20, IIIBR-RW140 = 20, IIIBWBO-RW160 = 60
Jul-2018300176124IVWBM-RW140 = 40, IVWBM-RW150 = 90, IVWBM-RW260 = 50, IVWBM-RW270 = 40, IVWBM-RW280 = 80
MOTTraffic Control TeamJun-2017290176114IICR-TC1000 = 10, IICR-TC130 = 10, IICR-TC160 = 10, IICR-TC170 = 100, IICR-TC180 = 10, IICR-TC200 = 10, IICR-TC210 = 10, IIIAWBO-TC100 = 10, IIIAWBO-TC110 = 10, IIIAWBO-TC120 = 10, IIIAWBO-TC130 = 30, IIIBWBO-TC110 = 30, IIIBWBO-TC120 = 40
Jul-2017275168107IBEBM-TC220 = 173, IIBEBO-ST480 = 12, IIBR-TC160 = 30, IIBR-TC170 = 10, IIBR-TC270 = 10, IICR-TC1020 = 10, IICR-TC120 = 10, IIIBR-TC120 = 10, IIIBR-TC130 = 10
Aug-201726918485IBEBM-TC220 = 27, IIAR-TC120 = 120, IIAR-TC130 = 90, IIBEBO-ST250 = 12, IICR-TC150 = 10, IICR-TC190 = 10
Sep-201726316895IIAR-TC120 = 80, IIAR-TC130 = 110, IIIAWBO-ST150 = 13, IIIBR-TC160 = 10, IIIBR-TC170 = 10, IIIBR-TC220 = 10, IIIBR-TC230 = 10, IIIBR-TC250 = 10, IIIBR-TC260 = 10
Nov-201719417618IIDEBO-ST230 = 12, IIIBR-TC270 = 10, IIIBR-TC280 = 10, IIIBR140 = 150, IIIBWBO-ST380 = 12
US&SUS & SJun-2017757176581IBR-IHM300 = 25, IIBR-EC10 = 30, IIBR-EHM360 = 10, IIBR-IB10 = 30, IIBR-IDS30 = 42, IIBR-IHM310 = 60, IIBR-IHM320 = 60, IIBR-SM380 = 130, IIIBR-EC20 = 60, IIIBR-IHM330 = 10, TF-CO-001 = 150, TF-CO-003 = 50, TF-CO-008 = 100
Oct-201712901761114IIBR-SM470 = 30, IIBR-SM480 = 30, IIBR-SM490 = 160, IIIBR-ET40 = 40, IIIBR-RES130 = 180, IIIBR-SM520 = 70, IIIBR-SM530 = 150, IVR-ET50 = 180, IVR-SM660 = 10, TF-CO-006 = 50, TF-CO-009 = 170, TF-CO-025 = 70, TF-CO-029 = 150
Sep-2017945168777IIBR-SM430 = 30, IIBR-SM440 = 54, IIBR-SM450 = 57, IIBR-SM460 = 54, IIIBR-ET40 = 120, IIIBR-IDS40 = 60, IIIBR-SM510 = 150, IIIBR-SM520 = 20, TF-CO-004 = 100, TF-CO-006 = 100, TF-CO-023 = 50, TF-CO-025 = 150
Jul-2017850168682IIBEBO-IE20 = 100, IIBR-CP10 = 60, IIBR-EHM360 = 170, IIBR-EHM370 = 30, IIBR-IB10 = 20, IIBR-IB180 = 150, IIBR-SM380 = 10, IIBR-SM390 = 80, IIBR-SM400 = 80, IIBR-SM410 = 30, IIIBR-IHM330 = 50, TF-CO-001 = 70
Aug-2017510184326IIBR-CP10 = 40, IIBR-EHM370 = 90, IIBR-IB180 = 50, IIBR-SM410 = 50, IIBR-SM420 = 140, IIBR-SM430 = 40, TF-CO-004 = 100
Dec-20171020168852IIIBR-SM540 = 30, IIIBR-SM550 = 70, IIIBR-SM560 = 80, IVR-SM670 = 20, IVR-SM680 = 160, TF-CO-013 = 60, TF-CO-014 = 150, TF-CO-015 = 150, TF-CO-018 = 150, TF-CO-019 = 150
Nov-2017970176794IIBR-SM490 = 40, IIBR-SM500 = 100, IIIBR-SM530 = 50, IIIBR-SM540 = 170, IVR-ET60 = 140, IVR-SM660 = 70, IVR-SM670 = 140, TF-CO-009 = 50, TF-CO-012 = 100, TF-CO-013 = 40, TF-CO-029 = 70
Mar-20181040176864IIIBR-SM580 = 70, IIIBR-SM590 = 120, IIIBR-SM600 = 30, IVEBO-SS100 = 100, IVR-EC30 = 60, IVR-IPM70 = 200, IVR-IPM80 = 20, IVR-RES140 = 60, IVWBO-SS100 = 100, TF-CO-016 = 60, TF-CO-017 = 60, TF-CO-024 = 160
Apr-201813401681172IIIBR-SM600 = 90, IIIBR-SM610 = 120, IVEBO-SS100 = 100, IVR-IPM100 = 40, IVR-IPM80 = 180, IVR-IPM90 = 200, IVWBO-SS100 = 100, TF-CO-024 = 60, TF-CO-026 = 150, TF-CO-027 = 150, TF-CO-028 = 150
Jan-2018920184736IIIBR-CP10 = 90, IIIBR-CP170 = 50, IIIBR-SM560 = 30, IIIBR-SM570 = 140, IIIC-AP170 = 80, IIIC-CP10 = 80, IVR-SM690 = 180, TF-CO-010 = 30, TF-CO-018 = 70, TF-CO-019 = 70, TF-CO-020 = 100
May-2018830184646IIIBR-IBM110 = 40, IIIBR-SM620 = 120, IIIBR-SM630 = 110, IVR-IPM100 = 160, TF-CO-026 = 70, TF-CO-027 = 100, TF-CO-028 = 100, TF-CO-030 = 130
Feb-20181080160920IIIBR-CP10 = 10, IIIBR-SM570 = 60, IIIBR-SM580 = 130, IIIC-AP170 = 120, IIIC-CP10 = 120, IVR-SM690 = 20, IVR-SM700 = 160, TF-CO-010 = 40, TF-CO-016 = 160, TF-CO-017 = 160, TF-CO-021 = 50, TF-CO-022 = 50
Jun-2018400168232IIIBR-SM630 = 90, IIIBR-SM640 = 90, IIIBR-SM650 = 20, TF-CO-030 = 90, TF-CO-031 = 110
Jul-2018340176164IIIBR-SM650 = 180, TF-CO-031 = 110, TF-CO-032 = 50

Lists project milestones, grouped by their WBS sequence and name, showing only those with negative float.

Highlighted in red are milestones with negative total or free float which means they are either behind their own finish dates or blocking downstream tasks, and therefore pose a risk to the overall project timeline.

Recommended actions:

  • Check for conflicting constraints or deadlines on these milestones.
  • Validate predecessor/successor links to ensure logic is correct.
  • Adjust sequencing or resource assignments as needed, then re‐run the schedule to confirm the float values return to zero or positive.

WBS Seq: NameMilestone IDMilestone NameTypeStatusTarget StartTarget FinishActual StartActual FinishTotal FloatFree Float
0: General GC-GCN160PH MS - Start Phase IV ConstructionStartNot Started16-Mar-1816-Mar-18-110
GC-GC110PH MS - Substantial CompletionFinishNot Started25-Aug-1825-Aug-18-512
4: Maintenance of Traffic GC-DP110PH MS - Project CompletionFinishNot Started05-Sep-1805-Sep-18-170

Lists project milestones, grouped by their WBS sequence and name.

Highlighted in red are milestones with negative total or free float which means they are either behind their own finish dates or blocking downstream tasks, and therefore pose a risk to the overall project timeline.

Recommended actions:

  • Check for conflicting constraints or deadlines on these milestones.
  • Validate predecessor/successor links to ensure logic is correct.
  • Adjust sequencing or resource assignments as needed, then re‐run the schedule to confirm the float values return to zero or positive.

WBS Seq: NameMilestone IDMilestone NameTypeStatusTarget StartTarget FinishActual StartActual FinishTotal FloatFree Float
0: General GC-DP100PH MS - NTPStartCompleted14-Nov-1514-Nov-1519-Aug-1519-Aug-1500
GC-GCN110PH MS - Start Phase IA ConstructionStartCompleted14-Nov-1514-Nov-1520-Sep-1520-Sep-1500
GC-GCN120PH MS - Start Phase IB ConstructionStartCompleted20-Nov-1520-Nov-1520-Nov-1520-Nov-1500
GC-GC100PH MS - NTP2 - Start Construction (35 days from NTP 1= Contract date )StartCompleted16-Dec-1516-Dec-1520-Sep-1520-Sep-1500
GC-GCN130PH MS - Start Phase IIA ConstructionStartCompleted17-Oct-1617-Oct-1619-Sep-1619-Sep-1600
GC-GCN140PH MS - Start Phase IIB ConstructionStartCompleted04-Jan-1704-Jan-1704-Oct-1604-Oct-1600
GC-GCN150PH MS - Start Phase IIC ConstructionStartNot Started12-Jun-1712-Jun-17400
GC-GCN200PH MS - Start Phase IIIA ConstructionStartNot Started12-Jun-1712-Jun-17200
GC-GCN190PH MS - Start Phase IID ConstructionStartNot Started24-Aug-1724-Aug-17210
GC-GCN170PH MS - Start Phase IIIB ConstructionStartNot Started14-Sep-1714-Sep-1710
GC-GCN180PH MS - Start Phase IIIC ConstructionStartNot Started11-Dec-1711-Dec-1710
GC-GCN160PH MS - Start Phase IV ConstructionStartNot Started16-Mar-1816-Mar-18-110
GC-GC110PH MS - Substantial CompletionFinishNot Started25-Aug-1825-Aug-18-512
4: Maintenance of Traffic GC-DP110PH MS - Project CompletionFinishNot Started05-Sep-1805-Sep-18-170

This report gives you a single view of all open WBS elements with remaining work and planned vs. actual dates, so you can immediately spot unfinished or slipped tasks. It flags at-risk items, validates your logic and constraints, and shows exactly how much effort remains (in hours or percent).

WBS Seq: NameRemaining Work, daysTarget StartTarget FinishActual StartActual Finish
0: General308919-Aug-1505-Sep-1819-Aug-1509-Jun-17
1: SPS &CPS Wall11312-Jun-1716-Nov-17
1: Retaining Walls14518-Apr-1605-Jul-1811-May-1625-Apr-17
1: MSE Walls8317-May-1626-Oct-1706-Jun-1627-Jul-16
1: Exc Ponds1814-Dec-1509-Oct-1726-Oct-1516-Jan-17
1: Embankment & Exc Road24614-Dec-1506-Feb-1805-Oct-1519-May-17
1: Misc Demo9627-Jan-1628-Mar-1826-Oct-1501-May-17
1: Barrier Wall (MOT)26129-Oct-1521-Mar-1821-Oct-1522-May-17
1: Temporary signs & Barricades116-Nov-1512-Jun-1720-Sep-1503-Oct-16
4: Maintenance of Traffic116-Dec-1505-Sep-1808-Oct-1509-Sep-16
7: Site Preparation & Access905-Nov-1520-Jun-1705-Nov-1522-Aug-16
8: Drainage44917-Feb-1618-Apr-1806-Jan-1608-Jun-17
10: Walls9405-Apr-1601-Feb-1816-Feb-1604-May-17
10: Demo (Bridge)13114-Dec-1516-Oct-1722-Nov-1511-May-17
10: Foundations2714-Dec-1523-Oct-1720-Nov-1502-Jun-17
11: (MOT) Structural Pavement117-Apr-1713-Jun-1729-Mar-1706-Apr-17
13: (MOT) Pavement Markings113-Jan-1620-Jun-1727-Sep-1501-Dec-15
14: Toll Facility56431-Mar-1723-Aug-1820-Mar-1731-Mar-17
101: Substructure9308-Mar-1630-Oct-1729-Jan-1617-Mar-17
101: Walls (Abutm & Wing)22805-May-1608-Dec-1718-Apr-1607-Jun-17
201: Superstructure28723-May-1616-Feb-1823-May-1630-May-17
301: Approach Slabs6606-Jul-1605-Mar-1813-Jul-1610-May-17
400: Beachline Update#20 DD June 11 TD June 1517512-Jun-1716-Feb-18
401: Imbeded Facilities (Electrical, Communications)1320-Jan-1706-Mar-1826-Jan-1718-May-17
501: Railing walls3401-Aug-1609-Mar-1804-Aug-1620-May-17
601: Finishes & Misc3404-Aug-1615-Mar-1803-Aug-1609-Jun-17

Successful Tests (no errors, changes, or issues)

  • Activities with Future Actual Dates
  • Activities with Constraint

Back Project Costs

The figures in this report should not be relied upon, excercise caution and double-check the values. This is merely a preview of a work-in-progress feature.
This table represents monthly project costs.

MonthActualActual CumulRemaining EarlyRemaining Early CumulRemaining LateRemaining Late Cumul
Aug-2015$5,537,599.61$5,537,599.610000
Sep-2015$2,445,696.60$7,983,296.210000
Oct-2015$3,171,096.91$11,154,393.120000
Nov-2015$1,372,651.15$12,527,044.270000
Dec-2015$1,093,149.68$13,620,193.950000
Jan-2016$666,775.56$14,286,969.510000
Feb-2016$1,000,323.64$15,287,293.150000
Mar-2016$662,043.51$15,949,336.650000
Apr-2016$689,435.13$16,638,771.780000
May-2016$1,853,885.53$18,492,657.310000
Jun-2016$2,101,471.48$20,594,128.790000
Jul-2016$2,719,063.08$23,313,191.870000
Aug-2016$1,619,326.51$24,932,518.390000
Sep-2016$1,429,111.36$26,361,629.750000
Oct-2016$1,245,161.83$27,606,791.590000
Nov-2016$1,131,474.20$28,738,265.790000
Dec-2016$3,630,160.50$32,368,426.280000
Jan-2017$2,489,504.53$34,857,930.810000
Feb-2017$2,351,203.14$37,209,133.950000
Mar-2017$3,060,488.40$40,269,622.360000
Apr-2017$2,079,382.07$42,349,004.420000
May-2017$2,150,416.80$44,499,421.2200$274,448.75$274,448.75
Jun-2017$807,088.73$45,306,509.95$6,314,001.15$6,314,001.15$1,492,428.50$1,766,877.26
Jul-201700$6,391,443.98$12,705,445.13$3,555,290.11$5,322,167.37
Aug-201700$4,410,405.59$17,115,850.72$4,708,404.90$10,030,572.27
Sep-201700$4,441,268.62$21,557,119.34$6,203,475.49$16,234,047.76
Oct-201700$6,303,210.34$27,860,329.68$3,430,737.24$19,664,785.00
Nov-201700$2,884,771.37$30,745,101.05$2,365,848.94$22,030,633.94
Dec-201700$3,187,722.49$33,932,823.54$4,348,599.06$26,379,232.99
Jan-201800$3,175,803.69$37,108,627.23$3,105,211.28$29,484,444.27
Feb-201800$2,006,503.17$39,115,130.40$7,032,683.90$36,517,128.17
Mar-201800$1,873,781.02$40,988,911.41$1,038,265.12$37,555,393.29
Apr-201800$1,505,955.76$42,494,867.17$1,000,871.36$38,556,264.66
May-201800$1,015,198.89$43,510,066.06$1,237,041.24$39,793,305.89
Jun-201800$776,140.79$44,286,206.85$2,046,014.28$41,839,320.17
Jul-201800$684,180.17$44,970,387.03$3,816,513.83$45,655,834.00
Aug-201800$2,414,153.45$47,384,540.48$1,801,005.32$47,456,839.33
Sep-201800$72,298.85$47,456,839.330$47,456,839.33

Back Charts

Download

The figures in this report should not be relied upon, excercise caution and double-check the values. This is merely a preview of a work-in-progress feature.
This chart represents monthly project costs

Report chart