Schedule analysis
Back Schedule Metrics
Beachline Update#20 DD June 11 TD June 15
- 534Not started activities
- 95In progress activities
- 583Completed activities
- 97 Critical activities
- 42 Activities on longest path
- 0 Activities with constraint
- 0 Activities with unsatisfied constraint
- 6 Available Calendars
- 18 Project Resources
- 14 Project Milestones
Activity Types
- 2Finish Milestones
- 12Start Milestones
- 1198Task Dependent
Project Dates
- Schedule-level Dates: are computed directly from the underlying activities, they reflect real-time changes and provide an updated view of the project timeline.
- Project-level Dates: often set as part of the project baseline, they might not change as activities update and are used for tracking planned versus actual performance.
- Must Finish By Date: a scheduling constraint that sets a hard deadline for a project, usually manually entered and is often left empty.
- 17-Jun-17Last Save Date
- 11-Jun-17Data Date
- 20-Aug-18Must Finish By Date
- 19-Aug-15Start Date (schedule-level)
- 05-Sep-18Finish Date (schedule-level)
- 1113 calendar daysProject Duration (schedule-level)
- 19-Aug-15Start Date (project-level)
- 05-Sep-18Finish Date (project-level)
- 1113 calendar daysProject Duration (project-level)
Back Schedule Analysis
The Longest Path table identifies the critical sequence of activities that directly determines your project's overall duration.
This table lists each activity's Start Date and Finish Date along with its Total Float - the available slack before a delay affects the project end date.
Highlighted in red are activities with negative total float.
| Activity ID | Activity Description | Start Date | Finish Date | Total Float |
|---|---|---|---|---|
| IIBEBO-RW180 | PH IIB - Base (Universal - JYP) - EB Outside Widening - LR - (STA 320 to 332) | 01-May-17 | 14-Jun-17 | -11 |
| IIBEBO-AP140 | PH IIB - Asphalt - Structural - EB Outside Widening (Univ to JYP) - STA 320 to 332 | 14-Jun-17 | 20-Jun-17 | -11 |
| IICR-TC130 | PH IIC - MOT Shift New Ramp Alignment - Ramp O | 20-Jun-17 | 21-Jun-17 | -11 |
| IICR-SP130 | PH IIC - Remove Ramp O Diversion - Construct EB Roadway Tie-In | 21-Jun-17 | 13-Jul-17 | -11 |
| IBEBM-TC220 | PH IIIA - Construct Diversion at Shingle Creek - WB Median Widening | 13-Jul-17 | 03-Aug-17 | -11 |
| IIIAR120 | PH IIIA - Construct Ramp Diversion P - Ramp P (Tie-in to SC Diversion) | 03-Aug-17 | 10-Aug-17 | -11 |
| IIIBWBO-ST190 | PH IIIB - Demo Traffic Rails - WB Outside Widening Area (Bridge over Shingle Creek) | 10-Aug-17 | 18-Aug-17 | -11 |
| IIIBWBO-ST650 | PH IIIB - Demo Bridge Deck - WB Outside Widening Area (Bridge over Shingle Creek) | 18-Aug-17 | 28-Aug-17 | -11 |
| IIIBWBO-ST660 | PH IIIB - Remove Beams - WB Outside Widening Area (Bridge over Shingle Creek) | 28-Aug-17 | 30-Aug-17 | -11 |
| IIIBWBO-ST670 | PH IIIB - Demo Pile Cap - WB Outside Widening Area (Bridge over Shingle Creek) | 30-Aug-17 | 05-Sep-17 | -11 |
| IIIBWBO-ST680 | PH IIIB - Extract Pile - WB Outside Widening Area (Bridge over Shingle Creek) | 05-Sep-17 | 08-Sep-17 | -11 |
| IIIBWBO-ST26 | PH IIIB - Production Pile (11-30)(Concrete) - WB Outside Widening Area (Bridge over Shingle Creek) | 08-Sep-17 | 22-Sep-17 | -11 |
| IIIBWBO-ST370 | PH IIIB - Wall Bent 1 - WB Outside Widening Area (Bridge over Shingle Creek) | 22-Sep-17 | 04-Oct-17 | -11 |
| IIIBWBO-ST400 | PH IIIB - End Bent 1 - WB Outside Widening Area (Bridge over Shingle Creek) | 04-Oct-17 | 25-Oct-17 | -11 |
| IIIBWBO-ST430 | PH IIIB - Wall Bent 4 - WB Outside Widening Area (Bridge over Shingle Creek) | 25-Oct-17 | 06-Nov-17 | -11 |
| IIIBWBO-ST480 | PH IIIB - End Bent 4 - WB Outside Widening Area (Bridge over Shingle Creek) | 06-Nov-17 | 01-Dec-17 | -11 |
| IIIBWBO-ST520 | PH IIIB - Curing for End Bent 4 - WB Outside Widening Area (Bridge over Shingle Creek) | 01-Dec-17 | 08-Dec-17 | -17 |
| IIIBWBO-ST560 | PH IIIB - Set Beams - WB Outside Widening Area (Bridge over Shingle Creek) | 08-Dec-17 | 27-Dec-17 | -11 |
| IIIBWBO-ST610 | PH IIIB - Superstructure Deck SIP & Start Rebar - WB Outside Widening Area (Bridge over Shingle Creek) | 27-Dec-17 | 26-Jan-18 | -11 |
| IIIBWBO-ST700 | PH IIIB - Superstructure Deck (Finish Rebar\Set Screed\Pour) - WB Outside Widening Area (Bridge over Shingle Creek) | 26-Jan-18 | 16-Feb-18 | -11 |
| IIIBWBO-ST120 | PH IIIB - Approach Slabs - WB Outside Widening Area (Bridge over Shingle Creek) | 16-Feb-18 | 05-Mar-18 | -11 |
| IIIBWBO-ST130 | PH IIIB - Lighting Conduit - WB Outside Widening Area (Bridge over Shingle Creek) | 06-Mar-18 | 06-Mar-18 | -11 |
| IIIBWBO-ST140 | PH IIIB - Traffic Railing (32") - WB Outside Widening Area (Bridge over Shingle Creek) | 07-Mar-18 | 09-Mar-18 | -11 |
| IIIBWBO-ST150 | PH IIIB - Grind and Groove - WB Outside Widening Area (Bridge over Shingle Creek) | 12-Mar-18 | 15-Mar-18 | -11 |
| GC-GCN160 | PH MS - Start Phase IV Construction | 16-Mar-18 | -11 | |
| IVEBM-TC100 | PH IV - Set Temp Traffic Barriers - EB Median Widening | 16-Mar-18 | 21-Mar-18 | -11 |
| IVEBM-GC100 | PH IV - Demo Temporary - EB Median Widening | 22-Mar-18 | 28-Mar-18 | -11 |
| IVEBM-W140 | PH IV - Median Wall - Grading for Station 1 (I4 to International Drive) | 29-Mar-18 | 30-Mar-18 | -11 |
| IVEBM-W150 | PH IV - Median Wall - FFP Footing/Stem for Station 1 (I4 to International Drive) | 02-Apr-18 | 13-Apr-18 | -11 |
| IVEBM-W160 | PH IV - Median Wall - Construct/ slip Top for Station 1 (I4 to International Drive) | 16-Apr-18 | 20-Apr-18 | -11 |
| IVEBM-W170 | PH IV - Median Wall - Grading for Station 2 (International Drive to Universal) | 23-Apr-18 | 30-Apr-18 | -11 |
| IVEBM-W180 | PH IV - Median Wall - FFP Footing/Stem for Station 2 (International Drive to Universal) | 01-May-18 | 21-May-18 | -11 |
| IVEBM-W190 | PH IV - Median Wall - Construct/ slip Top for Station 2 (International Drive to Universal) | 22-May-18 | 29-May-18 | -11 |
| IVEBM-W200 | PH IV - Median Wall - Grading for Station 3 (Universal to JYP) | 30-May-18 | 12-Jun-18 | -11 |
| IVEBM-W210 | PH IV - Median Wall - FFP Footing/Stem for Station 3 (Universal to JYP) | 13-Jun-18 | 26-Jun-18 | -11 |
| IVEBM-W220 | PH IV - Median Wall - Construct/ slip Top for Station 3 (Universal to JYP) | 27-Jun-18 | 05-Jul-18 | -11 |
| IVWBM-RW130 | PH IV - Grade for Station 3 (Universal to JYP) (B) | 06-Jul-18 | 12-Jul-18 | -11 |
| IVWBM-RW140 | PH IV - Stabilization for Station 3 (Universal to JYP) (A) | 13-Jul-18 | 18-Jul-18 | -11 |
| IVWBM-RW150 | PH IV - Base for Station 3 (Universal to JYP) (B) | 19-Jul-18 | 31-Jul-18 | -11 |
| IVWBM-AP100 | PH IV - Asphalt - Structural - WB Median Widening | 01-Aug-18 | 06-Aug-18 | -11 |
| GC-GCN210 | PH MS - Punch List/Acceptance | 07-Aug-18 | 05-Sep-18 | -17 |
| GC-DP110 | PH MS - Project Completion | 05-Sep-18 | -17 |
This table lists activities with zero or negative float - indicating no available slack before a delay impacts the overall project schedule. It helps you quickly pinpoint activities that require immediate attention to maintain project momentum.
| Activity ID | Activity Description | On LP | Total Float |
|---|---|---|---|
| GC-DP110 | PH MS - Project Completion | Yes | -17 |
| GC-GC110 | PH MS - Substantial Completion | No | -5 |
| IIIAR120 | PH IIIA - Construct Ramp Diversion P - Ramp P (Tie-in to SC Diversion) | Yes | -11 |
| NA-GC100 | TEC Install and Test | No | -4 |
| NA-GC110 | PH PW - ITS Testing and Commissioning - Critical Areas | No | 0 |
| GC-GCN160 | PH MS - Start Phase IV Construction | Yes | -11 |
| GC-GCN210 | PH MS - Punch List/Acceptance | Yes | -17 |
| TF-CO-004 | Precast Erection | No | -4 |
| TF-CO-006 | FRP Conc. Roof Dec/c | No | -4 |
| TF-CO-009 | Const. Roof System | No | -4 |
| TF-CO-010 | FRP Conc. Pad (Generator) | No | -4 |
| TF-CO-012 | Install Frames & Doors | No | -4 |
| TF-CO-013 | Const. Screen Wall (Con.) | No | -4 |
| TF-CO-016 | F+1 Generator | No | -4 |
| TF-CO-017 | F+1 Fuel Tank | No | -4 |
| TF-CO-019 | Install Security System | No | -4 |
| TF-CO-020 | Install Lightning Protection | No | -4 |
| TF-CO-024 | Wall Treatments (Ply) | No | -4 |
| TF-CO-026 | Cont. Lightning | No | -1 |
| TF-CO-027 | Cont. HVAC | No | -4 |
| TF-CO-030 | Pull Wire | No | -4 |
| TF-CO-031 | Toll Facility Finishes and Punchlist | No | -4 |
| TF-CO-032 | Toll Facility CO | No | -4 |
| IIAR-AP100 | PH IIB - Asphalt - Structural - Ramp O | No | -11 |
| IIAR-RW110 | PH IIB - Base - Ramp O | No | -11 |
| IIBR-ITS50 | PH IIB - Install ITS Poles (1-20) | No | 0 |
| IIBR-ITS60 | PH IIB - Install ITS Poles (21-41) | No | 0 |
| IIBR-ITS70 | PH IIB - Install CCTV's (1-8) | No | 0 |
| IIBR-ITS80 | PH IIB - Install CCTV's (9-16) | No | 0 |
| IIBR-ITS90 | PH IIB - Install CCTV's (17-22) | No | 0 |
| IICR-SP130 | PH IIC - Remove Ramp O Diversion - Construct EB Roadway Tie-In | Yes | -11 |
| IICR-TC130 | PH IIC - MOT Shift New Ramp Alignment - Ramp O | Yes | -11 |
| IVEBM-W140 | PH IV - Median Wall - Grading for Station 1 (I4 to International Drive) | Yes | -11 |
| IVEBM-W150 | PH IV - Median Wall - FFP Footing/Stem for Station 1 (I4 to International Drive) | Yes | -11 |
| IVEBM-W160 | PH IV - Median Wall - Construct/ slip Top for Station 1 (I4 to International Drive) | Yes | -11 |
| IVEBM-W170 | PH IV - Median Wall - Grading for Station 2 (International Drive to Universal) | Yes | -11 |
| IVEBM-W180 | PH IV - Median Wall - FFP Footing/Stem for Station 2 (International Drive to Universal) | Yes | -11 |
| IVEBM-W190 | PH IV - Median Wall - Construct/ slip Top for Station 2 (International Drive to Universal) | Yes | -11 |
| IVEBM-W200 | PH IV - Median Wall - Grading for Station 3 (Universal to JYP) | Yes | -11 |
| IVEBM-W210 | PH IV - Median Wall - FFP Footing/Stem for Station 3 (Universal to JYP) | Yes | -11 |
| IVEBM-W220 | PH IV - Median Wall - Construct/ slip Top for Station 3 (Universal to JYP) | Yes | -11 |
| PRE-FA-030 | Fabricate and Deliver 042200 Masonry | No | -4 |
| PRE-PS-030 | Prepare and Submit 042200 Masonry | No | -4 |
| PRE-RA-030 | Review and Approve 042200 Masonry | No | -4 |
| IBEBM-TC220 | PH IIIA - Construct Diversion at Shingle Creek - WB Median Widening | Yes | -11 |
| IIIBR-ITS80 | PH IIIB - Install Conduit/Boxes (JYP to TPK) | No | 0 |
| IIIBR-ITS90 | PH IIIB - Install ITS Cabinets/Hardware | No | 0 |
| IVEBM-AP100 | PH IV - Asphalt - Structural - EB Median Widening | No | -10 |
| IVEBM-GC100 | PH IV - Demo Temporary - EB Median Widening | Yes | -11 |
| IVEBM-TC100 | PH IV - Set Temp Traffic Barriers - EB Median Widening | Yes | -11 |
| IVEBM-TC110 | PH IV - Temp Striping for Phase - EB Median Widening | No | -5 |
| IVEBM-TC120 | PH IV - MOT Shift for Phase - EB Median Widening | No | -5 |
| IVEBO-AP100 | PH IV - Asphalt - Overbuild & Friction - EB Outside Widening | No | -5 |
| IVEBO-PM110 | PH IV - Pavement Markings (Final) - EB Outside Widening | No | -5 |
| IVWBM-AP100 | PH IV - Asphalt - Structural - WB Median Widening | Yes | -11 |
| IVWBM-RW130 | PH IV - Grade for Station 3 (Universal to JYP) (B) | Yes | -11 |
| IVWBM-RW140 | PH IV - Stabilization for Station 3 (Universal to JYP) (A) | Yes | -11 |
| IVWBM-RW150 | PH IV - Base for Station 3 (Universal to JYP) (B) | Yes | -11 |
| IVWBM-RW260 | PH IV - Grade for Station 3 (Universal to JYP) (A) | No | -10 |
| IVWBM-RW270 | PH IV - Stabilization for Station 3 (Universal to JYP) (A) | No | -10 |
| IVWBM-RW280 | PH IV - Base for Station 3 (Universal to JYP) | No | -10 |
| IVWBM-TC100 | PH IV - Set Temp Traffic Barriers - WB Median Widening | No | -6 |
| IVWBM-TC110 | PH IV - Temp Striping for Phase - WB Median Widening | No | -4 |
| IVWBM-TC120 | PH IV - MOT Shift for Phase - WB Median Widening | No | -4 |
| IVWBO-AP100 | PH IV - Asphalt - Overbuild & Friction - WB Outside Widening Area | No | -4 |
| IVWBO-PM110 | PH IV - Pavement Markings (Final) - WB Outside Widening Area | No | -4 |
| IIBEBO-AP140 | PH IIB - Asphalt - Structural - EB Outside Widening (Univ to JYP) - STA 320 to 332 | Yes | -11 |
| IIBEBO-RW180 | PH IIB - Base (Universal - JYP) - EB Outside Widening - LR - (STA 320 to 332) | Yes | -11 |
| IIIBR-ITS100 | PH IIIB - Install Vehicle Detection Systems (1-11) | No | 0 |
| IIIBR-ITS110 | PH IIIB - Install Vehicle Detection Systems (12-22) | No | 0 |
| IIIBR-ITS130 | PH IIIB - Install Digital Message Signs (1-12) | No | 0 |
| IIIBR-ITS140 | PH IIIB - Install Digital Message Signs (13-23) | No | 0 |
| IIIBR-ITS150 | PH IIIB - Pull FOC (I-4 to International) | No | 0 |
| IIIBR-ITS160 | PH IIIB - Pull FOC ( International to Univ) | No | 0 |
| IIIBR-ITS170 | PH IIIB - Pull FOC (UNIV to JYP) | No | 0 |
| IIIBR-ITS180 | PH IIIB - Pull FOC (JYP to TPK) | No | 0 |
| IIIBR-ITS190 | PH IIIB - Splice/Terminate FOC | No | 0 |
| IIIBWBO-ST26 | PH IIIB - Production Pile (11-30)(Concrete) - WB Outside Widening Area (Bridge over Shingle Creek) | Yes | -11 |
| IIIBR-ITS1000 | PH IIIB - Install Conduit/Boxes (I-4 to International) | No | 0 |
| IIIBR-ITS1020 | PH IIIB - Install Conduit/Boxes (Univ to JYP) | No | 0 |
| IIIBWBO-ST120 | PH IIIB - Approach Slabs - WB Outside Widening Area (Bridge over Shingle Creek) | Yes | -11 |
| IIIBWBO-ST130 | PH IIIB - Lighting Conduit - WB Outside Widening Area (Bridge over Shingle Creek) | Yes | -11 |
| IIIBWBO-ST140 | PH IIIB - Traffic Railing (32") - WB Outside Widening Area (Bridge over Shingle Creek) | Yes | -11 |
| IIIBWBO-ST150 | PH IIIB - Grind and Groove - WB Outside Widening Area (Bridge over Shingle Creek) | Yes | -11 |
| IIIBWBO-ST190 | PH IIIB - Demo Traffic Rails - WB Outside Widening Area (Bridge over Shingle Creek) | Yes | -11 |
| IIIBWBO-ST370 | PH IIIB - Wall Bent 1 - WB Outside Widening Area (Bridge over Shingle Creek) | Yes | -11 |
| IIIBWBO-ST400 | PH IIIB - End Bent 1 - WB Outside Widening Area (Bridge over Shingle Creek) | Yes | -11 |
| IIIBWBO-ST430 | PH IIIB - Wall Bent 4 - WB Outside Widening Area (Bridge over Shingle Creek) | Yes | -11 |
| IIIBWBO-ST480 | PH IIIB - End Bent 4 - WB Outside Widening Area (Bridge over Shingle Creek) | Yes | -11 |
| IIIBWBO-ST520 | PH IIIB - Curing for End Bent 4 - WB Outside Widening Area (Bridge over Shingle Creek) | Yes | -17 |
| IIIBWBO-ST560 | PH IIIB - Set Beams - WB Outside Widening Area (Bridge over Shingle Creek) | Yes | -11 |
| IIIBWBO-ST610 | PH IIIB - Superstructure Deck SIP & Start Rebar - WB Outside Widening Area (Bridge over Shingle Creek) | Yes | -11 |
| IIIBWBO-ST650 | PH IIIB - Demo Bridge Deck - WB Outside Widening Area (Bridge over Shingle Creek) | Yes | -11 |
| IIIBWBO-ST660 | PH IIIB - Remove Beams - WB Outside Widening Area (Bridge over Shingle Creek) | Yes | -11 |
| IIIBWBO-ST670 | PH IIIB - Demo Pile Cap - WB Outside Widening Area (Bridge over Shingle Creek) | Yes | -11 |
| IIIBWBO-ST680 | PH IIIB - Extract Pile - WB Outside Widening Area (Bridge over Shingle Creek) | Yes | -11 |
| IIIBWBO-ST700 | PH IIIB - Superstructure Deck (Finish Rebar\Set Screed\Pour) - WB Outside Widening Area (Bridge over Shingle Creek) | Yes | -11 |
This table identifies activities that lack defined predecessor relationships. Missing predecessors can indicate gaps in the dependency chain, potentially compromising the accuracy of your schedule.
| Activity ID | Activity Description | On LP |
|---|---|---|
| GC-DP100 | PH MS - NTP | Yes |
This table identifies activities that lack defined successor relationships. Missing successors may signal gaps in the dependency chain, leading to potential scheduling inaccuracies and oversight of critical follow-up tasks.
| Activity ID | Activity Description | On LP |
|---|---|---|
| GC-DP110 | PH MS - Project Completion | Yes |
Having unique and clear descriptions for each activity is essential for effective project tracking, resource allocation, and communication. Addressing this issue promptly is crucial to maintain clarity and efficiency in project execution.
Recommended actions: Review the activities with identical descriptions and update them with unique, specific descriptions showing phase, location or a category. This will help in distinguishing each activity clearly, improving tracking accuracy and communication, especially when it comes to a claim review process. Inform the project team of these updates to ensure everyone is aligned.
| Total | Activity Description | Activity IDs |
|---|---|---|
| 2 | PH IV - Stabilization for Station 3 (Universal to JYP) (A) | IVWBM-RW140, IVWBM-RW270 |
Several activities were completed out-of-sequence. This table should be used as a tool to understand the impact of out-of-sequence work on the project schedule and to develop strategies to minimize disruptions in the future.
Out-of-sequence work can lead to inefficiencies, increased costs, and potential delays in subsequent activities. A small number of out-of-sequence activities is typically normal and can be expected in any project. However, a large number indicates that the contractor is either not following the schedule or not updating the progress timely. In such cases, it is essential to revisit the scheduling logic and see if it needs to be adjusted or revised.
Recommended actions: Meet with the contractor to review and discuss the reasons behind the out-of-sequence work for these activities and identify any patterns or recurring issues. Implement process improvements and communicate the importance of following the planned sequence to the project team. Adjust the project schedule if necessary and inform stakeholders of any changes to ensure alignment and transparency.
| Activity ID | Activity Description | On LP | Act start date | Parent end date |
|---|---|---|---|---|
| GC-GC100 | PH MS - NTP2 - Start Construction (35 days from NTP 1= Contract date ) | Yes | 20-Sep-15 | 11-Jun-17 |
| GC-GCN100 | PH MS - Construction Mobilization | Yes | 19-Aug-15 | 11-Jun-17 |
| GC-GCN110 | PH MS - Start Phase IA Construction | Yes | 20-Sep-15 | 11-Jun-17 |
| GC-GCN120 | PH MS - Start Phase IB Construction | Yes | 20-Nov-15 | 11-Jun-17 |
| GC-GCN130 | PH MS - Start Phase IIA Construction | No | 19-Sep-16 | 11-Jun-17 |
| GC-GCN140 | PH MS - Start Phase IIB Construction | No | 04-Oct-16 | 11-Jun-17 |
| IAEBO-AP100 | PH IA - Overbuild Shoulder - EB Outside Widening (SR528) | Yes | 20-Sep-15 | 11-Jun-17 |
| IAEBO-GC100 | PH IA - Set Erosion Control Devices - EB Outside Widening | Yes | 21-Sep-15 | 11-Jun-17 |
| IAEBO-GC110 | PH IA - Clear & Grub - EB Outside Widening | No | 22-Sep-15 | 11-Jun-17 |
| IAEBO-GC120 | PH IA - Drill Scuppers in Bridge (Shingle Creek) - EB Outside Widening | Yes | 08-Oct-15 | 11-Jun-17 |
| IAEBO-GC130 | PH IA - Clear & Grub - EB Outside Widening (I-4 to Ramp H) | No | 22-Feb-16 | 11-Jun-17 |
| IAEBO-SP100 | PH IA - Jack & Bore 42" (Sta 351+00 near Duke energy access platform) - EB Outside Widening (SR528) | No | 06-Jul-16 | 11-Jun-17 |
| IAEBO-SP110 | PH IA - Drainage (42") @ JYP Interchange - EB Outside Widening (SR528) | No | 25-Jul-16 | 11-Jun-17 |
| IAEBO-TC100 | PH IA - Install Advance Sign & Traffic Control Devices - EB Outside Widening | Yes | 28-Sep-15 | 11-Jun-17 |
| IAEBO-TC110 | PH IA - Temp Striping for Phase IB - EB Outside Widening (SR528) | Yes | 27-Sep-15 | 11-Jun-17 |
| IAEBO-W100 | PH IA - Noise/Sound Wall Prep Work (W-1) - EB Outside Widening | No | 04-Jan-16 | 11-Jun-17 |
| IAEBO-W110 | PH IA - Install Posts (1-101)- EB Outside Widening | No | 29-Apr-16 | 11-Jun-17 |
| IAEBO-W120 | PH IA - Install Posts (102- 203) - EB Outside Widening | No | 09-May-16 | 11-Jun-17 |
| IAEBO-W130 | PH IA - Noise/Sound Wall Prep Work (W-2) - EB Outside Widening | No | 22-Feb-16 | 11-Jun-17 |
| IAEBO-W140 | PH IA - Install Posts (204-305) - EB Outside Widening | No | 18-May-16 | 11-Jun-17 |
| IAEBO-W150 | PH IA - Install Posts (306- 409) - EB Outside Widening | No | 26-May-16 | 11-Jun-17 |
| IAEBO-W160 | PH IA - Install Panels (0-32000 SF) - EB Outside Widening | No | 27-Jun-16 | 11-Jun-17 |
| IAEBO-W170 | PH IA - Install Panels (32000-64000 SF) - EB Outside Widening | No | 29-Jun-16 | 11-Jun-17 |
| IAEBO-W180 | PH IA - Install Panels (64000-96000 SF)- EB Outside Widening | No | 05-Jul-16 | 11-Jun-17 |
| IAEBO-W190 | PH IA - Install Panels (96000-128000 SF)- EB Outside Widening | No | 08-Jul-16 | 11-Jun-17 |
| IAEBO-W200 | PH IA - Install Panels (128000-160000 SF) - EB Outside Widening | No | 12-Jul-16 | 11-Jun-17 |
| IAI-TC100 | PH IA - Set Temp Traffic Barriers - Interchanges Roads International Dr | No | 21-Oct-15 | 11-Jun-17 |
| IAI-TC110 | PH IA - Set Temp Traffic Barriers - Interchanges Roads Universal Avn | No | 09-Nov-15 | 11-Jun-17 |
| IAI-TC120 | PH IA - Set Temp Traffic Barriers - Interchanges Roads John Young PKW | No | 17-Nov-15 | 11-Jun-17 |
| IAR-AP110 | PH IA - Mill & Resurface Transition (Ramp A) | Yes | 25-Oct-15 | 11-Jun-17 |
| IAR-AP130 | PH IA - Over Build Shoulder- Ramp A | Yes | 26-Oct-15 | 11-Jun-17 |
| IAR-AP140 | PH IA - Over Build Shoulder - Ramp D | Yes | 20-Sep-15 | 11-Jun-17 |
| IAR-GC100 | PH IA - Guardrail Replacement (Ramp A) | Yes | 25-Oct-15 | 11-Jun-17 |
| IAR-TC100 | PH IA - Close and Detour (Ramp A) | Yes | 25-Oct-15 | 11-Jun-17 |
| IAR-TC120 | PH IA - Set Temp Traffic Barriers - Ramp A | Yes | 26-Oct-15 | 11-Jun-17 |
| IAR-TC130 | PH IA - Set Temp Traffic Barriers for Phase IB - WB Median Widening | No | 01-Nov-15 | 11-Jun-17 |
| IAR-TC140 | PH IA - Set Temp Traffic Barriers for Phase IB - EB Median Widening | No | 29-Oct-15 | 11-Jun-17 |
| IAWBO-AP100 | PH IA - Overbuild Shoulder - WB Outside Widening Area (SR528) | Yes | 23-Sep-15 | 11-Jun-17 |
| IAWBO-EW100 | PH IA - Pond EXCAVATION (Shape 4A & 5A) - WB Outside Widening Area | No | 26-Oct-15 | 11-Jun-17 |
| IAWBO-EW110 | PH IA - Embankment(Duke energy access platform & Poles) - WB Outside Widening Area | No | 05-Oct-15 | 11-Jun-17 |
| IAWBO-GC100 | PH IA - Set Erosion Control Devices - WB Outside Widening Area | Yes | 21-Sep-15 | 11-Jun-17 |
| IAWBO-GC110 | PH IA - Clear & Grub - WB Outside Widening Area | No | 22-Sep-15 | 11-Jun-17 |
| IAWBO-GC120 | PH IA - Drill Scuppers in Bridge (Shingle Creek) - WB Outside Widening Area | Yes | 13-Oct-15 | 11-Jun-17 |
| IAWBO-SP110 | PH IA - Drainage (42") @ JYP Interchange - WB Outside Widening Area (SR528) | No | 10-Nov-16 | 11-Jun-17 |
| IAWBO-TC100 | PH IA - Install Advance Sign & Traffic Control Devices - WB Outside Widening Area | Yes | 20-Sep-15 | 11-Jun-17 |
| IAWBO-TC110 | PH IA - Temp Striping for Phase IB - WB Outside Widening Area (SR528) | Yes | 28-Sep-15 | 11-Jun-17 |
| IBEBM-AP100 | PH IB - Asphalt - Structural - EB Median Widening (I-4 to I-Drive) | No | 02-Mar-17 | 11-Jun-17 |
| IBEBM-AP110 | PH IB - Asphalt - Structural - EB Median Widening (I-Drive to Univ) | No | 06-Feb-17 | 11-Jun-17 |
| IBEBM-AP120 | PH IB - Asphalt - Structural - EB Median Widening (Univ to JYP) | Yes | 23-Jan-17 | 11-Jun-17 |
| IBEBM-GC100 | PH IB - Median Clearing and Grubbing - EB Median Widening | No | 26-Oct-15 | 11-Jun-17 |
| IBEBM-RW110 | PH IB - Grade for Permanent Shoulder Construction (JYP-TRP) - EB Median Widening | No | 11-Jul-16 | 11-Jun-17 |
| IBEBM-RW111 | PH IB - Stabilization for Permanent Shoulder Construction (JYP-TRP) - EB Median Widening | No | 13-Jul-16 | 11-Jun-17 |
| IBEBM-RW220 | PH IB - Grade (I4-International Drive) - EB Median Widening | No | 06-Feb-17 | 11-Jun-17 |
| IBEBM-RW230 | PH IB - Grade (International Drive - Universal) - EB Median Widening | No | 30-Jan-17 | 11-Jun-17 |
| IBEBM-RW240 | PH IB - Grade (Universal - JYP) - EB Median Widening | Yes | 19-Dec-16 | 11-Jun-17 |
| IBEBM-RW250 | PH IB - Stabilization (I4-international Drive) - EB Median Widening | No | 17-Feb-17 | 11-Jun-17 |
| IBEBM-RW260 | PH IB - Stabilization (International Drive - Universal) - EB Median Widening | No | 08-Feb-17 | 11-Jun-17 |
| IBEBM-RW270 | PH IB - Stabilization (Universal - JYP) - EB Median Widening | Yes | 18-Jan-17 | 11-Jun-17 |
| IBEBM-RW280 | PH IB - Base (I4-International Drive) - EB Median Widening | No | 13-Jul-16 | 11-Jun-17 |
| IBEBM-RW290 | PH IB - Base (International Drive - Universal) - EB Median Widening | No | 08-Feb-17 | 11-Jun-17 |
| IBEBM-RW300 | PH IB - Base (Universal - JYP) - EB Median Widening | Yes | 18-Jan-17 | 11-Jun-17 |
| IBEBM-RW310 | PH IB - Guard Rail Removal - EB Median Widening | Yes | 10-Dec-15 | 11-Jun-17 |
| IBEBM-RW320 | PH IB - Base for Permanent Shoulder Construction (JYP-TRP) - EB Median Widening | No | 01-Nov-16 | 16-Jun-17 |
| IBEBM-RW330 | PH IB - Pavement for Permanent Shoulder Construction (JYP-TRP) - EB Median Widening | No | 17-Nov-16 | 22-Jun-17 |
| IBEBM-ST100 | PH IB - Construct Crane Access - EB Median Widening (Bridge over Shingle Creek) | No | 05-Nov-15 | 11-Jun-17 |
| IBEBM-ST110 | PH IB - DemoTraffic Rail / End Bents - EB Median Widening (Bridge over Shingle Creek) | No | 22-Nov-15 | 11-Jun-17 |
| IBEBM-ST120 | PH IB - Construct Crane Access - EB Median Widening (Bridge over John Young PKWY) | No | 04-Dec-15 | 11-Jun-17 |
| IBEBM-ST130 | PH IB - Demo Traffic Rails - EB Median Widening (Bridge over John Young PKWY) | No | 04-Jan-16 | 11-Jun-17 |
| IBEBM-ST140 | PH IB - Construct Crane Access - EB Median Widening (Bridge over International DR) | No | 17-Mar-16 | 11-Jun-17 |
| IBEBM-ST150 | PH IB - Demo Traffic Rails - EB Median Widening (Bridge over International DR) | No | 14-Mar-16 | 11-Jun-17 |
| IBEBM-ST160 | PH IB - Test Pile (Concrete) - EB Median Widening (Bridge over Shingle Creek) | No | 20-Nov-15 | 11-Jun-17 |
| IBEBM-ST190 | PH IB - Production Pile (Concrete) - EB Median Widening (Bridge over Shingle Creek) | No | 18-Jan-16 | 11-Jun-17 |
| IBEBM-ST200 | PH IB - Temp Sheet Pile - EB Median Widening (Bridge over International DR) | No | 16-May-16 | 11-Jun-17 |
| IBEBM-ST210 | PH IB - Temp Sheet Pile - EB Median Widening (Bridge over John Young PKWY) | No | 06-Mar-16 | 11-Jun-17 |
| IBEBM-ST220 | PH IB - Drive Production Pile (H Piles) - EB Median Widening (Bridge over John Young PKWY) | No | 25-Jan-16 | 11-Jun-17 |
| IBEBM-ST230 | PH IB - Production Pile - EB Median Widening (Bridge over International DR) | No | 28-Mar-16 | 11-Jun-17 |
| IBEBM-ST240 | PH IB - Construct Crane Access - EB Median Widening (Bridge over universal BLVD) | No | 21-Feb-16 | 11-Jun-17 |
| IBEBM-ST250 | PH IB - Pier 2, (F/R/P)(Footer, Column & Pier Cap) - EB Median Widening (Bridge over International DR) | No | 18-May-16 | 11-Jun-17 |
| IBEBM-ST260 | PH IB - Demo Traffic Rails - EB Median Widening (Bridge over universal BLVD) | No | 29-Feb-16 | 11-Jun-17 |
| IBEBM-ST270 | PH IB - Test Pile - EB Median Widening (Bridge over universal BLVD) | No | 10-Mar-16 | 11-Jun-17 |
| IBEBM-ST280 | PH IB - Temp Sheet Pile - EB Median Widening (Bridge over universal BLVD) | No | 08-Jun-16 | 11-Jun-17 |
| IBEBM-ST290 | PH IB - Production Pile - EB Median Widening (Bridge over universal BLVD) | No | 10-Mar-16 | 11-Jun-17 |
| IBEBM-ST300 | PH IB - Curing for Pier 2, (Footer, Column & Pier Cap) - EB Median Widening (Bridge over International DR) | No | 27-Jul-16 | 11-Jun-17 |
| IBEBM-ST310 | PH IB - Removal of Concrete Forms for Pier 2, (Footer, Column & Pier Cap) - WB Median Widening (Bridge over Internation | No | 04-Aug-16 | 11-Jun-17 |
| IBEBM-ST320 | PH IB - Temp Sheet Pile Removal - EB Median Widening (Bridge over International DR) | No | 25-Jul-16 | 11-Jun-17 |
| IBEBM-ST330 | PH IB - Wall Bent 1 - EB Median Widening (Bridge over International DR) | No | 18-Apr-16 | 11-Jun-17 |
| IBEBM-ST340 | PH IB - Rip Rap Under Bridge - EB Median Widening (Bridge over Shingle Creek) | No | 16-Feb-16 | 11-Jun-17 |
| IBEBM-ST350 | PH IB - Pier 2 & 3 (F/R/P)( Pile Cap) - EB Median Widening (Bridge over Shingle Creek) | No | 29-Jan-16 | 11-Jun-17 |
| IBEBM-ST360 | PH IB - Pier 2, 3, 4(F/R/P) ( Pier Cap) - EB Median Widening (Bridge over John Young PKWY) | No | 06-May-16 | 11-Jun-17 |
| IBEBM-ST370 | PH IB - End Bent 1 - EB Median Widening (Bridge over International DR) | No | 18-Apr-16 | 11-Jun-17 |
| IBEBM-ST380 | PH IB - Wall Bent 3 - EB Median Widening (Bridge over International DR) | No | 09-May-16 | 11-Jun-17 |
| IBEBM-ST390 | PH IB - Curing for Pier 2, 3, (Pile Cap) - EB Median Widening (Bridge over Shingle Creek) | No | 24-Feb-16 | 11-Jun-17 |
| IBEBM-ST400 | PH IB - Remove Concrete Form for Pier 2, 3, (Pile Cap) - EB Median Widening (Bridge over Shingle Creek) | No | 02-Mar-16 | 11-Jun-17 |
| IBEBM-ST410 | PH IB - End Bent 3 - EB Median Widening (Bridge over International DR) | No | 09-May-16 | 11-Jun-17 |
| IBEBM-ST420 | PH IB - Curing for End Bent 3 - EB Median Widening (Bridge over International DR) | No | 12-May-16 | 11-Jun-17 |
| IBEBM-ST430 | PH IB - End Bent 1 - EB Median Widening (Bridge over Shingle Creek) | No | 28-Apr-16 | 11-Jun-17 |
| IBEBM-ST440 | PH IB - Curing For Pier 2, 3, 4(Footer, Column & Pier Cap) - EB Median Widening (Bridge over John Young PKWY) | No | 02-Aug-16 | 11-Jun-17 |
| IBEBM-ST450 | PH IB - Set Beams - EB Median Widening (Bridge over International Drive) | No | 13-Oct-16 | 11-Jun-17 |
| IBEBM-ST460 | PH IB - Superstructure Deck - EB Median Widening (Bridge over International Drive) | No | 24-Oct-16 | 11-Jun-17 |
| IBEBM-ST470 | PH IB - Remove Concrete Forms for Pier 2, 3, 4 (Footer, Column & Pier Cap) - EB Median Widening (Bridge over John Young | No | 26-Apr-16 | 11-Jun-17 |
| IBEBM-ST480 | PH IB - Temp Sheet Pile Removal - EB Median Widening (Bridge over John Young PKWY) | No | 05-May-16 | 11-Jun-17 |
| IBEBM-ST490 | PH IB - Wall Bent 1 - EB Median Widening (Bridge over John Young PKWY) | No | 05-Aug-16 | 11-Jun-17 |
| IBEBM-ST510 | PH IB - End Bent 1 - EB Median Widening (Bridge over John Young PKWY) | No | 03-Aug-16 | 11-Jun-17 |
| IBEBM-ST520 | PH IB - Wall Bent 5 - EB Median Widening (Bridge over John Young PKWY) | No | 13-Jun-16 | 11-Jun-17 |
| IBEBM-ST530 | PH IB - End Bent 4 - EB Median Widening (Bridge over Shingle Creek) | No | 05-May-16 | 11-Jun-17 |
| IBEBM-ST540 | PH IB - Pier 2,(F/R/P) (Footer, Column & Pier Cap) - EB Median Widening (Bridge over Universal BLVD) | No | 10-Jun-16 | 11-Jun-17 |
| IBEBM-ST550 | PH IB - Approach Slabs - EB Median Widening (Bridge over International DR) | No | 12-Jan-17 | 11-Jun-17 |
| IBEBM-ST560 | PH IB - Concrete Slope Pavement - EB Median Widening (Bridge over International DR) | No | 13-Jun-16 | 11-Jun-17 |
| IBEBM-ST570 | PH IB - End Bent 5 - EB Median Widening (Bridge over John Young PKWY) | No | 13-Jun-16 | 11-Jun-17 |
| IBEBM-ST580 | PH IB - Lighting Conduit - EB Median Widening (Bridge over International DR) | No | 26-Jan-17 | 11-Jun-17 |
| IBEBM-ST590 | PH IB - Traffic Railing (32") - EB Median Widening (Bridge over International DR) | No | 07-Feb-17 | 11-Jun-17 |
| IBEBM-ST600 | PH IB - Grind and Groove - EB Median Widening (Bridge over International DR) | No | 20-Feb-17 | 11-Jun-17 |
| IBEBM-ST610 | PH IB - Curing for Pier 2,(Footer, Column & Pier Cap) - EB Median Widening (Bridge over Universal BLVD) | No | 04-Aug-16 | 11-Jun-17 |
| IBEBM-ST620 | PH IB - Set Beams - EB Median Widening (Bridge over Shingle Creek) | No | 23-May-16 | 11-Jun-17 |
| IBEBM-ST630 | PH IB - Removal concrete form for Pier 2,(Footer, Column & Pier Cap) - EB Median Widening (Bridge over Universal BLVD) | No | 05-Aug-16 | 11-Jun-17 |
| IBEBM-ST640 | PH IB - Temp Sheet Pile Removal - EB Median Widening (Bridge over universal BLVD) | No | 26-Jul-16 | 11-Jun-17 |
| IBEBM-ST650 | PH IB - Wall Bent 1 - EB Median Widening (Bridge over universal BLVD) | No | 02-Sep-16 | 11-Jun-17 |
| IBEBM-ST660 | PH IB - Set Beams - EB Median Widening (Bridge over John Young PKWY) | No | 27-Sep-16 | 11-Jun-17 |
| IBEBM-ST670 | PH IB - Superstructure Deck - EB Median Widening (Bridge over John Young PKWY) | No | 21-Oct-16 | 11-Jun-17 |
| IBEBM-ST680 | PH IB - End Bent 1 - EB Median Widening (Bridge over universal BLVD) | No | 18-Aug-16 | 11-Jun-17 |
| IBEBM-ST690 | PH IB - Superstructure Deck- EB Median Widening (Bridge over Shingle Creek) | No | 26-May-16 | 11-Jun-17 |
| IBEBM-ST700 | PH IB - Wall Bent 3 - EB Median Widening (Bridge over universal BLVD) | No | 06-May-16 | 11-Jun-17 |
| IBEBM-ST710 | PH IB - End Bent 3 - EB Median Widening (Bridge over universal BLVD) | No | 20-Apr-16 | 11-Jun-17 |
| IBEBM-ST720 | PH IB - Curing for End Bent 5 - EB Median Widening (Bridge over John Young PKWY) | No | 22-Jul-16 | 11-Jun-17 |
| IBEBM-ST730 | PH IB - Approach Slabs - EB Median Widening (Bridge over John Young PKWY) | No | 15-Feb-17 | 11-Jun-17 |
| IBEBM-ST740 | PH IB - Concrete Slope Pavement - EB Median Widening (Bridge over John Young PKWY) | No | 12-Sep-16 | 11-Jun-17 |
| IBEBM-ST750 | PH IB - Set Beams - EB Median Widening (Bridge over Universal BLVD) | No | 11-Oct-16 | 11-Jun-17 |
| IBEBM-ST760 | PH IB - Superstructure Deck - EB Median Widening Bridge over Universal BLVD) | No | 24-Oct-16 | 11-Jun-17 |
| IBEBM-ST770 | PH IB - Lighting Conduit - EB Median Widening (Bridge over John Young PKWY) | No | 01-Feb-17 | 11-Jun-17 |
| IBEBM-ST780 | PH IB - Traffic Railing (32") - EB Median Widening (Bridge over John Young PKWY) | No | 03-Mar-17 | 11-Jun-17 |
| IBEBM-ST790 | PH IB - Grind and Groove - EB Median Widening (Bridge over John Young PKWY) | No | 28-Feb-17 | 11-Jun-17 |
| IBEBM-ST800 | PH IB - Approach Slabs - EB Median Widening (Bridge over Shingle Creek) | No | 13-Jul-16 | 11-Jun-17 |
| IBEBM-ST810 | PH IB - Grind and Groove - EB Median Widening (Bridge over Shingle Creek) | No | 03-Aug-16 | 11-Jun-17 |
| IBEBM-ST840 | PH IB - Approach Slabs - EB Median Widening (Bridge over universal BLVD) | No | 20-Jan-17 | 11-Jun-17 |
| IBEBM-ST850 | PH IB - Concrete Slope Pavement - EB Median Widening (Bridge over universal BLVD) | No | 06-Jun-16 | 11-Jun-17 |
| IBEBM-ST860 | PH IB - Lighting Conduit - EB Median Widening (Bridge over universal BLVD) | No | 30-Jan-17 | 11-Jun-17 |
| IBEBM-ST870 | PH IB - Traffic Railing (32") - EB Median Widening (Bridge over universal BLVD) | No | 09-Feb-17 | 11-Jun-17 |
| IBEBM-ST880 | PH IB - Grind and Groove - EB Median Widening (Bridge over universal BLVD) | No | 21-Feb-17 | 11-Jun-17 |
| IBEBM-ST890 | PH IB - Demo Bridge Deck - EB Median Widening (Bridge over International DR) | No | 14-Mar-16 | 11-Jun-17 |
| IBEBM-ST900 | PH IB - Demo Bridge Deck - EB Median Widening (Bridge over universal BLVD) | No | 29-Feb-16 | 11-Jun-17 |
| IBEBM-ST910 | PH IB - Demo Bridge Deck - EB Median Widening (Bridge over Shingle Creek) | No | 22-Nov-15 | 11-Jun-17 |
| IBEBM-ST920 | PH IB - Remove Beams - EB Median Widening (Bridge over Shingle Creek) | No | 09-Dec-15 | 11-Jun-17 |
| IBEBM-ST930 | PH IB - Demo Pile Caps - EB Median Widening (Bridge over Shingle Creek) | No | 20-Dec-15 | 11-Jun-17 |
| IBEBM-ST940 | PH IB - Extract Piles - EB Median Widening (Bridge over Shingle Creek) | No | 30-Jan-16 | 11-Jun-17 |
| IBEBM-ST950 | PH IB - Demo Bridge Deck - EB Median Widening (Bridge over John Young PKWY) | No | 04-Jan-16 | 11-Jun-17 |
| IBEBM-ST960 | PH IB - Pier 2, 3, 4(F/R/P) (Footer, Column) - EB Median Widening (Bridge over John Young PKWY) | No | 09-Mar-16 | 11-Jun-17 |
| IBEBM-ST970 | PH IB - Curing for End Bent 3 - EB Median Widening (Bridge over universal BLVD) | No | 10-May-16 | 11-Jun-17 |
| IBEBM-ST980 | PH IB - Curing for End Bent 4 - EB Median Widening (Bridge over Shingle Creek) | No | 18-May-16 | 11-Jun-17 |
| IBEBM-ST990 | PH IB - Bolt/Pin Temp B/W - EB Median Widening (Bridge over Shingle Creek) | No | 04-Aug-16 | 11-Jun-17 |
| IBEBM-TC110 | PH IB - Set Temp Traffic Barriers for Phase IIA - EB Median Widening | No | 18-Jul-16 | 11-Jun-17 |
| IBEBM-TC130 | PH IB - Temp Striping for Phase IIA - EB Median Widening | No | 18-Jul-16 | 11-Jun-17 |
| IBEBM-TC210 | PH IB - Construct Diversion at Shingle Creek- EB Median Widening | No | 20-Jun-16 | 11-Jun-17 |
| IBEBM-W100 | PH IB - Median Wall - Grading (JYP to TPK) | No | 11-May-16 | 11-Jun-17 |
| IBEBM-W110 | PH IB - Median Wall - FFP Footing/Stem (JYP to TPK) | No | 20-May-16 | 11-Jun-17 |
| IBEBM-W130 | PH IB - Wire (mse) Retaining Wall TW 18 - EB Median Widening (SR528) | No | 06-Jun-16 | 11-Jun-17 |
| IBEBM-W140 | PH IB - Wire (mse) Retaining Wall TW 20 - EB Median Widening (SR528) | No | 06-Jun-16 | 11-Jun-17 |
| IBEBO-EW110 | PH IB - Pond Excav/Embank JYP to TPK - EB Outside Widening | No | 16-Nov-15 | 11-Jun-17 |
| IBEBO-EW120 | PH IB - Pond Excav/Embank I-4 to Int. Dr. - EB Outside Widening | No | 16-Jan-17 | 11-Jun-17 |
| IBEBO-EW130 | PH IB - Pond Excav/Embank JYP to Universal - WB Outside Widening | No | 16-Nov-15 | 11-Jun-17 |
| IBEBO-EW140 | PH IB - Pond Excav/Embank Universal to Int. Dr. - WB Outside Widening | No | 19-Nov-15 | 13-Jun-17 |
| IBEBO-EW150 | PH IB - Pond Excav/Embank Universal to Int. Dr. - EB Outside Widening | No | 16-Nov-15 | 11-Jun-17 |
| IBEBO-EW160 | PH IB - Pond Excav/Embank Universal to JYP - EB Outside Widening | No | 30-Nov-15 | 13-Jun-17 |
| IBEBO-EW170 | PH IB - Pond Excav/Embank Int. Dr. to I-4 - WB Outside Widening | No | 18-Jan-16 | 16-Jun-17 |
| IBEBO-GC100 | PH IB - Remove Existing Overhead Sign (sta 356+25) & Foundation - EB Outside Widening | No | 08-Sep-16 | 11-Jun-17 |
| IBEBO-SP150 | PH IB - Drainage (Pond 5C @ John Young) - EB Outside Widening (Ponds) | No | 04-Aug-16 | 19-Jun-17 |
| IBR-AP120 | PH IB - Asphalt - Structural - Ramp C (Redundant) | No | 19-Dec-16 | 11-Jun-17 |
| IBR-EW110 | PH IB - Embankment - Ramp C (Redundant) | No | 19-Dec-16 | 11-Jun-17 |
| IBR-GC120 | PH IB - Guardrail (Roadway) - Ramp B/C Gore (Activity Not Req'd) | No | 19-Dec-16 | 06-Jul-17 |
| IBR-GC130 | PH IB - Clear & Grub/Demo - Ramp C (Redundant) | No | 19-Dec-16 | 11-Jun-17 |
| IBR-GC150 | PH IB - Performance Turf, SOD - Ramp C (Redundant) | No | 19-Dec-16 | 11-Jun-17 |
| IBR-GC160 | PH IB - Guardrail (Roadway) - Ramp C (Redundant) | No | 19-Dec-16 | 11-Jun-17 |
| IBR-IDS10 | PH IB - Install Drilled Shafts (1-13) | No | 04-Mar-16 | 11-Jun-17 |
| IBR-IHM300 | PH IB - Install High Mast/Service (1-3) | No | 06-Jun-16 | 11-Jun-17 |
| IBR-RW120 | PH IB - Stabilization - Ramp C (Redundant) | No | 19-Dec-16 | 11-Jun-17 |
| IBR-RW130 | PH IB - Base - Ramp C (Redundant) | No | 19-Dec-16 | 11-Jun-17 |
| IBR-TC100 | PH IB - Set Temp Traffic Barriers - Ramp B/C Gore | No | 22-May-17 | 11-Jun-17 |
| IBR-TC110 | PH IB - Set Temp Traffic Barriers - Ramp C (Redundant) | No | 19-Dec-16 | 11-Jun-17 |
| IBWBM-AP100 | PH IB - Asphalt - Structural - WB Median Widening | No | 16-Nov-16 | 11-Jun-17 |
| IBWBM-GC100 | PH IB - Median Clearing and Grubbing - WB Median Widening | No | 27-Oct-15 | 11-Jun-17 |
| IBWBM-RW110 | PH IB - Grade for Permanent Shoulder Construction (JYP-TRP) - WB Median Widening | No | 06-Jun-16 | 11-Jun-17 |
| IBWBM-RW111 | PH IB - Stabilization for Permanent Shoulder Construction (JYP-TRP) - WB Median Widening | No | 13-Jul-16 | 11-Jun-17 |
| IBWBM-RW130 | PH IB - Grade (JYP-Universal) - WB Median Widening | No | 26-Oct-16 | 11-Jun-17 |
| IBWBM-RW140 | PH IB - Stabilization (JYP-Universal) - WB Median Widening | No | 28-Oct-16 | 11-Jun-17 |
| IBWBM-RW150 | PH IB - Base (JYP-Universal) - WB Median Widening | No | 03-Nov-16 | 11-Jun-17 |
| IBWBM-RW160 | PH IB - Grade (Universal-International Drv.) - WB Median Widening | No | 14-Dec-16 | 11-Jun-17 |
| IBWBM-RW170 | PH IB - Stabilization (Universal-International Drv.) - WB Median Widening | No | 14-Dec-16 | 11-Jun-17 |
| IBWBM-RW180 | PH IB - Base (Universal-International Drv.) - WB Median Widening | No | 14-Dec-16 | 11-Jun-17 |
| IBWBM-RW190 | PH IB - Grade (International Drive-I4) - WB Median Widening | No | 15-Dec-16 | 11-Jun-17 |
| IBWBM-RW200 | PH IB - Stabilization (International Drv.-I4) - WB Median Widening | No | 15-Dec-16 | 11-Jun-17 |
| IBWBM-RW210 | PH IB - Base (International Drv.-I4) - WB Median Widening | No | 15-Dec-16 | 11-Jun-17 |
| IBWBM-RW220 | PH IB - Base for Permanent Shoulder Construction (JYP-TRP) - WB Median Widening | No | 27-Oct-16 | 16-Jun-17 |
| IBWBM-RW230 | PH IB - Pavement for Permanent Shoulder Construction (JYP-TRP) - WB Median Widening | No | 15-Nov-16 | 22-Jun-17 |
| IBWBM-RW240 | PH IB - Pavement for Permanent Shoulder Construction (Universal-International Drv.) - WB Median Widening | No | 18-Jul-16 | 11-Jun-17 |
| IBWBM-SP100 | PH IB - Drainage for JYP Interchange (Sta 354 +04) | No | 12-Apr-16 | 11-Jun-17 |
| IBWBM-SP110 | PH IB - Drainage for JYP to STA 390 | No | 18-Feb-16 | 11-Jun-17 |
| IBWBM-SP120 | PH IB - Drainage for JYP to Int. Dr. (Sta 354+04 to 234+50) | No | 12-Apr-16 | 11-Jun-17 |
| IBWBM-SP140 | PH IB - Drainage for STA 390 to TPK | No | 08-Feb-16 | 11-Jun-17 |
| IBWBM-ST110 | PH IB - Construct Crane Access - WB Median Widening (Bridge over International DR) | No | 17-Mar-16 | 11-Jun-17 |
| IBWBM-ST120 | PH IB - Demo Traffic Rail - WB Median Widening (Bridge over International DR) | No | 14-Mar-16 | 11-Jun-17 |
| IBWBM-ST130 | PH IB - Test Pile H-Piles - WB Median Widening (Bridge over International DR) | No | 28-Mar-16 | 11-Jun-17 |
| IBWBM-ST140 | PH IB - Temp Sheet Pile - WB Median Widening (Bridge over International DR) | No | 16-May-16 | 11-Jun-17 |
| IBWBM-ST150 | PH IB - Production Pile - WB Median Widening (Bridge over International DR) | No | 28-Mar-16 | 11-Jun-17 |
| IBWBM-ST160 | PH IB - Construct Crane Access - WB Median Widening (Bridge over universal BLVD) | No | 21-Feb-16 | 11-Jun-17 |
| IBWBM-ST170 | PH IB - Pier 2, (F/R/P)(Footer, Column & Pier Cap) - WB Median Widening (Bridge over International DR) | No | 18-May-16 | 11-Jun-17 |
| IBWBM-ST180 | PH IB - Demo Traffic Rail / End Bents - WB Median Widening (Bridge over universal BLVD) | No | 29-Feb-16 | 11-Jun-17 |
| IBWBM-ST190 | PH IB - Test Pile Concrete - WB Median Widening (Bridge over universal BLVD) | No | 10-Aug-16 | 11-Jun-17 |
| IBWBM-ST200 | PH IB - Temp Sheet Pile - WB Median Widening (Bridge over universal BLVD) | No | 08-Jun-16 | 11-Jun-17 |
| IBWBM-ST210 | PH IB - Production Pile Concrete - WB Median Widening (Bridge over universal BLVD) | No | 10-Mar-16 | 11-Jun-17 |
| IBWBM-ST220 | PH IB - Curing for Pier 2, (Footer, Column & Pier Cap) - WB Median Widening (Bridge over International DR) | No | 27-Jul-16 | 11-Jun-17 |
| IBWBM-ST230 | PH IB - Construct Crane Access - WB Median Widening (Bridge over John Young PKWY) | No | 04-Dec-15 | 11-Jun-17 |
| IBWBM-ST240 | PH IB - Demo Traffic Rails - WB Median Widening (Bridge over John Young PKWY) | No | 04-Jan-16 | 11-Jun-17 |
| IBWBM-ST250 | PH IB - Test Pile (H Piles) - WB Median Widening (Bridge over John Young PKWY) | No | 14-Dec-15 | 11-Jun-17 |
| IBWBM-ST260 | PH IB - Removal of Concrete Forms for Pier 2, (Footer, Column & Pier Cap) - (Bridge over International DR) | No | 04-Aug-16 | 11-Jun-17 |
| IBWBM-ST270 | PH IB - Temp Sheet Pile Removal - WB Median Widening (Bridge over International DR) | No | 25-Jul-16 | 11-Jun-17 |
| IBWBM-ST280 | PH IB - Wall Bent 1 - WB Median Widening (Bridge over International DR) | No | 18-Apr-16 | 11-Jun-17 |
| IBWBM-ST290 | PH IB - End Bent 1 - WB Median Widening (Bridge over International DR) | No | 18-Apr-16 | 11-Jun-17 |
| IBWBM-ST300 | PH IB - Temp Sheet Pile - WB Median Widening (Bridge over John Young PKWY) | No | 06-Mar-16 | 11-Jun-17 |
| IBWBM-ST310 | PH IB - Production Pile (H Piles) - WB Median Widening (Bridge over John Young PKWY) | No | 25-Jan-16 | 11-Jun-17 |
| IBWBM-ST320 | PH IB - Wall Bent 3 - WB Median Widening (Bridge over International DR) | No | 09-May-16 | 11-Jun-17 |
| IBWBM-ST330 | PH IB - End Bent 3 - WB Median Widening (Bridge over International DR) | No | 05-May-16 | 11-Jun-17 |
| IBWBM-ST340 | PH IB - Pier 2, 3, 4(F/R/P) (Footer, Column & Pier Cap) - WB Median Widening (Bridge over John Young PKWY) | No | 09-Mar-16 | 11-Jun-17 |
| IBWBM-ST350 | PH IB - Set Beams - WB Median Widening (Bridge over International Drive) | No | 13-Oct-16 | 11-Jun-17 |
| IBWBM-ST360 | PH IB - Superstructure Deck - WB Median Widening (Bridge over International Drive) | No | 24-Oct-16 | 11-Jun-17 |
| IBWBM-ST370 | PH IB - Curing For Pier 2, 3, 4(Footer, Column & Pier Cap) - WB Median Widening (Bridge over John Young PKWY) | No | 02-Aug-16 | 11-Jun-17 |
| IBWBM-ST380 | PH IB - Pier 2, (F/R/P)(Footer, Column & Pier Cap) - WB Median Widening (Bridge over Universal BLVD) | No | 13-Jun-16 | 11-Jun-17 |
| IBWBM-ST390 | PH IB - Approach Slabs - WB Median Widening (Bridge over International DR) | No | 12-Jan-17 | 11-Jun-17 |
| IBWBM-ST400 | PH IB - Concrete Slope Pavement - WB Median Widening (Bridge over International DR) | No | 13-Jun-16 | 11-Jun-17 |
| IBWBM-ST410 | PH IB - Removal of Concrete forms for Pier 2, 3, 4 (Footer, Column & Pier Cap) - WB Median Widening (Bridge over JYP) | No | 09-Aug-16 | 11-Jun-17 |
| IBWBM-ST420 | PH IB - Wall Bent 1 - WB Median Widening (Bridge over John Young PKWY) | No | 05-Aug-16 | 11-Jun-17 |
| IBWBM-ST430 | PH IB - Lighting Conduit - WB Median Widening (Bridge over International DR) | No | 26-Jan-17 | 11-Jun-17 |
| IBWBM-ST440 | PH IB - Traffic Railing (32") - WB Median Widening (Bridge over International DR) | No | 07-Feb-17 | 11-Jun-17 |
| IBWBM-ST450 | PH IB - Temp Sheet Pile Removal - WB Median Widening (Bridge over John Young PKWY) | No | 05-May-16 | 11-Jun-17 |
| IBWBM-ST460 | PH IB - End Bent 1 - WB Median Widening (Bridge over John Young PKWY) | No | 03-Aug-16 | 11-Jun-17 |
| IBWBM-ST470 | PH IB - Grind and Groove - WB Median Widening (Bridge over International DR) | No | 20-Feb-17 | 11-Jun-17 |
| IBWBM-ST480 | PH IB - Curing for Pier 2, (Footer, Column & Pier Cap) - WB Median Widening (Bridge over Universal BLVD) | No | 04-Aug-16 | 11-Jun-17 |
| IBWBM-ST490 | PH IB - Wall Bent 5 - WB Median Widening (Bridge over John Young PKWY) | No | 13-Jun-16 | 11-Jun-17 |
| IBWBM-ST500 | PH IB - Removal of Concrete Forms for Pier 2, (Footer, Column & Pier Cap) - WB Median Widening (Bridge over Universal BL | No | 05-Aug-16 | 11-Jun-17 |
| IBWBM-ST510 | PH IB - Temp Sheet Pile Removal - WB Median Widening (Bridge over universal BLVD) | No | 26-Jul-16 | 11-Jun-17 |
| IBWBM-ST520 | PH IB - Wall Bent 1 - WB Median Widening (Bridge over universal BLVD) | No | 02-Sep-16 | 11-Jun-17 |
| IBWBM-ST530 | PH IB - End Bent 5 - WB Median Widening (Bridge over John Young PKWY) | No | 13-Jun-16 | 11-Jun-17 |
| IBWBM-ST540 | PH IB - End Bent 1 - WB Median Widening (Bridge over universal BLVD) | No | 18-Aug-16 | 11-Jun-17 |
| IBWBM-ST550 | PH IB - Wall Bent 3 - WB Median Widening (Bridge over universal BLVD) | No | 06-May-16 | 11-Jun-17 |
| IBWBM-ST560 | PH IB - Set Beams - WB Median Widening (Bridge over John Young PKWY) | No | 27-Sep-16 | 11-Jun-17 |
| IBWBM-ST570 | PH IB - End Bent 3 - WB Median Widening (Bridge over universal BLVD) | No | 20-Apr-16 | 11-Jun-17 |
| IBWBM-ST580 | PH IB - Superstructure Deck - WB Median Widening (Bridge over John Young PKWY) | No | 18-Nov-16 | 11-Jun-17 |
| IBWBM-ST590 | PH IB - Set Beams - WB Median Widening (Bridge over Universal BLVD) | No | 11-Oct-16 | 11-Jun-17 |
| IBWBM-ST600 | PH IB - Superstructure Deck - WB Median Widening Bridge over Universal BLVD) | No | 06-Dec-16 | 11-Jun-17 |
| IBWBM-ST610 | PH IB - Approach Slabs - WB Median Widening (Bridge over John Young PKWY) | No | 15-Feb-17 | 11-Jun-17 |
| IBWBM-ST620 | PH IB - Concrete Slope Pavement - WB Median Widening (Bridge over John Young PKWY) | No | 06-Sep-16 | 11-Jun-17 |
| IBWBM-ST630 | PH IB - Lighting Conduit - WB Median Widening (Bridge over John Young PKWY) | No | 31-Jan-17 | 11-Jun-17 |
| IBWBM-ST640 | PH IB - Traffic Railing (32") - WB Median Widening (Bridge over John Young PKWY) | No | 06-Mar-17 | 11-Jun-17 |
| IBWBM-ST650 | PH IB - Approach Slabs - WB Median Widening (Bridge over universal BLVD) | No | 25-Jan-17 | 11-Jun-17 |
| IBWBM-ST660 | PH IB - Concrete Slope Pavement - WB Median Widening (Bridge over universal BLVD) | No | 15-Sep-16 | 11-Jun-17 |
| IBWBM-ST670 | PH IB - Grind and Groove - WB Median Widening (Bridge over John Young PKWY) | No | 27-Feb-17 | 11-Jun-17 |
| IBWBM-ST680 | PH IB - Lighting Conduit - WB Median Widening (Bridge over universal BLVD) | No | 31-Jan-17 | 11-Jun-17 |
| IBWBM-ST690 | PH IB - Traffic Railing (32") - WB Median Widening (Bridge over universal BLVD) | No | 09-Feb-17 | 11-Jun-17 |
| IBWBM-ST700 | PH IB - Grind and Groove - WB Median Widening (Bridge over universal BLVD) | No | 21-Feb-17 | 11-Jun-17 |
| IBWBM-ST710 | PH IB - Demo Bridge Deck- WB Median Widening (Bridge over universal BLVD) | No | 22-Mar-16 | 11-Jun-17 |
| IBWBM-ST720 | PH IB - Demo Bridge Deck - WB Median Widening (Bridge over John Young PKWY) | No | 04-Jan-16 | 11-Jun-17 |
| IBWBM-ST730 | PH IB - Demo Bridge Deck - WB Median Widening (Bridge over International DR) | No | 14-Mar-16 | 11-Jun-17 |
| IBWBM-ST740 | PH IB - Curing for End Bent 5 - WB Median Widening (Bridge over John Young PKWY) | No | 22-Jul-16 | 11-Jun-17 |
| IBWBM-ST750 | PH IB - Curing for End Bent 3 - WB Median Widening (Bridge over International DR) | No | 13-May-16 | 11-Jun-17 |
| IBWBM-ST760 | PH IB - Curing for End Bent 3 - WB Median Widening (Bridge over universal BLVD) | No | 16-May-16 | 11-Jun-17 |
| IBWBM-TC150 | PH IB - Construct Diversion at I-Drive - WB Median Widening | No | 08-Feb-17 | 11-Jun-17 |
| IBWBM-W100 | PH IB - Median Wall - Construct/ slip Top (JYP to TPK) | No | 27-Jun-16 | 11-Jun-17 |
| IBWBM-W120 | PH IB - Wire (mse) Retaining Wall TW 19 - WB Median Widening (SR528) | No | 06-Jun-16 | 11-Jun-17 |
| IBWBM-W140 | PH IB - Wire (mse) Retaining Wall TW 21 - WB Median Widening (SR528) | No | 06-Jun-16 | 11-Jun-17 |
| IBWBO-EW100 | PH IB - Pond Excav/Embank JYP to TPK - WB Outside Widening | No | 07-Dec-15 | 16-Jun-17 |
| IBWBO-SP100 | PH IB - Jack & Bore JYP Interchange (Sta 354 +04) | No | 11-Apr-16 | 11-Jun-17 |
| IBWBO-SP130 | PH IB - Jack & Bore JYP to TPK (East of Sta 354+04 to 415+33) | No | 06-Jan-16 | 11-Jun-17 |
| IBWBO-SP140 | PH IB - Jack & Bore JYP to Int. Dr. (Sta 354+04 to 234+50) | No | 17-Mar-16 | 11-Jun-17 |
| IBWBO-SP160 | PH IB - Drainage Outfalls (Pond 4A @ John Young) - WB Outside Widening Area (Ponds) | No | 13-Jul-16 | 11-Jun-17 |
| IBWBO-SP190 | PH IB - Drainage Outfalls (Pond 5A @ John Young) - WB Outside Widening Area (Ponds) | No | 24-Oct-16 | 06-Jul-17 |
| IIAEBO-AP100 | PH IIA - Mill & Resurface (sacrificial) - EB Outside Widening (SR528) | No | 29-Mar-17 | 11-Jun-17 |
| IIAEBO-TC100 | PH IIA - Install Sign & Traffic Control Devices - EB Outside Widening | No | 20-Sep-15 | 11-Jun-17 |
| IIAEBO-TC120 | PH IIA - MOT Shift for Phase IIA - EB Outside Widening | No | 07-Sep-16 | 11-Jun-17 |
| IIAR-EW100 | PH IIB - Embankment - Ramp O | No | 14-Dec-15 | 11-Jun-17 |
| IIAR-RW100 | PH IIB - Stabilization - Ramp O | No | 18-May-17 | 11-Jun-17 |
| IIAR-RW110 | PH IIB - Base - Ramp O | No | 30-May-17 | 11-Jun-17 |
| IIAR-SP100 | PH IIA - Jack & Bore (42" (Sta 351+00 near Duke energy access platform) - Ramp O | No | 06-Jul-16 | 11-Jun-17 |
| IIAR-SP110 | PH IIB - Drainage - Ramp O | No | 26-Jul-16 | 11-Jun-17 |
| IIAR-TC140 | PH IIA - Temp Striping New Ramp Alignment - Ramp O | No | 07-Sep-16 | 19-Jun-17 |
| IIAR100 | PH IIA - Construct Ramp O Diversion - Ramp O | No | 11-Jul-16 | 11-Jun-17 |
| IIAR110 | PH IIA - Construct Ramp O Diversion - Ramp O (Tie in to EB) | No | 07-Sep-16 | 11-Jun-17 |
| IIBEBO-AP100 | PH IIB - Mill & Resurface (sacrificial) - EB Outside Widening (SR528) | No | 05-Apr-17 | 11-Jun-17 |
| IIBEBO-EW101 | PH IIB - Embankment (Int. Drive - Universal) - EB Outside Widening | No | 15-Sep-16 | 10-Jul-17 |
| IIBEBO-EW102 | PH IIB - Embankment (Universal - JYP) - EB Outside Widening | No | 03-Oct-16 | 10-Jul-17 |
| IIBEBO-EW112 | PH IIB - Embankment (Int. Drive - Universal) - at Toll Facility | No | 10-Oct-16 | 11-Jun-17 |
| IIBEBO-GC100 | PH IIB - MISC. Demo - EB Outside Widening | No | 06-Feb-17 | 11-Jun-17 |
| IIBEBO-GC110 | PH IIB - Performance Turf, SOD - EB Outside Widening | No | 20-Mar-17 | 10-Jul-17 |
| IIBEBO-RW111 | PH IIB - Stabilization (Int. Drive - Universal) - EB Outside Widening | No | 03-Apr-17 | 10-Jul-17 |
| IIBEBO-RW112 | PH IIB - Stabilization (Universal - JYP) - EB Outside Widening - (STA 291 to 320) | No | 17-Mar-17 | 11-Jun-17 |
| IIBEBO-RW170 | PH IIB - Stabilization (Universal - JYP) - EB Outside Widening - (STA 320 to 332) | Yes | 17-Mar-17 | 11-Jun-17 |
| IIBEBO-RW180 | PH IIB - Base (Universal - JYP) - EB Outside Widening - LR - (STA 320 to 332) | Yes | 01-May-17 | 11-Jun-17 |
| IIBEBO-SP110 | PH IIB - Drainage (Int. Drive - Universal) - EB Outside Widening (SR528) | No | 07-Nov-16 | 11-Jun-17 |
| IIBEBO-SP120 | PH IIB - Drainage (Universal - JYP) - EB Outside Widening (SR528) | No | 20-Mar-17 | 11-Jun-17 |
| IIBEBO-SP130 | PH IIB - Gutter Drainage - STA 228 - 248 (EB Outside) | No | 18-May-17 | 10-Jul-17 |
| IIBEBO-SP140 | PH IIB - Gutter Drainage - STA 280 - 299 (EB Outside) | No | 08-May-17 | 10-Jul-17 |
| IIBEBO-SP150 | PH IIB - Gutter Drainage - STA 326 - 336 (EB Outside) | No | 05-Apr-17 | 10-Jul-17 |
| IIBEBO-ST1 | PH IIB - Construct Crane Access - EB Outside Widening (Bridge over International DR) | No | 18-Jul-16 | 11-Jun-17 |
| IIBEBO-ST10 | PH IIB - Test Pile - EB Outside Widening (Bridge over universal BLVD) | No | 10-Oct-16 | 11-Jun-17 |
| IIBEBO-ST11 | PH IIB - Temp Sheet Pile - EB Outside Widening (Bridge over universal BLVD) | No | 17-Oct-16 | 11-Jun-17 |
| IIBEBO-ST110 | PH IIB - Demo Traffic Rails - EB Outside Widening (Bridge over Shingle Creek) | No | 10-Oct-16 | 11-Jun-17 |
| IIBEBO-ST12 | PH IIB - Production Pile - EB Outside Widening (Bridge over universal BLVD) | No | 17-Oct-16 | 11-Jun-17 |
| IIBEBO-ST120 | PH IIB - Wall Bent 1 - EB Outside Widening (Bridge 750629 Ramp S over JYP) | No | 30-Jan-17 | 11-Jun-17 |
| IIBEBO-ST130 | PH IIB - Demo Traffic Rails - EB Outside Widening (Bridge over International DR) | No | 12-Apr-17 | 11-Jun-17 |
| IIBEBO-ST14 | PH IIB - Pier 2, (F/R/P)(Footer, Column & Pier Cap) - EB Outside Widening (Bridge over Universal BLVD) | No | 31-Oct-16 | 11-Jun-17 |
| IIBEBO-ST150 | PH IIB - End Bent 1 - EB Outside Widening (Bridge 750629 Ramp S over JYP) | No | 24-Jan-17 | 11-Jun-17 |
| IIBEBO-ST16 | PH IIB - Curing for Pier 2, (Footer, Column & Pier Cap) - EB Outside Widening (Bridge over Universal BLVD) | No | 08-Dec-16 | 11-Jun-17 |
| IIBEBO-ST17 | PH IIB - Removal of Concrete Forms Pier 2, (Footer, Column & Pier Cap) - EB Outside Widening (Bridge over Universal BLV | No | 15-Dec-16 | 11-Jun-17 |
| IIBEBO-ST170 | PH IIB - Pier 2, 3, (F/R/P)(Pile Cap) - EB Outside Widening (Bridge over Shingle Creek) | No | 07-Nov-16 | 11-Jun-17 |
| IIBEBO-ST18 | PH IIB - Temp Sheet Pile Removal - EB Outside Widening (Bridge over universal BLVD) | No | 15-Dec-16 | 11-Jun-17 |
| IIBEBO-ST180 | PH IIB - Wall Bent 5 - EB Outside Widening (Bridge 750629 Ramp S over JYP) | No | 13-Jan-17 | 11-Jun-17 |
| IIBEBO-ST19 | PH IIB - Construct Crane Access - EB Outside Widening (Bridge 750629 Ramp S over JYP) | No | 04-Jan-16 | 11-Jun-17 |
| IIBEBO-ST20 | PH IIB - Test Pile (H Piles) - EB Outside Widening (Bridge 750629 Ramp S over JYP) | No | 05-Jan-16 | 11-Jun-17 |
| IIBEBO-ST21 | PH IIB - Temp Sheet Pile - EB Outside Widening (Bridge 750629 Ramp S over JYP) | No | 17-Mar-16 | 11-Jun-17 |
| IIBEBO-ST210 | PH IIB - Curing Pier 2, 3, (Pile Cap) - EB Outside Widening (Bridge over Shingle Creek) | No | 10-Jan-17 | 11-Jun-17 |
| IIBEBO-ST22 | PH IIB - Production Pile (H Piles) (1-31) - EB Outside Widening (Bridge 750629 Ramp S over JYP) | No | 09-Feb-16 | 11-Jun-17 |
| IIBEBO-ST220 | PH IIB - End Bent 5 - EB Outside Widening (Bridge 750629 Ramp S over JYP) | No | 10-Jan-17 | 11-Jun-17 |
| IIBEBO-ST23 | PH IIB - Production Pile (H Piles) (32-62) -EB Outside Widening (Bridge 750629 Ramp S over JYP) | No | 18-Apr-16 | 11-Jun-17 |
| IIBEBO-ST230 | PH IIB - Removal concrete form for Pier 2, 3, (Pile Cap) - EB Outside Widening (Bridge over Shingle Cr | No | 20-Jan-17 | 11-Jun-17 |
| IIBEBO-ST24 | PH IIB - Pier 2, 3, 4 (F/R/P)(Footer, Column) - EB Outside Widening (Bridge 750629 Ramp S over JYP) | No | 18-Mar-16 | 11-Jun-17 |
| IIBEBO-ST240 | PH IIB - Wall Bent 1 - EB Outside Widening (Bridge over Shingle Creek) | No | 11-Jan-17 | 11-Jun-17 |
| IIBEBO-ST25 | PH IIB - Curing for Pier 2, 3, 4(Footer, Column & Pier Cap) - EB Outside Widening (Bridge 750629 Ramp S over JYP) | No | 14-Nov-16 | 11-Jun-17 |
| IIBEBO-ST26 | PH IIB - Remove of Concrete Form Pier 2, 3, 4 (Footer, Column & Pier Cap) - EB Outside Widening (Bridge 750629 Ramp S ov | No | 15-Sep-16 | 11-Jun-17 |
| IIBEBO-ST260 | PH IIB - End Bent 1 - EB Outside Widening (Bridge over Shingle Creek) | No | 11-Jan-17 | 11-Jun-17 |
| IIBEBO-ST27 | PH IIB - Temp Sheet Pile Removal - EB Outside Widening (Bridge 750629 Ramp S over JYP) | No | 12-Aug-16 | 11-Jun-17 |
| IIBEBO-ST28 | PH IIB - Construct Crane Access - EB Outside Widening (Bridge over Shingle Creek) | No | 01-Aug-16 | 11-Jun-17 |
| IIBEBO-ST280 | PH IIB - Set Beams - EB Outside Widening (Bridge 750629 Ramp S over JYP) | No | 13-Feb-17 | 11-Jun-17 |
| IIBEBO-ST290 | PH IIB - Superstructure Deck SIP & Start Rebar - EB Outside Widening (Bridge 750629 Ramp S over JYP) | No | 17-Feb-17 | 11-Jun-17 |
| IIBEBO-ST3 | PH IIB - Temp Sheet Pile - EB Outside Widening (Bridge over International DR) | No | 13-Jun-16 | 11-Jun-17 |
| IIBEBO-ST30 | PH IIB - Production Pile (Concrete) - EB Outside Widening (Bridge over Shingle Creek) | No | 17-Oct-16 | 11-Jun-17 |
| IIBEBO-ST300 | PH IIB - Wall Bent 4 - EB Outside Widening (Bridge over Shingle Creek) | No | 26-Jan-17 | 11-Jun-17 |
| IIBEBO-ST31 | PH IIB - Gravity Wall @ Shingle Creek - EB Outside Widening (Bridge over Shingle Creek) | No | 16-May-16 | 11-Jun-17 |
| IIBEBO-ST310 | PH IIB - End Bent 4 - EB Outside Widening (Bridge over Shingle Creek) | No | 13-Jan-17 | 11-Jun-17 |
| IIBEBO-ST32 | PH IIB - Rip Rap Under Bridge - EB Outside Widening (Bridge over Shingle Creek) | No | 02-Dec-16 | 11-Jun-17 |
| IIBEBO-ST320 | PH IIB - Demo Traffic Rails - EB Outside Widening (Bridge over universal BLVD) | No | 10-Apr-17 | 11-Jun-17 |
| IIBEBO-ST350 | PH IIB - Superstructure Deck Finish Rebar\Set screed\Pouring - EB Outside Widening (Bridge 750629 Ramp S over JYP) | No | 10-Mar-17 | 11-Jun-17 |
| IIBEBO-ST4 | PH IIB - Production Pile - EB Outside Widening (Bridge over International DR) | No | 01-May-16 | 11-Jun-17 |
| IIBEBO-ST400 | PH IIB - End Bent 1 - EB Outside Widening (Bridge over universal BLVD) | No | 06-Jun-17 | 16-Jun-17 |
| IIBEBO-ST410 | PH IIB - Set Beams - EB Outside Widening (Bridge over Shingle Creek) | No | 06-Feb-17 | 11-Jun-17 |
| IIBEBO-ST420 | PH IIB - Wall Bent 3 - EB Outside Widening (Bridge over universal BLVD) | No | 08-Jun-17 | 11-Jun-17 |
| IIBEBO-ST430 | PH IIB - Approach Slabs - EB Outside Widening (Bridge 750629 Ramp S over JYP) | No | 01-May-17 | 11-Jun-17 |
| IIBEBO-ST450 | PH IIB - End Bent 3 - EB Outside Widening (Bridge over universal BLVD) | No | 31-May-17 | 26-Jun-17 |
| IIBEBO-ST460 | PH IIB - Lighting Conduit - EB Outside Widening (Bridge 750629 Ramp S over JYP) | No | 17-May-17 | 11-Jun-17 |
| IIBEBO-ST470 | PH IIB - Traffic Railing (32") - EB Outside Widening (Bridge 750629 Ramp S over JYP) | No | 19-May-17 | 11-Jun-17 |
| IIBEBO-ST490 | PH IIB - Superstructure Deck SIP & Start Rebar - EB Outside Widening (Bridge over Shingle Creek) | No | 10-Feb-17 | 11-Jun-17 |
| IIBEBO-ST5 | PH IIB - Pier 2, (F/R/P) (Footer, Column & Pier Cap) - EB Outside Widening (Bridge over International DR) | No | 13-Jun-16 | 14-Jun-17 |
| IIBEBO-ST510 | PH IIB - Grind and Groove - EB Outside Widening (Bridge 750629 Ramp S over JYP) | No | 02-Jun-17 | 11-Jun-17 |
| IIBEBO-ST590 | PH IIB - Approach Slabs - EB Outside Widening (Bridge over Shingle Creek) | No | 27-Mar-17 | 11-Jun-17 |
| IIBEBO-ST6 | PH IIB - Curing for Pier 2, (Footer, Column & Pier Cap) - EB Outside Widening (Bridge over International DR) | No | 05-Aug-16 | 21-Jun-17 |
| IIBEBO-ST600 | PH IIB - Lighting Conduit - EB Outside Widening (Bridge over Shingle Creek) | No | 20-Apr-17 | 11-Jun-17 |
| IIBEBO-ST610 | PH IIB - Traffic Railing (32") - EB Outside Widening (Bridge over Shingle Creek) | No | 24-Apr-17 | 11-Jun-17 |
| IIBEBO-ST620 | PH IIB - Grind and Groove - EB Outside Widening (Bridge over Shingle Creek) | No | 31-May-17 | 11-Jun-17 |
| IIBEBO-ST630 | PH IIB - Demo Bridge Deck - EB Outside Widening (Bridge over International DR) | No | 24-Apr-17 | 11-Jun-17 |
| IIBEBO-ST640 | PH IIB - Demo Bridge Deck - EB Outside Widening (Bridge over universal BLVD) | No | 24-Apr-17 | 11-Jun-17 |
| IIBEBO-ST650 | PH IIB - Demo Bridge Deck - EB Outside Widening (Bridge over Shingle Creek) | No | 11-Oct-16 | 11-Jun-17 |
| IIBEBO-ST660 | PH IIB - Remove Beams - EB Outside Widening (Bridge over Shingle Creek) | No | 11-Oct-16 | 11-Jun-17 |
| IIBEBO-ST670 | PH IIB - Demo Pile Cap - EB Outside Widening (Bridge over Shingle Creek) | No | 12-Oct-16 | 11-Jun-17 |
| IIBEBO-ST680 | PH IIB - Extract Piles - EB Outside Widening (Bridge over Shingle Creek) | No | 13-Oct-16 | 11-Jun-17 |
| IIBEBO-ST690 | PH IIB - Pier 2, 3, 4 (F/R/P)(Pier Cap) - EB Outside Widening (Bridge 750629 Ramp S over JYP) | No | 06-Jul-16 | 11-Jun-17 |
| IIBEBO-ST7 | PH IIB- Removal of Concrete Forms for Pier 2, (Footer, Column & Pier Cap) - EB Outside Widening (Bridge over Internatio | No | 12-Aug-16 | 21-Jun-17 |
| IIBEBO-ST700 | PH IIB - Superstructure Deck (Finish Rebar\Set Screed\Pour) - EB Outside Widening (Bridge over Shingle Creek) | No | 24-Feb-17 | 11-Jun-17 |
| IIBEBO-ST710 | PH IIB - Curing for End Bent 5 - EB Outside Widening (Bridge 750629 Ramp S over JYP) | No | 30-Jan-17 | 11-Jun-17 |
| IIBEBO-ST740 | PH IIB - Curing for End Bent 4 - EB Outside Widening (Bridge over Shingle Creek) | No | 27-Jan-17 | 11-Jun-17 |
| IIBEBO-ST8 | PH IIB - Temp Sheet Pile Removal - EB Outside Widening (Bridge over International DR) | No | 26-Jul-16 | 21-Jun-17 |
| IIBEBO-ST9 | PH IIB - Construct Crane Access - EB Outside Widening (Bridge over universal BLVD) | No | 22-Aug-16 | 11-Jun-17 |
| IIBEBO-TC130 | PH IIB - Set Temp Traffic Barriers - EB Outside Widening | No | 21-Mar-17 | 11-Jun-17 |
| IIBR-AP160 | PH IIB - Asphalt - Structural - Ramp I4- Interstate | No | 19-Dec-16 | 07-Jul-17 |
| IIBR-AP180 | PH IIB - Asphalt - Structural - Ramp U | No | 11-May-17 | 05-Jul-17 |
| IIBR-EHM340 | PH IIB - Existing High Mast Removal (1-8) | No | 01-Mar-17 | 14-Jun-17 |
| IIBR-EHM350 | PH IIB - Existing High Mast Removal (9-18) | No | 05-May-17 | 14-Jun-17 |
| IIBR-EW110 | PH IIB - Embankment - Ramp E | No | 28-Dec-15 | 11-Jun-17 |
| IIBR-EW120 | PH IIB - Embankment - Ramp S-1 | No | 23-May-16 | 11-Jun-17 |
| IIBR-EW122 | PH IIB - Embankment - Ramp A | No | 18-May-16 | 11-Jun-17 |
| IIBR-EW130 | PH IIB - Embankment - Ramp R-1 | No | 20-Mar-17 | 12-Jun-17 |
| IIBR-EW160 | PH IIB - Embankment - Ramp H | No | 28-Nov-16 | 11-Jun-17 |
| IIBR-EW170 | PH IIB - Embankment - Ramp R-2 | No | 20-Mar-17 | 13-Jun-17 |
| IIBR-EW180 | PH IIB - Embankment - Ramp I4- Interstate | No | 19-Dec-16 | 07-Jul-17 |
| IIBR-EW190 | PH IIB - Embankment - Ramp L | No | 03-Apr-17 | 05-Jul-17 |
| IIBR-EW200 | PH IIB - Embankment - Ramp U | No | 15-Dec-15 | 12-Jun-17 |
| IIBR-GC110 | PH IIB - Demo - Ramp E | No | 06-Mar-17 | 11-Jun-17 |
| IIBR-GC130 | PH IIB - Demo - Ramp R-1 | No | 21-Mar-17 | 12-Jun-17 |
| IIBR-GC150 | PH IIB - Demo - Ramp S-1 | No | 16-Jan-17 | 11-Jun-17 |
| IIBR-GC171 | PH IIB - Clear & Grub/Demo - Ramp A | No | 13-Jun-16 | 11-Jun-17 |
| IIBR-GC191 | PH IIB - Performance Turf, SOD - Ramp A | No | 13-Sep-16 | 11-Jun-17 |
| IIBR-GC240 | PH IIB - Demo - Ramp H | No | 07-Mar-17 | 11-Jun-17 |
| IIBR-GC290 | PH IIB - Demo - Ramp R-2 | No | 21-Mar-17 | 11-Jun-17 |
| IIBR-GC300 | PH IIB - Demo - Ramp I4- Interstate | No | 19-Dec-16 | 07-Jul-17 |
| IIBR-GC310 | PH IIB - Demo - Ramp L | No | 20-Mar-17 | 11-Jun-17 |
| IIBR-GC340 | PH IIB - Performance Turf, SOD - Ramp I4- Interstate | No | 19-Dec-16 | 07-Jul-17 |
| IIBR-GC350 | PH IIB - Demo - Ramp U | No | 29-Mar-17 | 12-Jun-17 |
| IIBR-GC400 | PH IIB - Guardrail (Roadway) - Ramp I4- Interstate | No | 19-Dec-16 | 07-Jul-17 |
| IIBR-IDS20 | PH IIB - Install Drilled Shafts (14-35) | No | 14-Sep-16 | 11-Jun-17 |
| IIBR-IDS30 | PH IIB - Install Drilled Shafts (36-57) | No | 03-May-17 | 11-Jun-17 |
| IIBR-IHM310 | PH IIB - Install High Mast/Service (4-6) | No | 27-Oct-16 | 14-Jun-17 |
| IIBR-IHM320 | PH IIB - Install High Mast/Service (7-9) | No | 07-Mar-17 | 22-Jun-17 |
| IIBR-ITS10 | PH IIB - Install Conduit/Boxes (I-4 to International) | No | 28-Sep-16 | 11-Jun-17 |
| IIBR-ITS20 | PH IIB - Install Conduit/Boxes ( International to Univ) | No | 24-Feb-17 | 20-Jun-17 |
| IIBR-ITS30 | PH IIB - Install Conduit/Boxes (Univ to JYP) | No | 27-Jul-16 | 26-Jun-17 |
| IIBR-ITS40 | PH IIB - Install Conduit/Boxes (JYP to TPK) | No | 26-Jul-16 | 28-Jun-17 |
| IIBR-RES120 | PH IIB - Remove Existing Sign Structures (2-4) | No | 20-Mar-17 | 14-Jun-17 |
| IIBR-RW141 | PH IIB - Stabilization - Ramp A | No | 05-Jul-16 | 11-Jun-17 |
| IIBR-RW151 | PH IIB - Base - Ramp A | No | 14-Jul-16 | 11-Jun-17 |
| IIBR-RW210 | PH IIB - Stabilization - Ramp I4- Interstate | No | 19-Dec-16 | 07-Jul-17 |
| IIBR-RW230 | PH IIB - Base - Ramp I4- Interstate | No | 19-Dec-16 | 07-Jul-17 |
| IIBR-RW260 | PH IIB - Stabilization - Ramp U | No | 03-Apr-17 | 05-Jul-17 |
| IIBR-RW270 | PH IIB - Base - Ramp U | No | 12-Apr-17 | 05-Jul-17 |
| IIBR-SM390 | PH IIB - Shoulder Mount Light Pole/Service (International to Univ.) (20 EA) (A) | No | 19-Dec-16 | 05-Jul-17 |
| IIBR-SM400 | PH IIB - Shoulder Mount Light Pole/Service (International to Univ.) (20 EA) (B) | No | 27-Mar-17 | 17-Jul-17 |
| IIBR-SM410 | PH IIB - Shoulder Mount Light Pole/Service (International to Univ.) (20 EA) (C) | No | 25-Apr-17 | 27-Jul-17 |
| IIBR-SM440 | PH IIB - Shoulder Mount Light Pole/Service (Univ. to JYP) (18 EA) (A) | No | 27-Jul-16 | 07-Sep-17 |
| IIBR-SM450 | PH IIB - Shoulder Mount Light Pole/Service (Univ. to JYP) (19 EA) | No | 10-May-17 | 14-Sep-17 |
| IIBR-SM460 | PH IIB - Shoulder Mount Light Pole/Service (Univ. to JYP) (18 EA) (B) | No | 16-May-17 | 22-Sep-17 |
| IIBR-SM470 | PH IIB - Shoulder Mount Light Pole/Service (JYP to TPK) (20 EA) (A) | No | 26-Jul-16 | 29-Sep-17 |
| IIBR-SM480 | PH IIB - Shoulder Mount Light Pole/Service (JYP to TPK) (20 EA) (B) | No | 09-May-16 | 04-Oct-17 |
| IIBR-SP110 | PH IIB - Drainage - Ramp E | No | 22-May-17 | 11-Jun-17 |
| IIBR-SP120 | PH IIB - Drainage (Temp) - Ramp R-1 | No | 10-Apr-17 | 12-Jun-17 |
| IIBR-SP121 | PH IIB - Drainage - Ramp A | No | 13-Jun-16 | 11-Jun-17 |
| IIBR-SP140 | PH IIB - Drainage (Temp) - Ramp S-1 | No | 16-Jan-17 | 11-Jun-17 |
| IIBR-SP160 | PH IIB - Drainage (Temp) - Ramp H | No | 31-Jan-17 | 11-Jun-17 |
| IIBR-SP170 | PH IIB - Drainage (Temp) - Ramp R-2 | No | 20-Mar-17 | 13-Jun-17 |
| IIBR-SP180 | PH IIB - Drainage (Temp) - Ramp I4 Interstate | No | 19-Dec-16 | 07-Jul-17 |
| IIBR-SP190 | PH IIB - Drainage (Temp) - Ramp L | No | 19-Dec-16 | 11-Jun-17 |
| IIBR-SP200 | PH IIB - Drainage (Temp) - Ramp U | No | 19-Dec-16 | 12-Jun-17 |
| IIBR-SP250 | PH IIB - Drainage - Ramp R-2 | No | 17-Apr-17 | 13-Jun-17 |
| IIBR-TC220 | PH IIB - Set Temp Traffic Barriers (Shoulder) - Ramp E | No | 27-Feb-17 | 11-Jun-17 |
| IIBR-TC230 | PH IIB - Temp Striping New Ramp Alignment - Ramp E | No | 28-Feb-17 | 11-Jun-17 |
| IIBR-TC250 | PH IIB - Set Temp Traffic Barriers (Shoulder) - Ramp C | No | 16-Apr-17 | 07-Jul-17 |
| IIBR-TC280 | PH IIB - Set Temp Traffic Barriers (Shoulder) - Ramp I-1 | No | 16-Jan-17 | 11-Jun-17 |
| IIBR-TC290 | PH IIB - Set Temp Traffic Barriers (Shoulder) - Ramp I4- Interstate | No | 19-Dec-16 | 07-Jul-17 |
| IIBR-TC300 | PH IIB - Temp Striping New Ramp Alignment - Ramp I-1 | No | 23-Feb-17 | 11-Jun-17 |
| IIBR-TC310 | PH IIB - Set Temp Traffic Barriers (Shoulder) - Ramp H | No | 27-Feb-17 | 11-Jun-17 |
| IIBR-TC320 | PH IIB - Temp Striping New Ramp Alignment - Ramp H | No | 28-Feb-17 | 11-Jun-17 |
| IIBR-TC330 | PH IIB - Temp Striping New Ramp Alignment - Ramp R-2 | No | 13-Mar-17 | 11-Jun-17 |
| IIBR-TC340 | PH IIB - Set Temp Traffic Barriers (Shoulder) - Ramp R-2 | No | 09-Mar-17 | 11-Jun-17 |
| IIBR-TC360 | PH IIB - Temp Striping New Ramp Alignment - Ramp I4- Interstate | No | 19-Dec-16 | 11-Jun-17 |
| IIBR-TC370 | PH IIB - MOT Shift New Ramp Alignment - Ramp I4- Interstate | No | 19-Dec-16 | 11-Jun-17 |
| IIBR-TC380 | PH IIB - Set Temp Traffic Barriers (Shoulder) - Ramp L | No | 16-Jan-17 | 11-Jun-17 |
| IIBR-TC390 | PH IIB - Temp Striping New Ramp Alignment - Ramp L | No | 28-Feb-17 | 11-Jun-17 |
| IIBR-TC400 | PH IIB - Set Temp Traffic Barriers (Shoulder) - Ramp U | No | 16-Jan-17 | 11-Jun-17 |
| IIBR-TC410 | PH IIB - Temp Striping New Ramp Alignment - Ramp U | No | 09-Mar-17 | 12-Jun-17 |
| IIBR-TC440 | PH IIB - Temp Striping New Ramp Alignment - Ramp D | No | 10-Apr-17 | 11-Jun-17 |
| IIBR-TC450 | PH IIB - Set Temp Traffic Barriers (Shoulder) - Ramp D | No | 20-Mar-17 | 11-Jun-17 |
| IIBR100 | PH IIB - Construct Ramp E Diversion - Ramp E | No | 07-Dec-16 | 11-Jun-17 |
| IIBR110 | PH IIB - Construct Ramp I-1 Diversion - Ramp I-1 | No | 21-Nov-16 | 11-Jun-17 |
| IIBR120 | PH IIB - Construct Ramp R-1 Diversion - Ramp R-1 | No | 06-Feb-17 | 11-Jun-17 |
| IIBR140 | PH IIB - Construct Ramp R-2 Diversion - Ramps R-2 | No | 06-Feb-17 | 11-Jun-17 |
| IIBR150 | PH IIB - Construct Ramp H Diversion - Ramp H | No | 06-Dec-16 | 11-Jun-17 |
| IIBR151 | PH IIB - Construct Ramp L Diversion - Ramp L | No | 28-Jul-16 | 11-Jun-17 |
| IIBR170 | PH IIB - Construct Ramp U Diversion - Ramp U | No | 04-Jan-17 | 12-Jun-17 |
| IICR-EW100 | PH IIC - Embankment - Ramp S-2 | No | 04-Oct-16 | 13-Jul-17 |
| IICR-TC140 | PH IIC - MOT Shift for New Ramp Alignment - Ramp C | No | 19-Dec-16 | 04-Oct-17 |
| IICR100 | PH IIC - Construct Ramp S-2 Diversion - Ramp S-2 | No | 15-Feb-17 | 11-Jun-17 |
| IIDEBO-ST100 | PH IID - Construct Crane Access - EB Outside Widening (Bridge over John Young PKWY) | No | 29-Feb-16 | 23-Jun-17 |
| IIDEBO-ST120 | PH IID - Temp Sheet Pile - EB Outside Widening (Bridge over John Young PKWY) | No | 18-Mar-16 | 11-Jun-17 |
| IIDEBO-ST130 | PH IID - Production Pile (H Piles) - EB Outside Widening (Bridge over John Young PKWY) | No | 01-Mar-16 | 14-Sep-17 |
| IIDEBO-ST140 | PH IID - Pier 2, 3, 4 (F/R/P) (Footer & Column) - EB Outside Widening (Bridge over John Young PKWY) | No | 18-Mar-16 | 11-Jun-17 |
| IIDEBO-ST150 | PH IID - Curing for Pier 2, 3, 4(Footer, Column & Pier Cap) - EB Outside Widening (Bridge over John Young PKWY) | No | 21-Sep-16 | 16-Oct-17 |
| IIDEBO-ST160 | PH IID - Remove Concrete form for Pier 2, 3, 4(Footer, Column & Pier Cap) - EB Outside Widening (Bridge over JYP) | No | 16-Sep-16 | 16-Oct-17 |
| IIDEBO-ST170 | PH IID - Temp Sheet Pile Removal - EB Outside Widening (Bridge over John Young PKWY) | No | 05-May-16 | 16-Oct-17 |
| IIDEBO-ST310 | PH IID - Pier 2, 3, 4 (F/R/P) ( Pier Cap) - EB Outside Widening (Bridge over John Young PKWY) | No | 08-Jul-16 | 16-Oct-17 |
| IIIAR100 | PH IIIA - Construct Ramp Diversion P - Ramp P (STA 2013+84 to 2005+50) | No | 10-Jan-17 | 11-Jun-17 |
| IIIAWBO-SP100 | PH IIIA - Jack & Bore - WB Outside Widening Area (SR528) | No | 24-Apr-17 | 12-Jun-17 |
| IIIAWBO-ST15 | PH IIIA - Construct Crane Access - WB Outside Widening Area (Bridge 750630 Ramp T over JYP) | No | 12-Jan-16 | 23-Jun-17 |
| IIIAWBO-ST16 | PH IIIA - Test Pile (H Piles) - WB Outside Widening Area (Bridge 750630 Ramp T over JYP) | No | 07-Dec-15 | 11-Jun-17 |
| IIIAWBO-ST17 | PH IIIA - Temp Sheet Pile - WB Outside Widening Area (Bridge 750630 Ramp T over JYP) | No | 05-May-16 | 11-Jun-17 |
| IIIAWBO-ST18 | PH IIIA - Production Pile (H Piles) (1-32) - WB Outside Widening Area (Bridge 750630 Ramp T over JYP) | No | 04-Apr-16 | 11-Jun-17 |
| IIIAWBO-ST19 | PH IIIA - Production Pile (H Piles) (33-65) - WB Outside Widening Area (Bridge 750630 Ramp T over JYP) | No | 13-Apr-16 | 23-Jun-17 |
| IIIAWBO-ST20 | PH IIIA - Pier 2, 3, 4 (F/R/P)(Footer, Column) - WB Outside Widening Area (Bridge 750630 Ramp T over JYP) | No | 08-May-16 | 23-Jun-17 |
| IIIAWBO-ST200 | PH IIIA - Wall Bent 1 - WB Outside Widening Area (Bridge 750630 Ramp T over JYP) | No | 17-Mar-17 | 23-Jun-17 |
| IIIAWBO-ST21 | PH IIIA - Curing for Pier 2, 3, 4 (Footer, Column & Pier Cap) - WB Outside Widening Area (Bridge 750630 Ramp T over JYP) | No | 21-Sep-16 | 23-Jun-17 |
| IIIAWBO-ST22 | PH IIIA - Remove Concrete Form Pier 2, 3, 4 (Footer, Column & Pier Cap) - WB Outside Widening Area (Bridge 750630 Ramp T | No | 16-Sep-16 | 23-Jun-17 |
| IIIAWBO-ST23 | PH IIIA - Temp Sheet Pile Removal - WB Outside Widening Area (Bridge 750630 Ramp T over JYP) | No | 11-Aug-16 | 11-Jun-17 |
| IIIAWBO-ST230 | PH IIIA - End Bent 1 - WB Outside Widening Area (Bridge 750630 Ramp T over JYP) | No | 15-Mar-17 | 23-Jun-17 |
| IIIAWBO-ST27 | PH IIIA - Construct Crane Access - WB Outside Widening Area (Bridge over John Young PKWY) | No | 05-Apr-16 | 23-Jun-17 |
| IIIAWBO-ST290 | PH IIIA - Wall Bent 5 - WB Outside Widening Area (Bridge 750630 Ramp T over JYP) | No | 13-Apr-17 | 23-Jun-17 |
| IIIAWBO-ST30 | PH IIIA - Temp Sheet Pile - WB Outside Widening Area (Bridge over John Young PKWY) | No | 25-May-16 | 23-Jun-17 |
| IIIAWBO-ST31 | PH IIIA - Production Pile (H Piles) - WB Outside Widening Area (Bridge over John Young PKWY) | No | 07-Apr-16 | 11-Jun-17 |
| IIIAWBO-ST32 | PH IIIA - Pier 2, 3, 4 (F/R/P)(Footer, Column) - WB Outside Widening Area (Bridge over John Young PKWY) | No | 26-May-16 | 11-Jun-17 |
| IIIAWBO-ST33 | PH IIIA - Curing of Pier 2, 3, 4 (Footer, Column & Pier Cap) - WB Outside Widening Area (Bridge over John Young PKWY) | No | 21-Sep-16 | 17-Jul-17 |
| IIIAWBO-ST330 | PH IIIA - End Bent 5 - WB Outside Widening Area (Bridge 750630 Ramp T over JYP) | No | 05-Apr-17 | 23-Jun-17 |
| IIIAWBO-ST34 | PH IIIA - Remove Concrete Form for Pier 2, 3, 4(Footer, Column & Pier Cap) - WB Outside Widening Area (Bridge over John | No | 16-Sep-16 | 17-Jul-17 |
| IIIAWBO-ST340 | PH IIIA - Curing for End Bent 5 - WB Outside Widening Area (Bridge 750630 Ramp T over JYP) | No | 19-Apr-17 | 23-Jun-17 |
| IIIAWBO-ST35 | PH IIIA - Temp Sheet Pile Removal - WB Outside Widening Area (Bridge over John Young PKWY) | No | 10-Aug-16 | 17-Jul-17 |
| IIIAWBO-ST410 | PH IIIA - Set Beams - WB Outside Widening Area (Bridge 750630 Ramp T over JYP) | No | 10-May-17 | 23-Jun-17 |
| IIIAWBO-ST420 | PH IIIA - Superstructure Deck SIP & Start Rebar - WB Outside Widening Area (Bridge 750630 Ramp T over JYP) | No | 15-May-17 | 23-Jun-17 |
| IIIAWBO-ST520 | PH IIIA - Superstructure Deck Finish Rebar\Set Screed\ Pour - WB Outside Widening Area (Bridge 750630 Ramp T over JYP) | No | 31-May-17 | 11-Jun-17 |
| IIIAWBO-ST690 | PH IIIA - Pier 2, 3, 4 (F/R/P)(Pier Cap) - WB Outside Widening Area (Bridge 750630 Ramp T over JYP) | No | 15-Aug-16 | 23-Jun-17 |
| IIIAWBO-ST710 | PH IIIA - Pier 2, 3, 4 (F/R/P) (Pier Cap) - WB Outside Widening Area (Bridge over John Young PKWY) | No | 08-Jul-16 | 17-Jul-17 |
| IIIBR-EW120 | PH IIIB - Embankment - Ramp V | No | 18-May-17 | 22-Nov-17 |
| IIIBR-EW140 | PH IIIB - Embankment - Ramp T | No | 28-Dec-15 | 25-Sep-17 |
| IIIBR-GC180 | PH IIIB - Demo - Ramp V | No | 28-Mar-17 | 07-Nov-17 |
| IIIBR-IHM330 | PH IIIB - Install High Mast/Service (10-13) | No | 14-Mar-17 | 30-Jun-17 |
| IIIBR-ITS80 | PH IIIB - Install Conduit/Boxes (JYP to TPK) | No | 18-Jul-16 | 06-Jul-17 |
| IIIBR-SM550 | PH IIIB - Shoulder Mount Light Pole/Service (International to Univ.) (10 EA) | No | 19-Dec-16 | 11-Dec-17 |
| IIIBR-SM600 | PH IIIB - Shoulder Mount Light Pole/Service (JYP to TPK) (20 EA) (A) | No | 17-Oct-16 | 28-Mar-18 |
| IIIBR-SM610 | PH IIIB - Shoulder Mount Light Pole/Service (JYP to TPK) (20 EA) (B) | No | 17-Oct-16 | 13-Apr-18 |
| IIIBR-SM620 | PH IIIB - Shoulder Mount Light Pole/Service (JYP to TPK) (20 EA) (C) | No | 17-Oct-16 | 01-May-18 |
| IIIBR-SP140 | PH IIIB - Drainage (Temp) - Ramp T | No | 19-Dec-16 | 21-Sep-17 |
| IIIBR-TC180 | PH IIIB - Set Temp Traffic Barriers (Shoulder) - Ramp V | No | 19-Apr-17 | 07-Nov-17 |
| IIIBR-TC190 | PH IIIB - Temp Striping New Ramp Alignment - Ramp V | No | 16-Mar-17 | 07-Nov-17 |
| IIIBR120 | PH IIIB - Construct Ramp V Diversion - Ramp V | No | 23-Jan-17 | 14-Sep-17 |
| IIIBR130 | PH IIIB - Construct Ramp K Diversion/Temp Pavement - Ramp K | No | 03-Apr-17 | 14-Sep-17 |
| IIIBWBO-EW100 | PH IIIB - Surcharge/ Embankment 1 - WB Outside Widening Area | No | 01-May-17 | 14-Sep-17 |
| IIIBWBO-EW101 | PH IIIB - Surcharge/ Embankment 2 - WB Outside Widening Area | No | 19-May-17 | 14-Sep-17 |
| IIIBWBO-EW110 | PH IIIB - Embankment (JYP-Universal) - WB Outside Widening Area | No | 16-Nov-15 | 13-Jun-17 |
| IIIBWBO-EW120 | PH IIIB - Embankment (Universal - International) - WB Outside Widening Area | No | 18-Apr-16 | 14-Aug-17 |
| IIIBWBO-EW140 | PH IIIB - Pond Excav/Embank JYP to Universal - WB Outside Widening | No | 19-Sep-16 | 14-Sep-17 |
| IIIBWBO-SP100 | PH IIIB - Drainage (JYP-Universal) - WB Outside Widening Area (SR528) | No | 16-May-16 | 11-Jun-17 |
| IIIBWBO-SP110 | PH IIIB - Drainage (Universal - International) - WB Outside Widening Area (SR528) | No | 07-Mar-16 | 14-Jun-17 |
| IIIBWBO-ST1 | PH IIIB - Construct Crane Access - WB Outside Widening Area (Bridge over International DR) | No | 18-Jul-16 | 11-Jun-17 |
| IIIBWBO-ST10 | PH IIIB - Production Pile - WB Outside Widening Area (Bridge over universal BLVD) | No | 12-Sep-16 | 16-Aug-17 |
| IIIBWBO-ST11 | PH IIIB - Pier 2, (F/R/P)(Footer, Column & Pier Cap) - WB Outside Widening Area (Bridge over Universal BLVD) | No | 01-Nov-16 | 16-Aug-17 |
| IIIBWBO-ST12 | PH IIIB - Curing for Pier 2, (Footer, Column & Pier Cap) - WB Outside Widening Area (Bridge over Universal BLVD) | No | 08-Dec-16 | 21-Aug-17 |
| IIIBWBO-ST13 | PH IIIB - Removal for Concrete Forms for Pier 2, (Footer, Column & Pier Cap) - WB Outside Widening Area (Bridge over Uni | No | 15-Dec-16 | 21-Aug-17 |
| IIIBWBO-ST14 | PH IIIB - Temp Sheet Pile Removal - WB Outside Widening Area (Bridge over universal BLVD) | No | 16-Dec-16 | 11-Jun-17 |
| IIIBWBO-ST3 | PH IIIB - Temp Sheet Pile - WB Outside Widening Area (Bridge over International DR) | No | 27-Jun-16 | 11-Jun-17 |
| IIIBWBO-ST4 | PH IIIB - Production Pile - WB Outside Widening Area (Bridge over International DR) | No | 01-May-16 | 11-Jun-17 |
| IIIBWBO-ST5 | PH IIIB - Pier 2, (F/R/P)(Footer, Column & Pier Cap) - WB Outside Widening Area (Bridge over International DR) | No | 28-Jun-16 | 18-Sep-17 |
| IIIBWBO-ST6 | PH IIIB - Construct Crane Access - WB Outside Widening Area (Bridge over universal BLVD) | No | 15-Aug-16 | 11-Aug-17 |
| IIIBWBO-ST7 | PH IIIB - Test Pile - WB Outside Widening Area (Bridge over universal BLVD) | No | 08-Sep-16 | 11-Jun-17 |
| IIIBWBO-ST8 | PH IIIB - Temp Sheet Pile - WB Outside Widening Area (Bridge over universal BLVD) | No | 28-Oct-16 | 11-Aug-17 |
| IIIBWBO-ST9 | PH IIIB - Temp Sheet Pile Removal - WB Outside Widening Area (Bridge over International DR) | No | 27-Jul-16 | 26-Sep-17 |
| IIICR-EW100 | PH IIIC - Embankment - Ramp F | No | 05-Apr-16 | 29-Dec-17 |
| PRE-FA-001 | Fabricate and Deliver 506 Bridge Drainage System | No | 25-Jan-17 | 11-Jun-17 |
| PRE-FA-00123 | Fabricate and Deliver 455 Structure Foundations Prestressed Concrete Piling 18" (Structures 750089 & 750216) | No | 15-Feb-16 | 11-Jun-17 |
| PRE-FA-00132 | Fabricate and Deliver 455 Structure Foundations Prestressed Concrete Piling 24" (Structure 750631-Shingle Creek) | No | 21-Oct-15 | 11-Jun-17 |
| PRE-FA-00145 | Fabricate and Deliver 455 Structure Foundations Steel Pile HP 14X89 (Structures 750088 and 750215 I-Drive) | No | 15-Feb-16 | 11-Jun-17 |
| PRE-FA-00147 | Fabricate and Deliver 455 Structure Foundations Steel Pile HP 12X53 (Structure 750629-Ramp S JYP) | No | 17-Jan-16 | 11-Jun-17 |
| PRE-FA-00154 | Fabricate and Deliver 455 Structure Foundations Steel Pile HP 12X53 (Structures 750091 and 750218-JYP) | No | 16-Nov-15 | 11-Jun-17 |
| PRE-FA-00174 | Fabricate and Deliver 455 Structure Foundations Steel Pile HP 12X53 (Structure 750630-Ramp T JYP) | No | 16-Nov-15 | 11-Jun-17 |
| PRE-FA-007 | Fabricate and Deliver 400 Concrete Structures (Bearing Pads) | No | 09-Mar-16 | 11-Jun-17 |
| PRE-FA-008 | Fabricate and Deliver 450 Precast Prestressed Florida I Beam 36" (Structures 750088 & 750215- I-Drive) | No | 21-Feb-16 | 11-Jun-17 |
| PRE-FA-009 | Fabricate and Deliver 450 Precast Prestressed Florida I Beam 45" (Structures 750089, & 750216- Universal/Orangewood) | No | 21-Feb-16 | 11-Jun-17 |
| PRE-FA-010 | Fabricate and Deliver 450 Precast Prestressed Beams TY II (Structures 750631-Shingle Creek) | No | 21-Feb-16 | 11-Jun-17 |
| PRE-FA-011 | Fabricate and Deliver 450 Precast Prestressed Florida I Beam 36" (Structures 750091 & 750218- JYP) | No | 21-Feb-16 | 11-Jun-17 |
| PRE-FA-0111 | Fabricate and Deliver 455 Temp Sheet Pile/Critical | No | 26-Jan-16 | 11-Jun-17 |
| PRE-FA-012 | Fabricate and Deliver 450 Precast Prestressed Florida I Beam 36" (Structures 750629 Ramp S JYP & 750630 Ramp T JYP) | No | 21-Feb-16 | 11-Jun-17 |
| PRE-FA-013 | Fabricate and Deliver 455 Auger Cast Piles (w/noise wall submittal) | No | 26-Jan-16 | 11-Jun-17 |
| PRE-FA-014 | Fabricate and Deliver 534 Noise and Perimeter Walls | No | 01-Feb-16 | 11-Jun-17 |
| PRE-FA-015 | Fabricate and Deliver 548 Retaining/MSE Wall Systems | No | 18-Jul-16 | 11-Jun-17 |
| PRE-FA-016 | Fabricate and Deliver 641 Prestressed Concrete Poles | No | 22-Aug-16 | 11-Jun-17 |
| PRE-FA-019 | Fabricate and Deliver 700 Highway Signing (Single, Multi, Panel, and Overhead) | No | 09-Mar-17 | 11-Jun-17 |
| PRE-FA-021 | Fabricate and Deliver 05500 Metal Fabrications | No | 20-Mar-17 | 11-Jun-17 |
| PRE-FA-022 | Fabricate and Deliver 133420 Pre-Engineered Precast Concrete Structure | No | 27-Feb-17 | 11-Jun-17 |
| PRE-FA-023 | Fabricate and Deliver 263213 Engine Generator | No | 22-May-17 | 11-Jun-17 |
| PRE-FA-024 | Fabricate and Deliver 633 Communication Cable | No | 22-Aug-16 | 11-Jun-17 |
| PRE-FA-025 | Fabricate and Deliver 635 Pull, Splice, & Junction Boxes | No | 22-Aug-16 | 11-Jun-17 |
| PRE-FA-029 | Fabricate and Deliver 033000 Cast-In-Place Concrete | No | 15-May-17 | 11-Jun-17 |
| PRE-FA-031 | Fabricate and Deliver 081100 Metal Doors and Frames | No | 16-Jan-17 | 11-Jun-17 |
| PRE-FA-032 | Fabricate and Deliver 099100 Painting Product Data and Sample | No | 16-Jan-17 | 11-Jun-17 |
| PRE-FA-034 | Fabricate and Deliver 231113 Fuel Oil Piping | No | 05-May-17 | 11-Jun-17 |
| PRE-FA-035 | Fabricate and Deliver 231323 Aboveground Diesel Storage Tank and Piping | No | 05-May-17 | 11-Jun-17 |
| PRE-FA-036 | Fabricate and Deliver 232000 Piping and Specialties | No | 25-Jan-17 | 11-Jun-17 |
| PRE-FA-037 | Fabricate and Deliver 233113 Ductwork Product Data and Shop Drawing | No | 22-May-17 | 11-Jun-17 |
| PRE-FA-038 | Fabricate and Deliver 238119 Packaged Air Conditioners | No | 17-Jan-17 | 11-Jun-17 |
| PRE-FA-039 | Fabricate and Deliver 260536 Cable Trays | No | 09-Feb-17 | 11-Jun-17 |
| PRE-FA-040 | Fabricate and Deliver 264113 Lighting Protection System Product Data and Shop Drawing | No | 19-Apr-17 | 11-Jun-17 |
| PRE-FA-041 | Fabricate and Deliver 682 CCTV Camera | No | 22-Aug-16 | 11-Jun-17 |
| PRE-FA-042 | Fabricate and Deliver 781 DMS | No | 18-May-17 | 11-Jun-17 |
| PRE-FA-044 | Fabricate and Deliver 783 ITS Fiber Optic Cable | No | 22-Aug-16 | 11-Jun-17 |
| PRE-FA-046 | Fabricate and Deliver 784 ITS Managed Ethernet Hub Switch | No | 22-Aug-16 | 11-Jun-17 |
| PRE-FA-047 | Fabricate and Deliver 685 ITS Uninterruptible Power Source (UPS) | No | 22-Aug-16 | 11-Jun-17 |
| PRE-FA-049 | Fabricate and Deliver 262913 ITS Standby Generator Product Data and Shop Drawing | No | 22-Aug-16 | 11-Jun-17 |
| PRE-FA-050 | Fabricate and Deliver 400 Concrete Structures (SIP Metal Forms) | No | 14-Dec-15 | 11-Jun-17 |
| PRE-PS-001 | Prepare and Submit 506 Bridge Drainage System | No | 08-Aug-16 | 11-Jun-17 |
| PRE-PS-002 | Prepare and Submit 455 Pile Installation Plan (Structures 750089 & 750216-Universal/Orangewood) | No | 20-Sep-15 | 11-Jun-17 |
| PRE-PS-003 | Prepare and Submit 455 Pile Installation Plan (Structures 750091 & 750218-John Young Parkway) | No | 20-Sep-15 | 11-Jun-17 |
| PRE-PS-004 | Prepare and Submit 455 Pile Installation Plan (Structure 750629- Ramp S JYP) | No | 20-Sep-15 | 11-Jun-17 |
| PRE-PS-005 | Prepare and Submit 455 Pile Installation Plan (Structure 750630- Ramp T JYP) | No | 20-Sep-15 | 11-Jun-17 |
| PRE-PS-006 | Prepare and Submit Precast Erection | No | 03-Jun-16 | 11-Jun-17 |
| PRE-PS-007 | Prepare and Submit 400 Concrete Structures (Bearing Pads) | No | 11-Jan-16 | 11-Jun-17 |
| PRE-PS-008 | Prepare and Submit 450 Precast Prestressed Florida I Beam 36" (Structures 750088 & 750215- I-Drive) | No | 01-Oct-15 | 11-Jun-17 |
| PRE-PS-009 | Prepare and Submit 450 Precast Prestressed Florida I Beam 45" (Structures 750089, & 750216- Universal/Orangewood) | No | 01-Oct-15 | 11-Jun-17 |
| PRE-PS-010 | Prepare and Submit 450 Precast Prestressed Beams TY II (Structures 750631-Shingle Creek) | No | 01-Oct-15 | 11-Jun-17 |
| PRE-PS-011 | Prepare and Submit 450 Precast Prestressed Florida I Beam 36" (Structures 750091 & 750218- JYP) | No | 01-Oct-15 | 11-Jun-17 |
| PRE-PS-012 | Prepare and Submit 450 Precast Prestressed Florida I Beam 36" (Structures 750629 Ramp S JYP & 750630 Ramp T JYP) | No | 20-Sep-15 | 11-Jun-17 |
| PRE-PS-013 | Prepare and Submit 455 Auger Cast Piles (w/noise wall submittal) | No | 07-Oct-15 | 11-Jun-17 |
| PRE-PS-014 | Prepare and Submit 534 Noise and Perimeter Walls | No | 21-Oct-15 | 11-Jun-17 |
| PRE-PS-015 | Prepare and Submit 548 Retaining/MSE Wall Systems | No | 17-Apr-16 | 11-Jun-17 |
| PRE-PS-016 | Prepare and Submit 641 Prestressed Concrete Poles | No | 15-Feb-16 | 11-Jun-17 |
| PRE-PS-017 | Prepare and Submit 646 Aluminum Pedestal Poles | No | 20-Mar-17 | 11-Jun-17 |
| PRE-PS-018 | Prepare and Submit 650 Traffic Signals | No | 15-Feb-16 | 11-Jun-17 |
| PRE-PS-019 | Prepare and Submit 700 Highway Signing (Single, Multi, Panel, and Overhead) | No | 11-Jan-16 | 11-Jun-17 |
| PRE-PS-021 | Prepare and Submit 05500 Metal Fabrications | No | 16-May-16 | 11-Jun-17 |
| PRE-PS-022 | Prepare and Submit 133420 Pre-Engineered Precast Concrete Structure | No | 03-Jun-16 | 11-Jun-17 |
| PRE-PS-023 | Prepare and Submit 263213 Engine Generator | No | 18-Nov-16 | 11-Jun-17 |
| PRE-PS-024 | Prepare and Submit 633 Communication Cable | No | 15-Feb-16 | 11-Jun-17 |
| PRE-PS-025 | Prepare and Submit 635 Pull, Splice, & Junction Boxes | No | 18-Jan-16 | 11-Jun-17 |
| PRE-PS-026 | Prepare and Submit 653 Pedestrian Signals | No | 20-Mar-17 | 11-Jun-17 |
| PRE-PS-027 | Prepare and Submit 663 Signal Priority and Preemption Systems | No | 28-Jan-16 | 11-Jun-17 |
| PRE-PS-028 | Prepare and Submit 665 Pedestrian Detector | No | 20-Mar-17 | 11-Jun-17 |
| PRE-PS-029 | Prepare and Submit 033000 Cast-In-Place Concrete | No | 26-Sep-16 | 11-Jun-17 |
| PRE-PS-030 | Prepare and Submit 042200 Masonry | No | 20-Feb-17 | 11-Jun-17 |
| PRE-PS-031 | Prepare and Submit 081100 Metal Doors and Frames | No | 19-Oct-16 | 11-Jun-17 |
| PRE-PS-032 | Prepare and Submit 099100 Painting Product Data and Sample | No | 19-Oct-16 | 11-Jun-17 |
| PRE-PS-033 | Prepare and Submit 101400 Signage | No | 27-Feb-17 | 11-Jun-17 |
| PRE-PS-034 | Prepare and Submit 231113 Fuel Oil Piping | No | 13-Feb-17 | 11-Jun-17 |
| PRE-PS-035 | Prepare and Submit 231323 Aboveground Diesel Storage Tank and Piping | No | 13-Feb-17 | 11-Jun-17 |
| PRE-PS-036 | Prepare and Submit 232000 Piping and Specialties | No | 16-Jan-17 | 11-Jun-17 |
| PRE-PS-037 | Prepare and Submit 233113 Ductwork Product Data and Shop Drawing | No | 20-Feb-17 | 11-Jun-17 |
| PRE-PS-038 | Prepare and Submit 238119 Packaged Air Conditioners | No | 09-Jan-17 | 11-Jun-17 |
| PRE-PS-039 | Prepare and Submit 260536 Cable Trays | No | 16-Jan-17 | 11-Jun-17 |
| PRE-PS-040 | Prepare and Submit 264113 Lighting Protection System Product Data and Shop Drawing | No | 20-Mar-17 | 11-Jun-17 |
| PRE-PS-041 | Prepare and Submit 682 CCTV Camera | No | 01-Aug-16 | 11-Jun-17 |
| PRE-PS-042 | Prepare and Submit 781 DMS | No | 22-Aug-16 | 11-Jun-17 |
| PRE-PS-044 | Prepare and Submit 783 ITS Fiber Optic Cable | No | 08-Feb-16 | 11-Jun-17 |
| PRE-PS-045 | Prepare and Submit 660 ITS Vehicle Detection System | No | 01-Aug-16 | 11-Jun-17 |
| PRE-PS-046 | Prepare and Submit 684 ITS Managed Ethernet Hub Switch | No | 01-Aug-16 | 11-Jun-17 |
| PRE-PS-047 | Prepare and Submit 785 ITS Uninterruptible Power Source (UPS) | No | 01-Aug-16 | 11-Jun-17 |
| PRE-PS-049 | Prepare and Submit 639 ITS Standby Generator Product Data and Shop Drawing | No | 21-Mar-16 | 11-Jun-17 |
| PRE-PS-050 | Prepare and Submit 400 Concrete Structures (SIP Metal Forms) | No | 20-Sep-15 | 11-Jun-17 |
| PRE-RA-001 | Review and Approve 506 Bridge Drainage System | No | 19-Jan-17 | 11-Jun-17 |
| PRE-RA-002 | Review and Approve 455 Pile Installation Plan (Structures 750089 & 750216-Universal/Orangewood) | No | 27-Sep-15 | 11-Jun-17 |
| PRE-RA-003 | Review and Approve 455 Pile Installation Plan (Structures 750091 & 750218-John Young Parkway) | No | 27-Sep-15 | 11-Jun-17 |
| PRE-RA-004 | Review and Approve 455 Pile Installation Plan (Structure 750629- Ramp S JYP) | No | 27-Sep-15 | 11-Jun-17 |
| PRE-RA-005 | Review and Approve 455 Pile Installation Plan (Structure 750630- Ramp T JYP) | No | 27-Sep-15 | 11-Jun-17 |
| PRE-RA-007 | Review and Approve 400 Concrete Structures (Bearing Pads) | No | 02-Mar-16 | 11-Jun-17 |
| PRE-RA-008 | Review and Approve 450 Precast Prestressed Florida I Beam 36" (Structures 750088 & 750215- I-Drive) | No | 18-Oct-15 | 11-Jun-17 |
| PRE-RA-009 | Review and Approve 450 Precast Prestressed Florida I Beam 45" (Structures 750089, & 750216- Universal/Orangewood) | No | 18-Oct-15 | 11-Jun-17 |
| PRE-RA-010 | Review and Approve 450 Precast Prestressed Beams TY II (Structures 750631-Shingle Creek) | No | 18-Oct-15 | 11-Jun-17 |
| PRE-RA-011 | Review and Approve 450 Precast Prestressed Florida I Beam 36" (Structures 750091 & 750218- JYP) | No | 18-Oct-15 | 11-Jun-17 |
| PRE-RA-012 | Review and Approve 450 Precast Prestressed Florida I Beam 36" (Structures 750629 Ramp S JYP & 750630 Ramp T JYP) | No | 18-Oct-15 | 11-Jun-17 |
| PRE-RA-013 | Review and Approve 455 Auger Cast Piles (w/noise wall submittal) | No | 21-Oct-15 | 11-Jun-17 |
| PRE-RA-014 | Review and Approve 534 Noise and Perimeter Walls | No | 21-Oct-15 | 11-Jun-17 |
| PRE-RA-015 | Review and Approve 548 Retaining/MSE Wall Systems | No | 29-Apr-16 | 11-Jun-17 |
| PRE-RA-016 | Review and Approve 641 Prestressed Concrete Poles | No | 16-Feb-16 | 11-Jun-17 |
| PRE-RA-017 | Review and Approve 646 Aluminum Pedestal Poles | No | 23-Mar-17 | 11-Jun-17 |
| PRE-RA-018 | Review and Approve 650 Traffic Signals | No | 23-Mar-17 | 24-Jun-17 |
| PRE-RA-019 | Review and Approve 700 Highway Signing (Single, Multi, Panel, and Overhead) | No | 18-Jan-16 | 11-Jun-17 |
| PRE-RA-021 | Review and Approve 05500 Metal Fabrications | No | 08-Jun-16 | 11-Jun-17 |
| PRE-RA-022 | Review and Approve 133420 Pre-Engineered Precast Concrete Structure | No | 12-Jan-17 | 11-Jun-17 |
| PRE-RA-023 | Review and Approve 263213 Engine Generator | No | 01-Feb-17 | 11-Jun-17 |
| PRE-RA-024 | Review and Approve 633 Communication Cable | No | 16-Feb-16 | 11-Jun-17 |
| PRE-RA-025 | Review and Approve 635 Pull, Splice, & Junction Boxes | No | 16-Feb-16 | 11-Jun-17 |
| PRE-RA-026 | Review and Approve 653 Pedestrian Signals | No | 23-Mar-17 | 11-Jun-17 |
| PRE-RA-027 | Review and Approve 663 Signal Priority and Preemption Systems | No | 16-Feb-16 | 15-Jun-17 |
| PRE-RA-028 | Review and Approve 665 Pedestrian Detector | No | 23-Mar-17 | 11-Jun-17 |
| PRE-RA-029 | Review and Approve 033000 Cast-In-Place Concrete | No | 26-Oct-16 | 11-Jun-17 |
| PRE-RA-031 | Review and Approve 081100 Metal Doors and Frames | No | 26-Oct-16 | 11-Jun-17 |
| PRE-RA-032 | Review and Approve 099100 Painting Product Data and Sample | No | 26-Oct-16 | 11-Jun-17 |
| PRE-RA-033 | Review and Approve 101400 Signage | No | 29-Mar-17 | 11-Jun-17 |
| PRE-RA-034 | Review and Approve 231113 Fuel Oil Piping | No | 21-Apr-17 | 11-Jun-17 |
| PRE-RA-035 | Review and Approve 231323 Aboveground Diesel Storage Tank and Piping | No | 28-Mar-17 | 11-Jun-17 |
| PRE-RA-036 | Review and Approve 232000 Piping and Specialties | No | 18-Jan-17 | 11-Jun-17 |
| PRE-RA-037 | Review and Approve 233113 Ductwork Product Data and Shop Drawing | No | 22-May-17 | 11-Jun-17 |
| PRE-RA-038 | Review and Approve 238119 Packaged Air Conditioners | No | 12-Jan-17 | 11-Jun-17 |
| PRE-RA-039 | Review and Approve 260536 Cable Trays | No | 18-Jan-17 | 11-Jun-17 |
| PRE-RA-040 | Review and Approve 264113 Lighting Protection System Product Data and Shop Drawing | No | 28-Mar-17 | 11-Jun-17 |
| PRE-RA-041 | Review and Approve 682 CCTV Camera | No | 03-Aug-16 | 11-Jun-17 |
| PRE-RA-042 | Review and Approve 781 DMS | No | 25-Aug-16 | 11-Jun-17 |
| PRE-RA-044 | Review and Approve 633 ITS Fiber Optic Cable | No | 26-Jul-16 | 11-Jun-17 |
| PRE-RA-045 | Review and Approve 660 ITS Vehicle Detection System | No | 03-Aug-16 | 11-Jun-17 |
| PRE-RA-046 | Review and Approve 684 ITS Managed Ethernet Hub Switch | No | 03-Aug-16 | 11-Jun-17 |
| PRE-RA-047 | Review and Approve 685 ITS Uninterruptible Power Source (UPS) | No | 03-Aug-16 | 11-Jun-17 |
| PRE-RA-049 | Review and Approve 639 ITS Standby Generator Product Data and Shop Drawing | No | 30-Mar-16 | 11-Jun-17 |
| PRE-RA-050 | Review and Approve 400 Concrete Structures (SIP Metal Forms) | No | 30-Nov-15 | 11-Jun-17 |
| TF-CO-003 | Begin Electrical (Stub Outs & Site Electrical) | No | 23-May-17 | 11-Jun-17 |
| TF-CO-005 | Install Upright 2 D.S. | No | 22-Mar-17 | 11-Jun-17 |
| TF-CO-007 | Install Upright 3 D.S. | No | 24-Mar-17 | 11-Jun-17 |
| TF-CO-011 | AS Build D.S. | No | 30-Mar-17 | 11-Jun-17 |
| TF-FA-001 | Fabricate and Deliver Precast Erection | No | 30-Jan-17 | 11-Jun-17 |
| TF-RA-001 | Review and Approve Precast Erection | No | 12-Jan-17 | 11-Jun-17 |
| USATT-CO-001 | ATT Florida | No | 29-Oct-15 | 11-Jun-17 |
| USB-CO-001 | Bright house | No | 27-Oct-15 | 11-Jun-17 |
| USDED-CO-001 | Duke Energy Distribution (A) | No | 01-Dec-15 | 11-Jun-17 |
| USDED-CO-002 | Duke Energy Distribution (B) | No | 30-Nov-15 | 11-Jun-17 |
| USDET-CO-001 | Duke Energy Transmission Phase 1 | No | 12-Oct-15 | 11-Jun-17 |
| USOUC-CO-001 | OUC Remove Water Main @ JYP (Sta 325 - 329) | No | 29-Oct-15 | 11-Jun-17 |
| USS-CO-001 | Summit | No | 29-Oct-15 | 11-Jun-17 |
| UST-CO-001 | TECO | No | 07-Dec-15 | 11-Jun-17 |
| USV-CO-001 | Verizon | No | 07-Dec-15 | 11-Jun-17 |
This table lists activities with non-zero relationship lag, highlighting the intentional or unintentional delays (or overlaps) between tasks.
Lag reflects the gap between a predecessor and its successor, and it may be contributing to scheduling bottlenecks.
Highlighted in red are activities with negative lag - meaning the successor
is scheduled to start before the predecessor has finished. This can be intentional, to optimize parallel work, or unintentional, which might result in resource conflicts
or quality issues. In either case, monitoring negative lag is crucial for identifying potential risks and ensuring the project schedule remains realistic and achievable
| Activity ID | Activity Description | On LP | Relationship Type | Predecessor Activity ID | Predecessor Activity Description | Relationship Lag |
|---|---|---|---|---|---|---|
| IVEBM-TC120 | PH IV - MOT Shift for Phase - EB Median Widening | No | SS | IVEBM-TC110 | PH IV - Temp Striping for Phase - EB Median Widening | 1 |
This table lists the calendars, their weekly schedule and holidays used in the project and any default calendars. Calendars are essential for resource allocation, as they define working days, holidays, and other time-related constraints.
Highlighted in green are project default and global/base default calendars, if any.
Highlighted in red are calendars that are not used by any activity. This situation may indicate that the calendar is obsolete or not relevant to the current project schedule. It is important to review these calendars and determine if they should be removed or updated to reflect the current project requirements.
Recommended actions: Review the calendars listed in this table and ensure that they are relevant and up-to-date. Remove any obsolete calendars and update the project schedule to reflect the current working days and holidays.
| ID | Scope | Default | Linked Activities | Name | Last updated |
|---|---|---|---|---|---|
| 9959 | Base | No | 90 | 5 day FDOT with Holiday | 22-Aug-16 |
| 1559 | Base | No | - | 5 day FDOT with Holidays | 18-May-13 |
| 8489 | Base | No | - | Standard 7-Day Workweek | 19-Sep-16 |
| 21490 | Project | Yes | 836 | Beachline 5-days with Holidays | 15-Dec-15 |
| 21489 | Project | No | 197 | Beachline 7-Day Workweek | 15-Dec-15 |
| 21491 | Project | No | 89 | Beachline Night-Shift 5-Days with Holidays | 15-Dec-15 |
1559: 5 day FDOT with Holidays
Day Hours: 8, Week Hours: 40, Month Hours: 172, Year Hours: 2024
There are non-working days going back prior to 01-Jan-2020. You should consider migrating to a newer calendar.
Weekly Schedule
| Day | Time Slots |
|---|---|
| Sun | No Work |
| Mon | 08:00-12:00, 13:00-17:00 |
| Tue | 08:00-12:00, 13:00-17:00 |
| Wed | 08:00-12:00, 13:00-17:00 |
| Thu | 08:00-12:00, 13:00-17:00 |
| Fri | 08:00-12:00, 13:00-17:00 |
| Sat | No Work |
Holidays and No Work days
| Day | Holiday |
|---|---|
| 01-Jan-20 | New Year's Day |
| 25-May-20 | Memorial Day |
| 03-Jul-20 | - |
| 07-Sep-20 | Labor Day |
| 26-Nov-20 | Thanksgiving Day |
| 27-Nov-20 | - |
| 25-Dec-20 | Christmas Day |
| 01-Jan-21 | New Year's Day |
8489: Standard 7-Day Workweek
Day Hours: 8, Week Hours: 56, Month Hours: 172, Year Hours: 2000
There are non-working days going back prior to 01-Jan-2020. You should consider migrating to a newer calendar.
Weekly Schedule
| Day | Time Slots |
|---|---|
| Sun | 08:00-16:00 |
| Mon | 08:00-16:00 |
| Tue | 08:00-16:00 |
| Wed | 08:00-16:00 |
| Thu | 08:00-16:00 |
| Fri | 08:00-16:00 |
| Sat | 08:00-16:00 |
Holidays and No Work days
9959: 5 day FDOT with Holiday
Day Hours: 8, Week Hours: 40, Month Hours: 172, Year Hours: 2024
There are non-working days going back prior to 01-Jan-2020. You should consider migrating to a newer calendar.
Weekly Schedule
| Day | Time Slots |
|---|---|
| Sun | No Work |
| Mon | 08:00-12:00, 13:00-17:00 |
| Tue | 08:00-12:00, 13:00-17:00 |
| Wed | 08:00-12:00, 13:00-17:00 |
| Thu | 08:00-12:00, 13:00-17:00 |
| Fri | 08:00-12:00, 13:00-17:00 |
| Sat | No Work |
Holidays and No Work days
| Day | Holiday |
|---|---|
| 01-Jan-20 | New Year's Day |
| 20-Jan-20 | Martin Luther King Jr. Day |
| 25-May-20 | Memorial Day |
| 03-Jul-20 | - |
| 07-Sep-20 | Labor Day |
| 11-Nov-20 | Veterans Day |
| 26-Nov-20 | Thanksgiving Day |
| 27-Nov-20 | - |
| 25-Dec-20 | Christmas Day |
| 01-Jan-21 | New Year's Day |
21489: Beachline 7-Day Workweek
Day Hours: 8, Week Hours: 56, Month Hours: 172, Year Hours: 2000
Weekly Schedule
| Day | Time Slots |
|---|---|
| Sun | 08:00-16:00 |
| Mon | 08:00-16:00 |
| Tue | 08:00-16:00 |
| Wed | 08:00-16:00 |
| Thu | 08:00-16:00 |
| Fri | 08:00-16:00 |
| Sat | 08:00-16:00 |
Holidays and No Work days
21490: Beachline 5-days with Holidays
Day Hours: 8, Week Hours: 40, Month Hours: 172, Year Hours: 2024
There are non-working days going back prior to 01-Jan-2020. You should consider migrating to a newer calendar.
Weekly Schedule
| Day | Time Slots |
|---|---|
| Sun | No Work |
| Mon | 08:00-12:00, 13:00-17:00 |
| Tue | 08:00-12:00, 13:00-17:00 |
| Wed | 08:00-12:00, 13:00-17:00 |
| Thu | 08:00-12:00, 13:00-17:00 |
| Fri | 08:00-12:00, 13:00-17:00 |
| Sat | No Work |
Holidays and No Work days
| Day | Holiday |
|---|---|
| 01-Jan-20 | New Year's Day |
| 20-Jan-20 | Martin Luther King Jr. Day |
| 25-May-20 | Memorial Day |
| 03-Jul-20 | - |
| 07-Sep-20 | Labor Day |
| 11-Nov-20 | Veterans Day |
| 26-Nov-20 | Thanksgiving Day |
| 27-Nov-20 | - |
| 25-Dec-20 | Christmas Day |
| 01-Jan-21 | New Year's Day |
21491: Beachline Night-Shift 5-Days with Holidays
Day Hours: 8, Week Hours: 40, Month Hours: 172, Year Hours: 2024
There are non-working days going back prior to 01-Jan-2020. You should consider migrating to a newer calendar.
Weekly Schedule
| Day | Time Slots |
|---|---|
| Sun | No Work |
| Mon | 00:00-06:00, 22:00-00:00 |
| Tue | 00:00-06:00, 22:00-00:00 |
| Wed | 00:00-06:00, 22:00-00:00 |
| Thu | 00:00-06:00, 22:00-00:00 |
| Fri | 00:00-06:00, 22:00-00:00 |
| Sat | No Work |
Holidays and No Work days
| Day | Holiday |
|---|---|
| 01-Jan-20 | New Year's Day |
| 20-Jan-20 | Martin Luther King Jr. Day |
| 25-May-20 | Memorial Day |
| 03-Jul-20 | - |
| 07-Sep-20 | Labor Day |
| 11-Nov-20 | Veterans Day |
| 26-Nov-20 | Thanksgiving Day |
| 27-Nov-20 | - |
| 25-Dec-20 | Christmas Day |
| 01-Jan-21 | New Year's Day |
Each row represents a unique resource and summarizes how it is being utilized across activities.
Highlighted in red are resources that P6 will not allow you to assign tasks to
(i.e. those not cost‑linked or not auto‑compute‑active).
The Assignable in P6 column shows "Yes" for resources P6 treats as assignable and "No" for those it hides.
| Type | ID | Name | Assigned Activities | Assignable in P6 |
|---|---|---|---|---|
| Labor | Asphalt | Asphalt team | 71 | Yes |
| Labor | Base | Road base team | 81 | Yes |
| Labor | Carr | Carr | 24 | Yes |
| Labor | CIF | CIF | 2 | Yes |
| Labor | Concrete | Concrete team | 254 | Yes |
| Labor | Demo | Demo Team | 72 | Yes |
| Labor | Drainage | Drainage team | 54 | Yes |
| Labor | Electrical | Electrical team | 16 | Yes |
| Labor | Embankment | Embankment | 58 | Yes |
| Labor | Excavation | Excavation team | 23 | Yes |
| Labor | JVD | JVD | 23 | Yes |
| Labor | MOT | Traffic Control Team | 107 | Yes |
| Labor | Paff | Paff | 26 | Yes |
| Labor | Pile | Pile team | 64 | Yes |
| Labor | Slagter | Slagter | 26 | Yes |
| Labor | Stabilization | Stabilization team | 69 | Yes |
| Labor | US&S | US & S | 101 | Yes |
| Mat | TPKCO | TPK COST | 1041 | Yes |
This report compares each resource's scheduled workload against their available capacity on a month-by-month basis. We calculate capacity using each resource's work
calendar (their working days and hours), shift schedules, and defined production or labor rates. Remaining activity work is then spread across the months that the
activity is scheduled to run. Whenever the total assigned units in a given month exceed the resource's calculated capacity, that resource is flagged as overallocated.
Demand is the total work assigned to a resource in a month.
Limit is that resource's available capacity.
Overage is the actual resource overallocation - the amount by which Demand exceeds Limit.
Resource overallocation can lead to missed deadlines, reduced quality, and team burnout. By clearly highlighting these overbooked periods, this report helps you take
corrective action: adjust task start or finish dates, redistribute work to less-busy teams, extend deadlines, or bring in additional support.
| Resource ID | Resource Name | Month | Demand | Limit | Overage | Activities |
|---|---|---|---|---|---|---|
| Asphalt | Asphalt team | Jun-2017 | 468 | 176 | 292 | IBEBM-RW330 = 60, IBWBM-RW220 = 45, IBWBM-RW230 = 50, IIAR-AP100 = 20, IIBEBO-AP140 = 200, IIBR-AP110 = 20, IIBR-AP151 = 10, IICR-SP130 = 53, IIIAWBO-AP100 = 10 |
| Jul-2017 | 398 | 168 | 230 | IBR-AP110 = 50, IIBEBO-AP130 = 200, IIBR-AP130 = 20, IIBR-AP140 = 20, IIBR-AP150 = 20, IIBR-AP170 = 20, IIBR-AP180 = 1, IICR-AP100 = 20, IICR-SP130 = 47 | ||
| Aug-2017 | 195 | 184 | 11 | IIBEBO-AP120 = 175, IICR-AP120 = 20 | ||
| Sep-2017 | 235 | 168 | 67 | IIBEBO-AP110 = 200, IIBEBO-AP120 = 25, IIBR-AP120 = 10 | ||
| Oct-2017 | 596 | 176 | 420 | IIBR-AP100 = 40, IIBR-AP120 = 30, IIDEBO-RW150 = 143, IIIBR-AP100 = 20, IIIBR-AP140 = 20, IIIBR-AP150 = 20, IIICR130 = 83, IIICR170 = 40, IIICR180 = 200 | ||
| Nov-2017 | 434 | 176 | 258 | IIDEBO-RW150 = 78, IIIBWBO-AP100 = 80, IIICR130 = 117, IIICR170 = 160 | ||
| Dec-2017 | 610 | 168 | 442 | IIIBR-AP110 = 20, IIIBR-AP120 = 20, IIIBWBO-AP100 = 20, IIICR110 = 150, IIICR140 = 200, IIICR200 = 200 | ||
| Jan-2018 | 567 | 184 | 383 | IIIBR-AP130 = 20, IIIBR-AP160 = 20, IIICR-AP100 = 20, IIICR110 = 50, IIICR120 = 107, IIICR160 = 150, IIICR190 = 200 | ||
| Feb-2018 | 317 | 160 | 157 | IIIBWBO-AP110 = 100, IIICR-AP110 = 20, IIICR120 = 93, IIICR150 = 53, IIICR160 = 50 | ||
| Aug-2018 | 310 | 184 | 126 | IVEBM-AP100 = 30, IVEBO-AP100 = 80, IVEBO-PM110 = 50, IVWBM-AP100 = 40, IVWBO-AP100 = 60, IVWBO-PM110 = 50 | ||
| Carr | Carr | Jun-2017 | 534 | 176 | 358 | IIBR-ITS10 = 70, IIBR-ITS20 = 40, IIBR-ITS30 = 20, IIBR-ITS40 = 4, IIIBR-ITS1000 = 200, IIIBR-ITS1010 = 100, IIIBR-ITS1020 = 100 |
| Jul-2017 | 356 | 168 | 188 | IIBR-ITS40 = 6, IIBR-ITS50 = 90, IIIBR-ITS1010 = 100, IIIBR-ITS1020 = 100, IIIBR-ITS80 = 60 | ||
| Aug-2017 | 230 | 184 | 46 | IIBR-ITS50 = 110, IIBR-ITS60 = 120 | ||
| Sep-2017 | 200 | 168 | 32 | IIBR-ITS60 = 80, IIIBR-ITS90 = 120 | ||
| Oct-2017 | 255 | 176 | 79 | IIBR-ITS70 = 175, IIIBR-ITS90 = 80 | ||
| Nov-2017 | 285 | 176 | 109 | IIBR-ITS70 = 25, IIBR-ITS80 = 200, IIBR-ITS90 = 60 | ||
| Dec-2017 | 280 | 168 | 112 | IIBR-ITS90 = 140, IIIBR-ITS100 = 140 | ||
| Feb-2018 | 200 | 160 | 40 | IIIBR-ITS110 = 100, IIIBR-ITS130 = 100 | ||
| Mar-2018 | 220 | 176 | 44 | IIIBR-ITS130 = 100, IIIBR-ITS140 = 120 | ||
| Apr-2018 | 210 | 168 | 42 | IIIBR-ITS140 = 80, IIIBR-ITS150 = 100, IIIBR-ITS160 = 30 | ||
| May-2018 | 230 | 184 | 46 | IIIBR-ITS160 = 70, IIIBR-ITS170 = 100, IIIBR-ITS180 = 60 | ||
| Jun-2018 | 200 | 168 | 32 | IIIBR-ITS180 = 40, IIIBR-ITS190 = 160 | ||
| Concrete | Concrete team | Jun-2017 | 475 | 176 | 299 | IIBEBO-ST140 = 70, IIBEBO-ST160 = 10, IIBEBO-ST360 = 50, IIBEBO-ST400 = 20, IIBEBO-ST420 = 40, IIBEBO-ST440 = 100, IIBEBO-ST730 = 40, IIIAWBO-ST520 = 15, IIIAWBO-ST570 = 40, IIIAWBO-ST580 = 40, IIIAWBO-ST700 = 50 |
| Jul-2017 | 816 | 168 | 648 | IIBEBO-ST160 = 60, IIBEBO-ST190 = 70, IIBEBO-ST200 = 70, IIBEBO-ST480 = 18, IIBEBO-ST500 = 150, IIBEBO-ST520 = 8, IIBEBO-ST730 = 30, IIBEBO-W130 = 150, IIIAWBO-ST111 = 50, IIIAWBO-ST120 = 50, IIIAWBO-ST570 = 60, IIIAWBO-ST580 = 60, IIIAWBO-ST620 = 40 | ||
| Aug-2017 | 833 | 184 | 649 | IIBEBO-ST250 = 18, IIBEBO-ST270 = 113, IIBEBO-ST520 = 33, IIBEBO-ST530 = 50, IIBEBO-ST540 = 50, IIBEBO-ST570 = 10, IIBEBO-ST580 = 30, IIBEBO-ST720 = 70, IIBEBO-W140 = 210, IIIAWBO-ST120 = 50, IIIAWBO-ST130 = 50, IIIAWBO-ST140 = 100, IIIAWBO-ST170 = 30, IIIBWBO-ST220 = 20 | ||
| Sep-2017 | 1162 | 168 | 994 | IIBEBO-ST270 = 88, IIBEBO-ST330 = 50, IIBEBO-ST340 = 40, IIBEBO-ST390 = 30, IIBEBO-W140 = 10, IIBEBO-W150 = 190, IIIAWBO-ST150 = 27, IIIAWBO-ST160 = 113, IIIAWBO-ST170 = 40, IIIBWBO-ST220 = 30, IIIBWBO-ST240 = 50, IIIBWBO-ST260 = 50, IIIBWBO-ST270 = 45, IIIBWBO-ST28 = 60, IIIBWBO-ST300 = 50, IIIBWBO-ST330 = 30, IIIBWBO-ST370 = 60, IIIBWBO-ST750 = 150, IIIBWBO-W101 = 20, IIIBWBO-W110 = 30 | ||
| Oct-2017 | 1621 | 176 | 1445 | IIBEBO-W150 = 30, IIDEBO-ST190 = 50, IIDEBO-ST200 = 50, IIDEBO-ST210 = 20, IIIAWBO-ST160 = 108, IIIAWBO-ST171 = 50, IIIAWBO-ST181 = 100, IIIAWBO-ST211 = 40, IIIBWBO-ST211 = 70, IIIBWBO-ST250 = 70, IIIBWBO-ST270 = 105, IIIBWBO-ST28 = 140, IIIBWBO-ST280 = 40, IIIBWBO-ST320 = 70, IIIBWBO-ST330 = 40, IIIBWBO-ST340 = 18, IIIBWBO-ST350 = 120, IIIBWBO-ST360 = 10, IIIBWBO-ST370 = 20, IIIBWBO-ST400 = 150, IIIBWBO-ST430 = 50, IIIBWBO-W101 = 80, IIIBWBO-W110 = 190 | ||
| Nov-2017 | 854 | 176 | 678 | IIDEBO-ST210 = 30, IIDEBO-ST220 = 50, IIDEBO-ST230 = 18, IIDEBO-ST240 = 15, IIDEBO-ST340 = 70, IIIBWBO-ST100 = 135, IIIBWBO-ST280 = 30, IIIBWBO-ST310 = 70, IIIBWBO-ST350 = 80, IIIBWBO-ST380 = 18, IIIBWBO-ST390 = 8, IIIBWBO-ST410 = 70, IIIBWBO-ST430 = 30, IIIBWBO-ST480 = 160, IIIBWBO-W111 = 70 | ||
| Dec-2017 | 783 | 168 | 615 | IIDEBO-ST240 = 135, IIDEBO-ST330 = 60, IIIBWBO-ST100 = 15, IIIBWBO-ST390 = 193, IIIBWBO-ST440 = 50, IIIBWBO-ST450 = 80, IIIBWBO-ST510 = 30, IIIBWBO-ST520 = 70, IIIBWBO-ST560 = 120, IIIBWBO-ST610 = 23, IIIBWBO-ST690 = 8 | ||
| Jan-2018 | 650 | 184 | 466 | IIDEBO-ST250 = 60, IIDEBO-ST260 = 50, IIDEBO-ST290 = 30, IIDEBO-ST330 = 90, IIIBWBO-ST490 = 50, IIIBWBO-ST500 = 20, IIIBWBO-ST610 = 178, IIIBWBO-ST690 = 143, IIIBWBO-ST700 = 30 | ||
| Feb-2018 | 250 | 160 | 90 | IIIBWBO-ST120 = 90, IIIBWBO-ST500 = 10, IIIBWBO-ST550 = 30, IIIBWBO-ST700 = 120 | ||
| Apr-2018 | 210 | 168 | 42 | IVEBM-W150 = 100, IVEBM-W160 = 50, IVEBM-W170 = 60 | ||
| May-2018 | 220 | 184 | 36 | IVEBM-W180 = 150, IVEBM-W190 = 50, IVEBM-W200 = 20 | ||
| Jun-2018 | 210 | 168 | 42 | IVEBM-W200 = 80, IVEBM-W210 = 100, IVEBM-W220 = 30 | ||
| Demo | Demo Team | Jun-2017 | 290 | 176 | 114 | IBR-GC100 = 150, IIBR-GC140 = 20, IIIBWBO-GC100 = 80, IIICWBO-ST100 = 40 |
| Jul-2017 | 340 | 168 | 172 | IIBR-GC100 = 80, IIBR-GC170 = 100, IICR-GC100 = 20, IICR-GC170 = 20, IIIBWBO-GC100 = 20, IIICWBO-ST220 = 100 | ||
| Aug-2017 | 373 | 184 | 189 | IIDEBO-ST180 = 40, IIDEBO-ST300 = 20, IIIBWBO-ST180 = 20, IIIBWBO-ST190 = 80, IIIBWBO-ST640 = 50, IIIBWBO-ST650 = 80, IIIBWBO-ST660 = 50, IIIBWBO-ST670 = 33 | ||
| Sep-2017 | 457 | 168 | 289 | IIDEBO-ST300 = 80, IIDEBO-ST320 = 120, IIIBR-GC100 = 20, IIIBR-GC210 = 20, IIIBR-GC250 = 20, IIIBWBO-ST171 = 20, IIIBWBO-ST631 = 10, IIIBWBO-ST670 = 17, IIIBWBO-ST680 = 150 | ||
| Drainage | Drainage team | Jun-2017 | 754 | 176 | 578 | IBWBM-RW111 = 25, IIBEBO-SP100 = 150, IIBEBO-SP120 = 20, IIBEBO-SP160 = 200, IIBR-SP130 = 100, IIBR-SP210 = 30, IIBR-SP240 = 100, IIIBWBO-SP110 = 99, IIIBWBO-SP120 = 30 |
| Jul-2017 | 680 | 168 | 512 | IIBEBO-SP100 = 50, IIBEBO-SP130 = 160, IIBEBO-SP140 = 80, IIBR-SP100 = 50, IIBR-SP150 = 60, IICR-SP100 = 50, IICR-SP120 = 60, IIIBWBO-SP120 = 170 | ||
| Aug-2017 | 730 | 184 | 546 | IIBR-SP100 = 50, IIBR-SP150 = 40, IICR-SP120 = 40, IIIBWBO-SP130 = 200, IIIBWBO-SP140 = 200, IIIBWBO-SP150 = 200 | ||
| Sep-2017 | 380 | 168 | 212 | IIIBR-SP100 = 100, IIIBR-SP150 = 80, IIIBWBO-SP160 = 200 | ||
| Dec-2017 | 300 | 168 | 132 | IIIBR-SP130 = 100, IIIBR-SP160 = 100, IIICR-SP100 = 100 | ||
| Apr-2018 | 260 | 168 | 92 | IVEBM-SP100 = 130, IVWBM-SP100 = 130 | ||
| Embankment | Embankment | Aug-2017 | 575 | 184 | 391 | IIBR-EW100 = 220, IIBR-EW140 = 200, IIIBWBO-EW110 = 75, IIIBWBO-EW130 = 80 |
| Jun-2017 | 453 | 176 | 277 | IBR-EW100 = 220, IIBEBO-EW100 = 150, IIBR-EW130 = 3, IIBR-EW150 = 30, IIBR-EW210 = 30, IIIAWBO-ST24 = 20 | ||
| Sep-2017 | 245 | 168 | 77 | IIIBWBO-EW101 = 45, IIIBWBO-EW102 = 80, IIIBWBO-EW130 = 120 | ||
| Oct-2017 | 463 | 176 | 287 | IIDEBO-RW150 = 143, IIIBR-EW100 = 50, IIIBR-EW150 = 50, IIIBWBO-EW102 = 90, IIIBWBO-EW103 = 130 | ||
| Pile | Pile team | Jun-2017 | 180 | 176 | 4 | IIBEBO-ST2 = 30, IIBEBO-W100 = 150 |
| Jul-2017 | 200 | 168 | 32 | IIBEBO-W110 = 150, IIBEBO-W120 = 50 | ||
| Sep-2017 | 250 | 168 | 82 | IIIBWBO-ST2 = 30, IIIBWBO-ST26 = 100, IIIBWBO-W100 = 120 | ||
| Oct-2017 | 220 | 176 | 44 | IIIBWBO-W100 = 30, IIIBWBO-W120 = 150, IIIBWBO-W130 = 40 | ||
| Base | Road base team | Jun-2017 | 1292 | 176 | 1116 | IBR-RW110 = 165, IIAR-RW110 = 20, IIBR-RW130 = 80, IIBR-RW190 = 30, IIBR-RW220 = 50, IIBR-RW310 = 30, IIBR-RW320 = 30, IIBR120 = 10, IICR-SP130 = 107, IICR100 = 150, IICR120 = 140, IIIAR100 = 30, IIIBR100 = 150, IIIBR110 = 150, IIICR100 = 150 |
| Jul-2017 | 688 | 168 | 520 | IBR-RW110 = 55, IIBR-RW170 = 80, IIBR-RW190 = 50, IIBR-RW220 = 30, IIBR-RW250 = 80, IICR-RW110 = 80, IICR-SP130 = 93, IICR100 = 10, IICR120 = 60, IIIBR100 = 50, IIIBR110 = 50, IIICR100 = 50 | ||
| Aug-2017 | 395 | 184 | 211 | IIBEBO-RW120 = 80, IIBR-RW110 = 5, IIBR-RW160 = 30, IICR-RW140 = 80, IIIAR120 = 200 | ||
| Sep-2017 | 495 | 168 | 327 | IIBEBM-GC110 = 20, IIBEBO-RW120 = 140, IIBR-RW110 = 15, IIBR-RW160 = 190, IIBR-RW280 = 50, IIBR-RW290 = 10, IIIAR110 = 60, IIIBR-RW190 = 10 | ||
| Oct-2017 | 996 | 176 | 820 | IIBEBM-GC110 = 10, IIBR-RW280 = 50, IIBR-RW290 = 140, IIDEBO-RW150 = 143, IIIBR-RW110 = 80, IIIBR-RW190 = 70, IIIBR-RW210 = 80, IIIBWBO-RW140 = 100, IIICR130 = 83, IIICR170 = 40, IIICR180 = 200 | ||
| Nov-2017 | 464 | 176 | 288 | IIDEBO-RW150 = 78, IIIBR-RW130 = 80, IIIBR-RW150 = 30, IIICR130 = 117, IIICR170 = 160 | ||
| Dec-2017 | 660 | 168 | 492 | IIIBR-RW150 = 50, IIIBR-RW230 = 30, IIIBWBM-GC110 = 30, IIICR110 = 150, IIICR140 = 200, IIICR200 = 200 | ||
| Jan-2018 | 777 | 184 | 593 | IIIBR-GC380 = 60, IIIBR-RW170 = 80, IIIBR-RW230 = 50, IIICR-RW110 = 80, IIICR110 = 50, IIICR120 = 107, IIICR160 = 150, IIICR190 = 200 | ||
| Feb-2018 | 317 | 160 | 157 | IIIBR-GC380 = 40, IIICR-RW130 = 80, IIICR120 = 93, IIICR150 = 53, IIICR160 = 50 | ||
| Slagter | Slagter | Oct-2017 | 283 | 176 | 107 | IIBR-GC160 = 80, IIDEBO-RW150 = 143, IIIBR-GC120 = 20, IIIBR-GC290 = 20, IIIBR-GC320 = 20 |
| Stabilization | Stabilization team | Jun-2017 | 681 | 176 | 505 | IBEBM-RW111 = 25, IBEBM-RW320 = 45, IBR-RW100 = 120, IIBEBO-RW112 = 110, IIBEBO-RW140 = 160, IIBEBO-RW160 = 60, IIBEBO-RW180 = 48, IIBR-RW120 = 20, IIBR-RW180 = 20, IIBR-RW200 = 20, IICR-SP130 = 53 |
| Jul-2017 | 322 | 168 | 154 | IIBEBO-RW110 = 70, IIBEBO-RW111 = 55, IIBEBO-RW130 = 90, IIBR-RW150 = 20, IIBR-RW240 = 20, IICR-RW100 = 20, IICR-SP130 = 47 | ||
| Aug-2017 | 480 | 184 | 296 | IIBEBO-RW110 = 150, IIBEBO-RW130 = 60, IIBEBO-RW150 = 70, IIBR-RW100 = 60, IIBR-RW140 = 120, IICR-RW150 = 20 | ||
| Sep-2017 | 280 | 168 | 112 | IIIBR-RW180 = 20, IIIBWBO-RW100 = 120, IIIBWBO-RW110 = 120, IIIBWBO-RW120 = 20 | ||
| Oct-2017 | 663 | 176 | 487 | IIDEBO-RW150 = 143, IIIBR-RW100 = 20, IIIBR-RW200 = 20, IIIBWBO-RW100 = 80, IIIBWBO-RW110 = 80, IIIBWBO-RW120 = 180, IIIBWBO-RW150 = 100, IIIBWBO-RW160 = 40 | ||
| Nov-2017 | 178 | 176 | 2 | IIDEBO-RW150 = 78, IIIBR-RW120 = 20, IIIBR-RW140 = 20, IIIBWBO-RW160 = 60 | ||
| Jul-2018 | 300 | 176 | 124 | IVWBM-RW140 = 40, IVWBM-RW150 = 90, IVWBM-RW260 = 50, IVWBM-RW270 = 40, IVWBM-RW280 = 80 | ||
| MOT | Traffic Control Team | Jun-2017 | 290 | 176 | 114 | IICR-TC1000 = 10, IICR-TC130 = 10, IICR-TC160 = 10, IICR-TC170 = 100, IICR-TC180 = 10, IICR-TC200 = 10, IICR-TC210 = 10, IIIAWBO-TC100 = 10, IIIAWBO-TC110 = 10, IIIAWBO-TC120 = 10, IIIAWBO-TC130 = 30, IIIBWBO-TC110 = 30, IIIBWBO-TC120 = 40 |
| Jul-2017 | 275 | 168 | 107 | IBEBM-TC220 = 173, IIBEBO-ST480 = 12, IIBR-TC160 = 30, IIBR-TC170 = 10, IIBR-TC270 = 10, IICR-TC1020 = 10, IICR-TC120 = 10, IIIBR-TC120 = 10, IIIBR-TC130 = 10 | ||
| Aug-2017 | 269 | 184 | 85 | IBEBM-TC220 = 27, IIAR-TC120 = 120, IIAR-TC130 = 90, IIBEBO-ST250 = 12, IICR-TC150 = 10, IICR-TC190 = 10 | ||
| Sep-2017 | 263 | 168 | 95 | IIAR-TC120 = 80, IIAR-TC130 = 110, IIIAWBO-ST150 = 13, IIIBR-TC160 = 10, IIIBR-TC170 = 10, IIIBR-TC220 = 10, IIIBR-TC230 = 10, IIIBR-TC250 = 10, IIIBR-TC260 = 10 | ||
| Nov-2017 | 194 | 176 | 18 | IIDEBO-ST230 = 12, IIIBR-TC270 = 10, IIIBR-TC280 = 10, IIIBR140 = 150, IIIBWBO-ST380 = 12 | ||
| US&S | US & S | Jun-2017 | 757 | 176 | 581 | IBR-IHM300 = 25, IIBR-EC10 = 30, IIBR-EHM360 = 10, IIBR-IB10 = 30, IIBR-IDS30 = 42, IIBR-IHM310 = 60, IIBR-IHM320 = 60, IIBR-SM380 = 130, IIIBR-EC20 = 60, IIIBR-IHM330 = 10, TF-CO-001 = 150, TF-CO-003 = 50, TF-CO-008 = 100 |
| Oct-2017 | 1290 | 176 | 1114 | IIBR-SM470 = 30, IIBR-SM480 = 30, IIBR-SM490 = 160, IIIBR-ET40 = 40, IIIBR-RES130 = 180, IIIBR-SM520 = 70, IIIBR-SM530 = 150, IVR-ET50 = 180, IVR-SM660 = 10, TF-CO-006 = 50, TF-CO-009 = 170, TF-CO-025 = 70, TF-CO-029 = 150 | ||
| Sep-2017 | 945 | 168 | 777 | IIBR-SM430 = 30, IIBR-SM440 = 54, IIBR-SM450 = 57, IIBR-SM460 = 54, IIIBR-ET40 = 120, IIIBR-IDS40 = 60, IIIBR-SM510 = 150, IIIBR-SM520 = 20, TF-CO-004 = 100, TF-CO-006 = 100, TF-CO-023 = 50, TF-CO-025 = 150 | ||
| Jul-2017 | 850 | 168 | 682 | IIBEBO-IE20 = 100, IIBR-CP10 = 60, IIBR-EHM360 = 170, IIBR-EHM370 = 30, IIBR-IB10 = 20, IIBR-IB180 = 150, IIBR-SM380 = 10, IIBR-SM390 = 80, IIBR-SM400 = 80, IIBR-SM410 = 30, IIIBR-IHM330 = 50, TF-CO-001 = 70 | ||
| Aug-2017 | 510 | 184 | 326 | IIBR-CP10 = 40, IIBR-EHM370 = 90, IIBR-IB180 = 50, IIBR-SM410 = 50, IIBR-SM420 = 140, IIBR-SM430 = 40, TF-CO-004 = 100 | ||
| Dec-2017 | 1020 | 168 | 852 | IIIBR-SM540 = 30, IIIBR-SM550 = 70, IIIBR-SM560 = 80, IVR-SM670 = 20, IVR-SM680 = 160, TF-CO-013 = 60, TF-CO-014 = 150, TF-CO-015 = 150, TF-CO-018 = 150, TF-CO-019 = 150 | ||
| Nov-2017 | 970 | 176 | 794 | IIBR-SM490 = 40, IIBR-SM500 = 100, IIIBR-SM530 = 50, IIIBR-SM540 = 170, IVR-ET60 = 140, IVR-SM660 = 70, IVR-SM670 = 140, TF-CO-009 = 50, TF-CO-012 = 100, TF-CO-013 = 40, TF-CO-029 = 70 | ||
| Mar-2018 | 1040 | 176 | 864 | IIIBR-SM580 = 70, IIIBR-SM590 = 120, IIIBR-SM600 = 30, IVEBO-SS100 = 100, IVR-EC30 = 60, IVR-IPM70 = 200, IVR-IPM80 = 20, IVR-RES140 = 60, IVWBO-SS100 = 100, TF-CO-016 = 60, TF-CO-017 = 60, TF-CO-024 = 160 | ||
| Apr-2018 | 1340 | 168 | 1172 | IIIBR-SM600 = 90, IIIBR-SM610 = 120, IVEBO-SS100 = 100, IVR-IPM100 = 40, IVR-IPM80 = 180, IVR-IPM90 = 200, IVWBO-SS100 = 100, TF-CO-024 = 60, TF-CO-026 = 150, TF-CO-027 = 150, TF-CO-028 = 150 | ||
| Jan-2018 | 920 | 184 | 736 | IIIBR-CP10 = 90, IIIBR-CP170 = 50, IIIBR-SM560 = 30, IIIBR-SM570 = 140, IIIC-AP170 = 80, IIIC-CP10 = 80, IVR-SM690 = 180, TF-CO-010 = 30, TF-CO-018 = 70, TF-CO-019 = 70, TF-CO-020 = 100 | ||
| May-2018 | 830 | 184 | 646 | IIIBR-IBM110 = 40, IIIBR-SM620 = 120, IIIBR-SM630 = 110, IVR-IPM100 = 160, TF-CO-026 = 70, TF-CO-027 = 100, TF-CO-028 = 100, TF-CO-030 = 130 | ||
| Feb-2018 | 1080 | 160 | 920 | IIIBR-CP10 = 10, IIIBR-SM570 = 60, IIIBR-SM580 = 130, IIIC-AP170 = 120, IIIC-CP10 = 120, IVR-SM690 = 20, IVR-SM700 = 160, TF-CO-010 = 40, TF-CO-016 = 160, TF-CO-017 = 160, TF-CO-021 = 50, TF-CO-022 = 50 | ||
| Jun-2018 | 400 | 168 | 232 | IIIBR-SM630 = 90, IIIBR-SM640 = 90, IIIBR-SM650 = 20, TF-CO-030 = 90, TF-CO-031 = 110 | ||
| Jul-2018 | 340 | 176 | 164 | IIIBR-SM650 = 180, TF-CO-031 = 110, TF-CO-032 = 50 |
Lists project milestones, grouped by their WBS sequence and name, showing only those with negative float.
Highlighted in red are milestones with negative total or free float which means
they are either behind their own finish dates or blocking downstream tasks, and therefore pose a risk to the overall project timeline.
Recommended actions:
- Check for conflicting constraints or deadlines on these milestones.
- Validate predecessor/successor links to ensure logic is correct.
- Adjust sequencing or resource assignments as needed, then re‐run the schedule to confirm the float values return to zero or positive.
| WBS Seq: Name | Milestone ID | Milestone Name | Type | Status | Target Start | Target Finish | Actual Start | Actual Finish | Total Float | Free Float |
|---|---|---|---|---|---|---|---|---|---|---|
| 0: General | GC-GCN160 | PH MS - Start Phase IV Construction | Start | Not Started | 16-Mar-18 | 16-Mar-18 | -11 | 0 | ||
| GC-GC110 | PH MS - Substantial Completion | Finish | Not Started | 25-Aug-18 | 25-Aug-18 | -5 | 12 | |||
| 4: Maintenance of Traffic | GC-DP110 | PH MS - Project Completion | Finish | Not Started | 05-Sep-18 | 05-Sep-18 | -17 | 0 |
Lists project milestones, grouped by their WBS sequence and name.
Highlighted in red are milestones with negative total or free float which means
they are either behind their own finish dates or blocking downstream tasks, and therefore pose a risk to the overall project timeline.
Recommended actions:
- Check for conflicting constraints or deadlines on these milestones.
- Validate predecessor/successor links to ensure logic is correct.
- Adjust sequencing or resource assignments as needed, then re‐run the schedule to confirm the float values return to zero or positive.
| WBS Seq: Name | Milestone ID | Milestone Name | Type | Status | Target Start | Target Finish | Actual Start | Actual Finish | Total Float | Free Float |
|---|---|---|---|---|---|---|---|---|---|---|
| 0: General | GC-DP100 | PH MS - NTP | Start | Completed | 14-Nov-15 | 14-Nov-15 | 19-Aug-15 | 19-Aug-15 | 0 | 0 |
| GC-GCN110 | PH MS - Start Phase IA Construction | Start | Completed | 14-Nov-15 | 14-Nov-15 | 20-Sep-15 | 20-Sep-15 | 0 | 0 | |
| GC-GCN120 | PH MS - Start Phase IB Construction | Start | Completed | 20-Nov-15 | 20-Nov-15 | 20-Nov-15 | 20-Nov-15 | 0 | 0 | |
| GC-GC100 | PH MS - NTP2 - Start Construction (35 days from NTP 1= Contract date ) | Start | Completed | 16-Dec-15 | 16-Dec-15 | 20-Sep-15 | 20-Sep-15 | 0 | 0 | |
| GC-GCN130 | PH MS - Start Phase IIA Construction | Start | Completed | 17-Oct-16 | 17-Oct-16 | 19-Sep-16 | 19-Sep-16 | 0 | 0 | |
| GC-GCN140 | PH MS - Start Phase IIB Construction | Start | Completed | 04-Jan-17 | 04-Jan-17 | 04-Oct-16 | 04-Oct-16 | 0 | 0 | |
| GC-GCN150 | PH MS - Start Phase IIC Construction | Start | Not Started | 12-Jun-17 | 12-Jun-17 | 40 | 0 | |||
| GC-GCN200 | PH MS - Start Phase IIIA Construction | Start | Not Started | 12-Jun-17 | 12-Jun-17 | 20 | 0 | |||
| GC-GCN190 | PH MS - Start Phase IID Construction | Start | Not Started | 24-Aug-17 | 24-Aug-17 | 21 | 0 | |||
| GC-GCN170 | PH MS - Start Phase IIIB Construction | Start | Not Started | 14-Sep-17 | 14-Sep-17 | 1 | 0 | |||
| GC-GCN180 | PH MS - Start Phase IIIC Construction | Start | Not Started | 11-Dec-17 | 11-Dec-17 | 1 | 0 | |||
| GC-GCN160 | PH MS - Start Phase IV Construction | Start | Not Started | 16-Mar-18 | 16-Mar-18 | -11 | 0 | |||
| GC-GC110 | PH MS - Substantial Completion | Finish | Not Started | 25-Aug-18 | 25-Aug-18 | -5 | 12 | |||
| 4: Maintenance of Traffic | GC-DP110 | PH MS - Project Completion | Finish | Not Started | 05-Sep-18 | 05-Sep-18 | -17 | 0 |
This report gives you a single view of all open WBS elements with remaining work and planned vs. actual dates, so you can immediately spot unfinished or slipped tasks. It flags at-risk items, validates your logic and constraints, and shows exactly how much effort remains (in hours or percent).
| WBS Seq: Name | Remaining Work, days | Target Start | Target Finish | Actual Start | Actual Finish |
|---|---|---|---|---|---|
| 0: General | 3089 | 19-Aug-15 | 05-Sep-18 | 19-Aug-15 | 09-Jun-17 |
| 1: SPS &CPS Wall | 113 | 12-Jun-17 | 16-Nov-17 | ||
| 1: Retaining Walls | 145 | 18-Apr-16 | 05-Jul-18 | 11-May-16 | 25-Apr-17 |
| 1: MSE Walls | 83 | 17-May-16 | 26-Oct-17 | 06-Jun-16 | 27-Jul-16 |
| 1: Exc Ponds | 18 | 14-Dec-15 | 09-Oct-17 | 26-Oct-15 | 16-Jan-17 |
| 1: Embankment & Exc Road | 246 | 14-Dec-15 | 06-Feb-18 | 05-Oct-15 | 19-May-17 |
| 1: Misc Demo | 96 | 27-Jan-16 | 28-Mar-18 | 26-Oct-15 | 01-May-17 |
| 1: Barrier Wall (MOT) | 261 | 29-Oct-15 | 21-Mar-18 | 21-Oct-15 | 22-May-17 |
| 1: Temporary signs & Barricades | 1 | 16-Nov-15 | 12-Jun-17 | 20-Sep-15 | 03-Oct-16 |
| 4: Maintenance of Traffic | 1 | 16-Dec-15 | 05-Sep-18 | 08-Oct-15 | 09-Sep-16 |
| 7: Site Preparation & Access | 9 | 05-Nov-15 | 20-Jun-17 | 05-Nov-15 | 22-Aug-16 |
| 8: Drainage | 449 | 17-Feb-16 | 18-Apr-18 | 06-Jan-16 | 08-Jun-17 |
| 10: Walls | 94 | 05-Apr-16 | 01-Feb-18 | 16-Feb-16 | 04-May-17 |
| 10: Demo (Bridge) | 131 | 14-Dec-15 | 16-Oct-17 | 22-Nov-15 | 11-May-17 |
| 10: Foundations | 27 | 14-Dec-15 | 23-Oct-17 | 20-Nov-15 | 02-Jun-17 |
| 11: (MOT) Structural Pavement | 1 | 17-Apr-17 | 13-Jun-17 | 29-Mar-17 | 06-Apr-17 |
| 13: (MOT) Pavement Markings | 1 | 13-Jan-16 | 20-Jun-17 | 27-Sep-15 | 01-Dec-15 |
| 14: Toll Facility | 564 | 31-Mar-17 | 23-Aug-18 | 20-Mar-17 | 31-Mar-17 |
| 101: Substructure | 93 | 08-Mar-16 | 30-Oct-17 | 29-Jan-16 | 17-Mar-17 |
| 101: Walls (Abutm & Wing) | 228 | 05-May-16 | 08-Dec-17 | 18-Apr-16 | 07-Jun-17 |
| 201: Superstructure | 287 | 23-May-16 | 16-Feb-18 | 23-May-16 | 30-May-17 |
| 301: Approach Slabs | 66 | 06-Jul-16 | 05-Mar-18 | 13-Jul-16 | 10-May-17 |
| 400: Beachline Update#20 DD June 11 TD June 15 | 175 | 12-Jun-17 | 16-Feb-18 | ||
| 401: Imbeded Facilities (Electrical, Communications) | 13 | 20-Jan-17 | 06-Mar-18 | 26-Jan-17 | 18-May-17 |
| 501: Railing walls | 34 | 01-Aug-16 | 09-Mar-18 | 04-Aug-16 | 20-May-17 |
| 601: Finishes & Misc | 34 | 04-Aug-16 | 15-Mar-18 | 03-Aug-16 | 09-Jun-17 |
Successful Tests (no errors, changes, or issues)
- Activities with Future Actual Dates
- Activities with Constraint
Back Project Costs
The figures in this report should not be relied upon, excercise caution and double-check the values. This is merely a preview of a work-in-progress feature.
This table represents monthly project costs.
| Month | Actual | Actual Cumul | Remaining Early | Remaining Early Cumul | Remaining Late | Remaining Late Cumul | |
|---|---|---|---|---|---|---|---|
| Aug-2015 | $5,537,599.61 | $5,537,599.61 | 0 | 0 | 0 | 0 | |
| Sep-2015 | $2,445,696.60 | $7,983,296.21 | 0 | 0 | 0 | 0 | |
| Oct-2015 | $3,171,096.91 | $11,154,393.12 | 0 | 0 | 0 | 0 | |
| Nov-2015 | $1,372,651.15 | $12,527,044.27 | 0 | 0 | 0 | 0 | |
| Dec-2015 | $1,093,149.68 | $13,620,193.95 | 0 | 0 | 0 | 0 | |
| Jan-2016 | $666,775.56 | $14,286,969.51 | 0 | 0 | 0 | 0 | |
| Feb-2016 | $1,000,323.64 | $15,287,293.15 | 0 | 0 | 0 | 0 | |
| Mar-2016 | $662,043.51 | $15,949,336.65 | 0 | 0 | 0 | 0 | |
| Apr-2016 | $689,435.13 | $16,638,771.78 | 0 | 0 | 0 | 0 | |
| May-2016 | $1,853,885.53 | $18,492,657.31 | 0 | 0 | 0 | 0 | |
| Jun-2016 | $2,101,471.48 | $20,594,128.79 | 0 | 0 | 0 | 0 | |
| Jul-2016 | $2,719,063.08 | $23,313,191.87 | 0 | 0 | 0 | 0 | |
| Aug-2016 | $1,619,326.51 | $24,932,518.39 | 0 | 0 | 0 | 0 | |
| Sep-2016 | $1,429,111.36 | $26,361,629.75 | 0 | 0 | 0 | 0 | |
| Oct-2016 | $1,245,161.83 | $27,606,791.59 | 0 | 0 | 0 | 0 | |
| Nov-2016 | $1,131,474.20 | $28,738,265.79 | 0 | 0 | 0 | 0 | |
| Dec-2016 | $3,630,160.50 | $32,368,426.28 | 0 | 0 | 0 | 0 | |
| Jan-2017 | $2,489,504.53 | $34,857,930.81 | 0 | 0 | 0 | 0 | |
| Feb-2017 | $2,351,203.14 | $37,209,133.95 | 0 | 0 | 0 | 0 | |
| Mar-2017 | $3,060,488.40 | $40,269,622.36 | 0 | 0 | 0 | 0 | |
| Apr-2017 | $2,079,382.07 | $42,349,004.42 | 0 | 0 | 0 | 0 | |
| May-2017 | $2,150,416.80 | $44,499,421.22 | 0 | 0 | $274,448.75 | $274,448.75 | |
| Jun-2017 | $807,088.73 | $45,306,509.95 | $6,314,001.15 | $6,314,001.15 | $1,492,428.50 | $1,766,877.26 | |
| Jul-2017 | 0 | 0 | $6,391,443.98 | $12,705,445.13 | $3,555,290.11 | $5,322,167.37 | |
| Aug-2017 | 0 | 0 | $4,410,405.59 | $17,115,850.72 | $4,708,404.90 | $10,030,572.27 | |
| Sep-2017 | 0 | 0 | $4,441,268.62 | $21,557,119.34 | $6,203,475.49 | $16,234,047.76 | |
| Oct-2017 | 0 | 0 | $6,303,210.34 | $27,860,329.68 | $3,430,737.24 | $19,664,785.00 | |
| Nov-2017 | 0 | 0 | $2,884,771.37 | $30,745,101.05 | $2,365,848.94 | $22,030,633.94 | |
| Dec-2017 | 0 | 0 | $3,187,722.49 | $33,932,823.54 | $4,348,599.06 | $26,379,232.99 | |
| Jan-2018 | 0 | 0 | $3,175,803.69 | $37,108,627.23 | $3,105,211.28 | $29,484,444.27 | |
| Feb-2018 | 0 | 0 | $2,006,503.17 | $39,115,130.40 | $7,032,683.90 | $36,517,128.17 | |
| Mar-2018 | 0 | 0 | $1,873,781.02 | $40,988,911.41 | $1,038,265.12 | $37,555,393.29 | |
| Apr-2018 | 0 | 0 | $1,505,955.76 | $42,494,867.17 | $1,000,871.36 | $38,556,264.66 | |
| May-2018 | 0 | 0 | $1,015,198.89 | $43,510,066.06 | $1,237,041.24 | $39,793,305.89 | |
| Jun-2018 | 0 | 0 | $776,140.79 | $44,286,206.85 | $2,046,014.28 | $41,839,320.17 | |
| Jul-2018 | 0 | 0 | $684,180.17 | $44,970,387.03 | $3,816,513.83 | $45,655,834.00 | |
| Aug-2018 | 0 | 0 | $2,414,153.45 | $47,384,540.48 | $1,801,005.32 | $47,456,839.33 | |
| Sep-2018 | 0 | 0 | $72,298.85 | $47,456,839.33 | 0 | $47,456,839.33 |